Woodward, C. J.

Raught having erected, and for many years maintained, a mill-dam in the Clarion river, the plaintiff, in navigating that stream with his lumber, suffered detention and loss by reason of the dam, and brought this action on the case to recover his damages. Raught having died pending the action, his executors were substituted.

The court below ruled that the action would not lie because a statutory mode of redress for such injuries had been provided by the Act of Assembly of 27th March 1852 (Pi L. p. 183), and thus the plaintiff was put out of court.

If it be so, that the legislature have provided a special remedy for injuries of this sort, it must be strictly pursued, and the common-law remedy disappears by virtue of the Act of 1806 : Purd. 41. Let us, therefore, look into the Act of 1852, and consider the effect of its provisions.

It is an act of multitudinous purposes, as its title indicates; but in the 6th section it touches the Clarion river, and declares that the law in relation to mill-dams on that river shall be continued to protect the descending but not the ascending navigation.

Then follows the 7th section, in these words :—

“ See. 7. That whenever it shall be alleged that any dam on said river is not erected according to the requirements of law, and that damages have been sustained in consequence thereof, it [99]*99shall be lawful for any person aggrieved to notify the owner, agent, or person in possession of such premises, that he will proceed to ascertain the damages according to the following provisions, viz.: the person claiming damages shall select one person, and the owner or agent of the dam shall choose one, and if the parties cannot agree on a third person, then the two selected by the parties shall select such person. After being duly sworn or affirmed, the persons so selected shall proceed to inquire into and ascertain the nature and amount of damages sustained, and file their award of the same under their hands and seals, in the office of the prothonotary of the proper county, which shall be entered upon the judgment docket, and when so entered, shall have the full effect and force of a judgment, and such judgment shall have priority of lien on such premises over any other judgments obtained after the-passage of this act: in case the party, his agent or attorney, shall neglect or refuse to perform the part prescribed in relation to the selection of referees, it shall be the duty of the prothonotary to do it for him.”

This is the only section that relates to damages for injury to private property. The 8th section relates to proceedings in the Common Pleas for the alteration or removal of any dam not constructed according to law, and the 9th section provides that all proceedings then commenced in relation to dams in the Clarion, shall be finished according to the provisions of this act.

Recurring now to the 7th section, it is obvious that the case intended to be provided for by the legislature was that of damages resulting from a dam “ not erected according to the requirements of law,” and the reference here, we suppose, was to the Mill-Dam Act of 1803, Purd. 742. That act authorized the owners of lands along any stream of water that was declared by law to be a highway, except the Delaware, Lehigh, and Schuylkill, to erect dams for the convenience of mills on their land, provided they should not obstruct the navigation of such streams, nor prevent the ascent of fish. It gave to the Quarter Sessions of the proper county supervising power over such dams, and it entitled the owner of any boat, raft, or other vessel, who was obstructed or suffered damage by reason of such dam, to sue before a justice of the peace, who had power to appoint referees, if the damages claimed did not exceed $50, with the. right of appeal to the Common Pleas, and if the damages claimed exceeded $50, the suit was to be brought in the first instance in the Common Pleas. Such was the Mill-Dam Act of 1803, to which the Act of 1852 refers itself, and instead of leaving the injured party, to the redress provided by the Mill-Dam Act, the Act of 1852 substitutes a new and wholly inconsistent remedy.

The injured navigator is to choose one referee, and to notify the person in possession of the dam to choose another, and these [100]*100two are to choose a third, if the parties cannot agree on him. If the dam-owner neglect or refuse to choose referees, the prothonotary is to act for him; but the board, when thus constituted, is under no legal obligation to act, and no compensation is provided for them. From their award, if they do act, no appeal lies, but it is to be entered up as a lien without exception, writ of error, or further motion.

Now, according to the ruling of the court below, this was a statutory remedy, that superseded all common-law remedies ; but was it, really, any remedy at all ? The Act of 1806 must be understood as contemplating a statutory remedy that is constitutional and efficacious, not a mere form without substance. To take away the common-law rights of a citizen, without giving him a substantial and adequate redress by statute, would be oppression and injustice: would be violative of his constitutional immunities.

There can be no doubt of the legal right of the plaintiff to navigate the Clarion river. It is a public highway, both by nature and by statute, and is therefore within the purview of the Act of 1803, and of all our legislation protective of the natural right of navigation. If obstructed or injured in the exercise of this right, he must have remedy by “ due course of law.” If no statute provides such remedy, he may resort to the common law. Whether he might seek redress according to the Mill-Dam Act, is not the question before us, but our only question is, whether the Act of 1852 supplied him with that adequate remedy which he had a constitutional right to demand.

We think it did not, for two reasons: First, because the tribunal which it provides is under no legal obligation to act. The referees may in all cases, and certainly would in many cases, decline to decide such disputes between neighbours. The legislature have indeed power to constitute other courts besides those mentioned in the constitution, and we do not doubt that they might provide a compulsory reference for cases of this sort, but we hold that to be no court at all which is under no compulsion to act as a court in a proper ease.

All courts are bound to keep open doors, and to entertain all suitors who present themselves in due form. Our General Arbitration Law imposes a penalty on arbitrators who refuse to take upon themselves the duties of their appointment. It is not a matter of taste or convenience, but of imperative duty with courts of justice, to hear and determine what is duly brought before them. But these referees are placed under no legal duty — no statute has said they shall act — the statute under consideration neither rewards them for action, nor punishes them for inaction, but merely refers the dispute to their pleasure and convenience, and therefore it fails to provide any tribunal whatever.

In the next place, the statute makes their award final, without [101]*101any possibility of a trial by jury. In this respect we think the enactment was palpably unconstitutional.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blum v. Merrell Dow Pharmaceuticals, Inc.
626 A.2d 537 (Supreme Court of Pennsylvania, 1993)
Printed Terry Finishing Co. v. City of Lebanon
372 A.2d 460 (Superior Court of Pennsylvania, 1977)
Commonwealth v. Dillworth
246 A.2d 859 (Supreme Court of Pennsylvania, 1968)
William Goldman Theatres, Inc. v. Dana
173 A.2d 59 (Supreme Court of Pennsylvania, 1961)
Woodring v. Edelman
47 Pa. D. & C. 181 (Northampton County Court of Common Pleas, 1943)
Pennsylvania Publications, Inc. v. Pennsylvania Public Utility Commission
32 A.2d 40 (Superior Court of Pennsylvania, 1942)
Lieberman v. Garbo Amusement Co.
38 Pa. D. & C. 153 (Delaware County Court of Common Pleas, 1939)
Spungin's Appeal
32 Pa. D. & C. 611 (Dauphin County Court of Common Pleas, 1938)
Hall's Estate
28 Pa. D. & C. 169 (Susquehanna County Orphans' Court, 1936)
Povilaitis v. Stainis
21 Pa. D. & C. 81 (Luzerne County Court of Common Pleas, 1933)
Premier Cereal & Beverage Co. v. Pennsylvania Alcohol Permit Board
140 A. 858 (Supreme Court of Pennsylvania, 1928)
Premier Cereal & Beverage Co. v. Pennsylvania Alcohol Permit Board
9 Pa. D. & C. 554 (Philadelphia County Court of Common Pleas, 1927)
Commonwealth v. Dietz
132 A. 572 (Supreme Court of Pennsylvania, 1926)
Commonwealth v. Dietz
7 Pa. D. & C. 25 (Alleghany County Court of Common Pleas, 1925)
Fleming's Estate
109 A. 265 (Supreme Court of Pennsylvania, 1919)
West Virginia Pulp & Paper Co. v. Public Service Commission
61 Pa. Super. 555 (Superior Court of Pennsylvania, 1915)
Ames v. State
11 Ohio N.P. (n.s.) 385 (Cuyahoga County Common Pleas Court, 1911)
School District v. Pitts
39 A. 64 (Supreme Court of Pennsylvania, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
51 Pa. 96, 1866 Pa. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rhines-v-clark-pa-1866.