Richco Structures v. Parkside Village, Inc.

263 N.W.2d 204, 82 Wis. 2d 547, 1978 Wisc. LEXIS 1162
CourtWisconsin Supreme Court
DecidedMarch 7, 1978
Docket75-798
StatusPublished
Cited by27 cases

This text of 263 N.W.2d 204 (Richco Structures v. Parkside Village, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richco Structures v. Parkside Village, Inc., 263 N.W.2d 204, 82 Wis. 2d 547, 1978 Wisc. LEXIS 1162 (Wis. 1978).

Opinion

ABRAHAMSON, J.

At issue is whether the failure of one named as a neutral arbitrator to make full disclosure *550 regarding his relationship with the parties or with a representative of the parties to an arbitration proceeding requires vacating the arbitration award. The trial court vacated the award, and we affirm.

I.

In April of 1971, Richco Structures (hereinafter Rich-co) contracted with Parkside Village, Inc. to fabricate and erect the exteriors and certain parts of the interiors of three buildings. Abendroth and Associates, Inc. (hereinafter Associates) was the architect; Emil Abendroth was president of both Parkside Village, Inc. and Associates. Emil Abendroth, Associates and Parkside Village, Inc. will collectively be referred to as “Parkside.”

During the construction process, Parkside complained about the quality of Richco’s work. Parkside ultimately refused to pay the full contract price, and Richco commenced suit seeking $106,003 on the contract. Parkside counterclaimed asserting damages of $590,000 resulting from breaches of contract by Richco.

Richco and Parkside agreed to submit the controversy to arbitration and stipulated to the terms of arbitration. Each was to appoint an arbitrator and the two appointed arbitrators would choose, as the stipulation phrased it, “a third, independent arbitrator.” If agreement among the three arbitrators proved impossible, the findings and award of the independent arbitrator were to be accepted as final and binding. The arbitrators’ report was to be entered by the trial court as a final judgment from which both parties expressly waived right to appeal. The trial court stayed proceedings pending the report of the arbitrators.

Wallace Syring, a Milwaukee contractor, was appointed as the third, independent arbitrator. Since unanimity proved to be impossible, the final report was signed by *551 Syring alone. His award was in favor of Parkside. Parkside then moved the court to confirm Syring’s report and enter judgment upon it, pursuant to sec. 298.09, Stats. 1 Richco moved the court to vacate the award, alleging, inter alia, that the award had been procured by corruption and undue means and that there was evident partiality on the part of the arbitrators.

The court filed a written decision ruling on various aspects of the motions and stating that, upon Syring’s submission of an amended report, the court would confirm the award. The amended report was requested not for the purpose of modifying the award made by Syring, but in order to make Syring’s report conform to the stipulated terms of the arbitration by stating whether either of the other arbitrators had concurred in any portion of the report and award.

After the amended report had been submitted, Richco made a motion that the trial court review its previously stated intention to confirm Syring’s award. Based upon Richco’s motion for review, the trial court ordered an evidentiary hearing for the purpose of determining whether the award had been “procured by corruption and undue means.”

At the hearing, business relationships between Syring and Parkside were disclosed. Syring’s business association with Emil Abendroth dated back to the 1950’s. At that time the connection was attenuated: Abendroth’s *552 company bid as a subcontractor on jobs managed by the company for which Syring then worked. On two occasions during 1973 and 1974 Associates and Syring’s firm worked on the same construction project. The two did not have contracts with each other, but Associates’ project captain provided some supervisory assistance to Syring’s crew. Syring hired Associates to do design work on two small projects in 1974, one of which was not completed at the time of the arbitration. Associates and Syring’s company bid on a few projects together between 1972 and 1974, but they were not awarded the contracts.

Syring also had connections with Attorney Gerald Rice who represented Parkside briefly in the proceedings. Attorney Rice had obtained an extension of time from the court for the filing of the arbitrator’s report and had later filed the motion requesting confirmation of the arbitrator’s report. Rice had drafted wills for Syring, had incorporated Syring’s company, and had been retained to represent Syring in litigation. He was representing Syring on one. matter pending at the time of the arbitration.

Syring also had a prior acquaintance with Marvin Hersh, the arbitrator appointed by Parkside. Syring first met Hersh in 1962 when both were members of a general contractors’ group. Between 1968 and 1973, Syring was one of the contractors working on a hospital; Hersh was construction coordinator for the hospital from 1971 through the arbitration period, and in that capacity he supervised Syring’s employees. Hersh testified that he saw Syring personally about once a week at the construction site.

Following the hearing, the court vacated the award “in all fairness and justice” because of the failure to disclose previous business and social contacts among the arbitrators and parties and because of the type of final award made by Syring. The court further ordered the *553 parties to return to arbitration. Parkside appeals from the order vacating the award. Eichco requests review of the trial court’s order requiring further arbitration.

Because the policy of this state is to foster arbitration as an alternative to litigation, arbitration awards are presumed to be valid. Scherrer Constr. Co. v. Burlington Mem. Hosp., 64 Wis.2d 720, 735, 221 N.W.2d 855 (1974). An award will be set aside only upon a showing that one of the statutory grounds for vacatur exists. Sec. 298.10 (1), Stats., provides as follows:

“(1) In either of the following cases the court in and for the county wherein the award was made must make an order vacating the award upon the application of any party to the arbitration:
“(a) Where the award was procured by corruption, fraud or undue means;
“ (b) Where there was evident partiality or corruption on the part of the arbitrators, or either of them;
“ (c) Where the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced;
“(d) Where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.”

Invalidity of the award must be demonstrated by clear and convincing evidence. Scherrer, supra at 735; Koepke v. E. Liethen Grain Co., 205 Wis. 75, 77-79, 236 N.W. 544 (1931).

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loren Imhoff Homebuilder, Inc. v. Lisa Taylor
2022 WI App 14 (Court of Appeals of Wisconsin, 2022)
John McAdams v. Marquette University
2018 WI 88 (Wisconsin Supreme Court, 2018)
Borst v. Allstate Insurance Co.
2006 WI 70 (Wisconsin Supreme Court, 2006)
Beebe Medical Center, Inc. v. InSight Health Services Corp.
751 A.2d 426 (Court of Chancery of Delaware, 1999)
TUCO Inc. v. Burlington Northern Railroad
912 S.W.2d 311 (Court of Appeals of Texas, 1995)
Cellular Radio Corp. v. OKI America, Inc.
664 A.2d 357 (District of Columbia Court of Appeals, 1995)
DeBaker v. Shah
533 N.W.2d 464 (Wisconsin Supreme Court, 1995)
DeBaker v. Shah
522 N.W.2d 268 (Court of Appeals of Wisconsin, 1994)
State v. P.G. Miron Construction Co.
512 N.W.2d 499 (Wisconsin Supreme Court, 1994)
Northwestern National Insurance v. Allstate Insurance
832 F. Supp. 1280 (E.D. Wisconsin, 1993)
Manu-Tronics, Inc. v. Effective Management Systems, Inc.
471 N.W.2d 263 (Court of Appeals of Wisconsin, 1991)
School District of Spooner v. Northwest United Educators
401 N.W.2d 578 (Wisconsin Supreme Court, 1987)
Village of Turtle Lake v. Orvedahl Construction, Inc.
400 N.W.2d 475 (Court of Appeals of Wisconsin, 1986)
Diversified Management Services, Inc. v. Slotten
351 N.W.2d 176 (Court of Appeals of Wisconsin, 1984)
Hartman v. Cooper
474 A.2d 959 (Court of Special Appeals of Maryland, 1984)
Bernstein v. Gramercy Mills, Inc.
452 N.E.2d 231 (Massachusetts Appeals Court, 1983)
Barcon Associates, Inc. v. Tri-County Asphalt Corp.
430 A.2d 214 (Supreme Court of New Jersey, 1981)
Barcon Associates, Inc. v. Tri-County Asphalt Corp.
411 A.2d 709 (New Jersey Superior Court App Division, 1980)
Milwaukee Police Ass'n v. City of Milwaukee
285 N.W.2d 133 (Wisconsin Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
263 N.W.2d 204, 82 Wis. 2d 547, 1978 Wisc. LEXIS 1162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richco-structures-v-parkside-village-inc-wis-1978.