Richmond D. Co. v. Atchison Etc. Ry. Co.

160 P. 862, 31 Cal. App. 399, 1916 Cal. App. LEXIS 436
CourtCalifornia Court of Appeal
DecidedSeptember 13, 1916
DocketCiv. No. 1484.
StatusPublished
Cited by5 cases

This text of 160 P. 862 (Richmond D. Co. v. Atchison Etc. Ry. Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richmond D. Co. v. Atchison Etc. Ry. Co., 160 P. 862, 31 Cal. App. 399, 1916 Cal. App. LEXIS 436 (Cal. Ct. App. 1916).

Opinion

CHIPMAN, P. J.

The action is for damages arising out of a written contract of date January 31, 1910, between defendant as first party, plaintiff as second party, and East Shore & Suburban Railway Company, third party. This latter company is not made a party to the action.

Defendant is the owner of a tract of land situated in the city of Richmond, Contra Costa County, and was desirous of having “said land filled in as herein (by the contract) provided. ’ ’ The area to be filled is particularly described in the contract; the cubic measurement of said area as stated in the contract was “estimated at approximately two hundred and twenty thousand yards,” and “the second party agrees to fill, at the rate of fifteen cents per cubic yard, within the area described.” A map was attached to the contract as part thereof showing the area to be filled and other facts.

Defendant was to pay plaintiff on “the 15th day of each month, for the work done during the preceding month, seventy-five per cent of the amount estimated by the engineer of the first party to have been earned by the second party during such preceding month and the first party will retain the remaining twenty-five per cent of all monthly estimates of work done until thirty-five days after the completion and acceptance by the first party, of the work herein agreed to be performed. . . . The first party is to construct and maintain any and all levees north of Ohio street necessary or proper to impound the material deposited on the area hereinabove described as lying north of said Ohio street; also such levees as may be necessary to protect its main line between Ohio street and Richmond avenue.”

Plaintiff’s claim is presented in four causes of action. By the first cause of action it is alleged that plaintiff entered *402 upon the work pursuant to the contract and gave the bond specified therein and continued the work “up to on or about the 17th day of August, 1910” ,- that the work performed and material furnished “was accepted by the defendant as having been done and supplied in a workmanlike manner and in accordance with the terms of said contract”; that defendant refused to pay plaintiff for its said services and material furnished by plaintiff “during the month of July, 1910, or any part of said money, and in accordance with the terms of said contract, and by so refusing and neglecting to pay such money, defendant rendered, caused, and made it impossible for the plaintiff to further continue performance under the contract; and on or about the 17th day of August, 1910, the plaintiff without fault on its part, did discontinue and suspend work under said contract, although plaintiff was fully equipped and prepared to continue such work and had expended a large amount of money for materials and supplies necessary to complete the same”; whereupon on said last-mentioned day, “plaintiff notified the defendant that plaintiff would perform no further work under said - contract because of defendant’s neglect and refusal to pay to the plaintiff in accordance with the terms of said contract the amount due, owing and coming to the plaintiff from the defendant for the work and services theretofore performed and labor and material theretofore supplied under said contract”; that plaintiff furnished material and performed work under said contract and in accordance with its terms of the value of $46,575, no part of which has been paid to plaintiff except the sum of $10,575, and there is now due and owing plaintiff from defendant the sum of thirty-six thousand dollars.

The second cause of action is for “work and labor and services heretofore performed and material furnished and supplied by plaintiff for the defendant at the special instance and request of defendant.”

In the third cause of action the making of the contract is alleged; furthermore, that the defendant undertook to build the levees called for in said contract, but that it constructed said levees in such a negligent and imperfect manner as that they failed to hold or impound the material deposited on the said area by plaintiff to the great damage of plaintiff; that by reason thereof the defendant so delayed and embarrassed plaintiff as to cause plaintiff to suspend the entire work un *403 der said contract, and large amounts of material deposited on said area by plaintiff were not held or impounded thereon; that by reason of defendant’s said default, plaintiff was compelled to keep its working forces idle for long periods of time and to pay wages to its employees and rent for a dredger used by plaintiff, all to the loss and damage of said plaintiff in the sum of $6,818.81.

As a fourth cause of action the contract is pleaded and it is alleged that plaintiff on February 12, 1910, notified defendant that plaintiff would be ready to commence operation under said contract as soon as the necessary levees were constructed to impound the material to be dredged and defendant, on or about February 15, 1910, notified plaintiff that proper levees would be constructed on or before February ■20, 1910; that on said last-named date plaintiff hired a dredger at large expense and placed it in position to enter upon said work together with a full crew of men to operate the same and was in readiness to commence work on February 25th; that defendant failed and neglected to construct the levees necessary to impound the material to be deposited until March 10, 1910, and thus prevented plaintiff from commencing operations under said contract until March 10, 1910, to its damage in the sum of three thousand dollars.

In the prayer plaintiff asks judgment for thirty-six thousand dollars, the amount claimed in the first and second causes of action, and interest from August 15, 1910; for the further sum of $16,818, the amount claimed in the third cause of action-; and for the further sum of three thousand dollars, the amount claimed in the fourth cause of action.

In its answer to the first cause of action defendant denies most of its averments; alleges that it mailed at Los Angeles vouchers for work done by plaintiff, to wit, for March, on April 21, 1910; for April, on May 21; for May, on June 21, and for June on July 20,1910, amounting in all to $10,596.53, and that plaintiff accepted the said payments and that on or about August 17, 1910, defendant offered to pay plaintiff the amount found to be due for work performed and materials furnished for the month of July, but plaintiff refused and still refuses to accept the same; alleges that at the time of the abandonment of said contract by plaintiff the value of the work done and materials furnished by it was the sum of $21,978.80 and not the sum of $46,575 as set forth in the com *404 plaint; denies that .there is any sum due and owing plaintiff save and except the sum of $3,387,57; that there was due plaintiff for July the sum of $4,080, which sum defendant tendered plaintiff and was refused, and that there is due plaintiff for work done and materials furnished from August 1 to August 17, 1910, the sum of $1,837.57; that said contract was signed, and delivered on March 3,1910, and not on January 31, 1910, as alleged in the complaint.

Answering the second cause of action, defendant alleges that there is due plaintiff from defendant the sum of $3,387.57 and no more.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Golden
186 P.2d 485 (Idaho Supreme Court, 1947)
Konda v. Lamkin
66 P.2d 164 (California Court of Appeal, 1937)
American Fruit Growers, Inc. v. Jackson
265 P. 926 (California Supreme Court, 1928)
Vaughan v. County of Tulare
205 P. 21 (California Court of Appeal, 1922)
Fawcett v. Nampa & Meridian Irrigation District
187 P. 946 (Idaho Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
160 P. 862, 31 Cal. App. 399, 1916 Cal. App. LEXIS 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richmond-d-co-v-atchison-etc-ry-co-calctapp-1916.