Hammond-Mitchell, Inc. v. Construction Materials Co.

77 Va. Cir. 5, 2008 Va. Cir. LEXIS 126
CourtAlleghany County Circuit Court
DecidedApril 28, 2008
DocketCase No. CL05000082-00
StatusPublished

This text of 77 Va. Cir. 5 (Hammond-Mitchell, Inc. v. Construction Materials Co.) is published on Counsel Stack Legal Research, covering Alleghany County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hammond-Mitchell, Inc. v. Construction Materials Co., 77 Va. Cir. 5, 2008 Va. Cir. LEXIS 126 (Va. Super. Ct. 2008).

Opinion

By Judge Malfourd W. Trumbo

Hammond-Mitchell, Inc. (hereinafter referred to as “HMI”) contracted with Construction Materials Company (hereinafter referred to as “ConRock”), to supply HMI with 16 yards of 4000 psi for a bridge’s foundation at MeadWestvaco. The concrete was delivered as ordered, December 23,2004. After performing a “slump” test on arrival, HMI took “cores” (samples) from the concrete and had the cores independently tested to verify that the concrete met the 4000 psi specifications. The cylinders were tested at 22, 28, 34, and 56 days; none of the tests consistently confirmed the contracted 4000 psi strength. HMI notified ConRock of the problem on January 31, 2005. On February 4, 2005, HMI informed MeadWestvaco of the deficient concrete testing at 28 days and MeadWestvaco instructed HMI to demolish and replace the concrete foundation. On February 17,2005, the cores still tested below the 4000 psi.

On September 5, 2005, HMI filed suit to recover $40,483.42 in damages, $20,251.00 in labor, $10,090.00 in equipment, and $4,160.55 in materials. HMI alleges that ConRock is responsible under breach of contract for failure to provide 4000 psi concrete and breach of warranty either express or implied.

[6]*6On October 4,2005, ConRock filed a Demurrer and Motion Objecting to Venue. Both parties briefed the issues and a hearing was held on May 25,

2006. By order entered on June 9, 2006, the Court overruled Defendant’s Motion to transfer venue and took Defendant’s Demurrer under advisement, allowing Plaintiff twenty-one days to file an amended complaint, if it chose to do so. On June 9, 2006, Plaintiff filed an amended complaint.

Another hearing was held on November 9, 2006, with ConRock renewing its Motion to transfer venue and demurring to HMI’s amended complaint. By Order entered on December 5,2006, the court again overruled ConRock’s motion to transfer venue as well as overruling its demurrer, being of the opinion that the allegations in the amended complaint covered issues of fact which should be decided by the trier of fact. ConRock was given twenty-one days in which to file responsive pleadings, which were filed on December 21,2006. Said responsive pleadings included (1) a motion to strike Counts II and IV for failing to seek any relief, (2) a demurrer to Counts III and IV as neither stated any grounds for relief, (3) a plea craving oyer for the alleged contract, (4) an answer to the amended complaint, and (5) affirmative defenses. A scheduling order was entered by the court on April 23, 2007.

On April 20,2007, ConRock filed a motion to dismiss etc., raising the issue of spoliation. This motion requested a dismissal with prejudice or, in the alternative, certain evidence be excluded. Subsequently, on October 5,2007, HMI moved to compel a view of ConRock’s premises and supplemental depositions. A hearing was held on October 9, 2007, and, on October 25, 2007, the court entered an order (1) dismissing ConRock’s motion to dismiss on the grounds of spoliation of evidence, (2) overruling, at that time, HMI’s motion to compel a view, and (3) granting HMI’s motion to compel redeposition of two witnesses.

Pursuant to the scheduling order, a trial was held on October 24 and 25, 2007. Upon agreement of the parties, the trial was heard without a jury and, because of the volume of evidence, was extended to October 29,2007. Upon the completion of the evidence, the court requested that the parties submit their arguments in writing in lieu of in-court summations.

Analysis

Breach of Contract

Based on both the evidence reports and the deposition testimony of Defendant’s own concrete manager, Michael Dabbs, the Court finds beyond a preponderance of the evidence that ConRock did not provide 4000 psi [7]*7concrete to the MeadWestvaco utility bridge project on December 23, 2004. There is no question that all parties knew that the project in question required 4000 psi concrete. The real question is how do the parties and, at trial, the trier of fact determine if the requirements have been met. Michael Dabbs testified regarding the mix ingredients to be used for a (Mead)Westvaco project, “Westvaco does a 4,000 psi concrete straight cement as they use that for ... whatever they do. That is what I send unless they specify they want something different.” (Dabbs 10/29/07, 8.) Further, “For this particular mix, this mix was given to ConRock by the Westvaco engineering department.” (Dabbs 10/28/07,9.) Mr. Dabbs estimated the date MeadWestvaco provided ConRock the design mix to be “roughly 2000, 2001.” (Dabbs 10/29/07, 10.)

When asked if (Mead)Westvaco would require their mixes to be VDOT acceptable, Mr. Dabbs made it clear, “No ... in our line of work there are three lines. It is the way the homeowner does it, it is the way VDOT does it, and it is the way Westvaco does it, and Westvaco recognizes nobody but the way they want it done.” (Dabbs 10/29/07,28.) “It is just the way it is. I mean I have heard it from contractors, I have heard it in a round about way through the Westvaco engineering department.” (Dabbs 10/29/07, 28.) “I have dealt with them for 25 years, and I know how they deal.” (Dabbs 10/29/07, 29.)

Mr. Sibold, of HMI, verified Mr. Dabbs testimony by relating it to the pour in question: “then we got a 32 day break [core sample]... 30 something . . . when I received that I told Mike that we were going to have to talk to Westvaco and see what we could do, because we had had some low breaks, not that low, and BE&K had okayed it, and so I wanted to get back with them before we did anything else.” (Sibold 10/24/07, 11.) Sibold continued that Dabbs responded, “well, let me know what you are going to do, what happens.” (Sibold 10/24/07,12.) Sibold continued, “I told him I was going to talk to Westvaco and let them get with the engineering to see what they wanted to do.” (Sibold, 10/24/07, 12.) In response to his notifying MeadWestvaco of the situation, Sibold “called him [Russell of HMI] and told him we had to gear up, we had to take the concrete out, and we were behind schedule and they want us to work over the weekend to get it out. I called people in. I called Mike at the concrete plant.” (Sibold, 10/24/07, 16.) After delivering samples to F & R, Sibold continued, “At that point, when they ran the results, they sent them back to me, then I reported to Westvaco, and then I started to dig concrete out.” (Sibold 10/24/07, 17.)

HMI contracted with ConRock to provide 4000 psi concrete to meet the specifications of a contract HMI had with MeadWestvaco. Through the course of many years of dealing with the ultimate consumer, MeadWestvaco, both parties know that it, MeadWestvaco, would make the final determination as to [8]*8whether the product met their specifications. The evidence through the trial, only a portion of which has been recited, shows that, if MeadWestvaco determined that the concrete was not provided per the contract, it was not.

The issue then focused on who was responsible for the non-compliant concrete. HMI provided the testing results that lead to bearing their initial burden of showing the concrete to be defective. ConRock, in response, questioned the tests, their outcome, and procedures. They further presented evidence that they had provided the appropriate mix design as required by MeadWestvaco. Without reciting the briefs provided by counsel to either party, the court holds that HMI met its burden on that issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wolfe v. Virginia Birth-Related Neurological Injury Compensation Program
580 S.E.2d 467 (Court of Appeals of Virginia, 2003)
Flintkote Co. v. W. W. Wilkinson, Inc.
260 S.E.2d 229 (Supreme Court of Virginia, 1979)
Envirotech Corp. v. Halco Engineering, Inc.
364 S.E.2d 215 (Supreme Court of Virginia, 1988)
Brown v. Range Rover of North America, Inc.
33 Va. Cir. 104 (Fairfax County Circuit Court, 1993)
Bowdoin v. Showell Growers, Inc.
817 F.2d 1543 (Eleventh Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
77 Va. Cir. 5, 2008 Va. Cir. LEXIS 126, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hammond-mitchell-inc-v-construction-materials-co-vaccalleghany-2008.