[387]*387HOWELL, J.

This is an action for damages resulting from personal injuries and property damage sustained by plaintiff when he collided with a railroad locomotive operated by defendant Boise-Cascade Corporation and its wholly owned subsidiary, defendant Valley & Siletz Railroad Company. The jury returned a verdict finding defendants to have been 63 per cent negligent and plaintiff to have been 37 per cent negligent. Plaintiffs damages were determined to be $129,377, and judgment was entered against defendants for 63 per cent of this stun, or $81,508.13. Defendants appeal.

The accident occurred on June 21, 1973, at a railroad crossing in Polk County. The road on which plaintiff was traveling intersects the railroad track at a right angle. Plaintiff testified that as he approached the crossing, he slowed his speed to approximately 45 miles per hour, and when he came within 400 feet of the crossing he slowed his speed again to approximately 40 miles per hour. Plaintiff first saw the train approximately 100 feet from the crossing. He applied his brakes, but his speed carried him into the side of the engine.

Plaintiff claimed his view of the approaching train was obstructed by a line of trees, shrubs, and bushes between the highway and the railroad tracks. Plaintiff also testified that he heard no warning from the train immediately prior to the collision.

The point at which the train crew saw plaintiffs truck, the speed of the train, and the point at which the engineer applied the brakes are all subject to dispute. Except for minor inconsistencies, the crew members generally agreed that the train was traveling between 8 and 10 miles per hour at the time the crew realized plaintiff was not going to stop, and that the engineer then applied the brakes immediately. Plaintiff, however, argues that this testimony is inconsistent with the distance that the train traveled beyond the point of impact.

[388]*388On this evidence, the trial court concluded that the question of the relative fault of the parties should be submitted to the jury, pursuant to Oregon’s comparative negligence law, ORS 18.470. Defendants assign as error: (1) the trial court’s refusal to direct a verdict in favor of defendants; (2) the trial court’s failure to instruct the jury that plaintiff was negligent as a matter of law; and (3) the trial court’s instruction to the jury that the railroad had forfeited its right of way. The three assignments will be considered separately.

1. Defendant’s Motion for Directed Verdict

Oregon’s comparative negligence statute, ORS 18.470, provides in pertinent part:

"Contributory negligence shall not bar recovery in an action by any person or his legal representative to recover damages for death or injury to person or property if the fault attributable to the person seeking recovery was not greater than the combined fault of the person or persons against whom recovery is sought, but any damages allowed shall be diminished in the proportion to the percentage of fault attributable to the person recovering. * *

In Jordan v. Coos-Curry Elec. Coop., 267 Or 164, 515 P2d 913, 516 P2d 472 (1973), we discussed the role of court and jury in cases arising under this statute. We noted that:

"Generally, the apportionment of negligence is for the jury and will not be upset except where it is manifest as a matter of law that the allocation is unreasonably disproportionate.” 267 Or at 165, quoting Skybrock v. Concrete Construction Co., 42 Wis 2d 480, 490, 167 NW2d 209 (1969).

Despite our holding in Jordan, defendant claims the trial court in the present case should have directed a verdict for defendants because "the jury’s finding of negligence on the part of defendants could be based only on speculation.” We disagree.

Plaintiff’s complaint contained four specifications of negligence: (1) that the train was operated at an unreasonable speed; (2) that the train crew failed to [389]*389keep a proper lookout; (3) that the engineer failed to apply the brakes in a timely manner; and (4) that defendants failed to properly maintain their right of way. In analyzing the evidence to determine whether or not there existed a question of fact as to any of these specifications, the trial court was required to view the evidence most favorably to the plaintiff, giving him the benefit of every inference that could be drawn from the evidence. Denley v. Mutual of Omaha, 251 Or 333, 445 P2d 505 (1968). If reasonable minds could differ as to the relative fault of the parties on any of plaintiff’s specifications of negligence, the motion for a directed verdict was properly denied.

Plaintiff’s first three specifications can be considered together. Defendants’ engineer testified that he first saw plaintiff’s truck approaching the crossing when the train was 500 to 600 feet away from the crossing. It was not until the train was 100 to 150 feet from the crossing, however, that the engineer claimed he applied the emergency brake. The evidence showed that after the collision with plaintiff, the train continued on and came to rest 135 feet beyond the point of impact. Plaintiff testified that he did not hear any warning from the train immediately prior to the collision, but that he did hear a loud burst of air, similar to the sound emitted by the train’s braking system, immediately after the collision. The engineer told the investigating police officer that under normal conditions the train, composed of the number of cars it was and traveling 15 miles per hour, could be stopped in 150 feet.

From this evidence, the jurors might reach a number of conclusions. They might conclude that the train crew failed to exercise due care in following the progress of plaintiff’s truck and that no proper lookout was maintained. Alternatively, they might find that if the operators did see plaintiff in time to stop, they were negligent in waiting to apply the brake until it was too late. Finally, they might conclude that in light [390]*390of the distance the train traveled after impact, the speed of the train was unreasonable under the circumstances. Whichever of these conclusions the jury might draw, we cannot say that they are so unreasonable as to be "based only on speculation.”

Of course, the mere fact that defendants may have been negligent does not by itself justify the trial court in submitting the case to the jury. Under ORS 18.470, it must appear that defendants’ negligence was equal to or exceeded any negligence attributable to plaintiff. It is clear in the present case that plaintiff was not entirely free from negligence,1 and the jury so found. Nevertheless, in light of the evidence reviewed above, we believe reasonable minds could differ over the relative fault of the parties, and we cannot say that "it is manifest as a matter of law” that plaintiff’s negligence exceeded defendants’. Jordan v. Coos-Curry Elec. Coop., supra at 165.

A different question, however, is presented by plaintiff’s allegation that the defendants negligently failed to maintain the condition of their right of way.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deckard v. Bunch
370 P.3d 478 (Oregon Supreme Court, 2016)
Towe v. Sacagawea, Inc.
346 P.3d 1207 (Oregon Supreme Court, 2015)
Towe v. SACAGAWEA, INC.
264 P.3d 184 (Court of Appeals of Oregon, 2011)
Hernandez v. Barbo MacHinery Co.
957 P.2d 147 (Oregon Supreme Court, 1998)
United Employer Benefit Corp. v. Department of Insurance & Finance
892 P.2d 722 (Court of Appeals of Oregon, 1995)
Hardt v. Columbia Plywood
826 P.2d 85 (Court of Appeals of Oregon, 1992)
Cervantes v. Mattson
752 P.2d 1293 (Court of Appeals of Oregon, 1988)
Gattman v. Favro
739 P.2d 572 (Court of Appeals of Oregon, 1987)
Torres v. Pacific Power & Light
740 P.2d 792 (Oregon Supreme Court, 1987)
Torres v. Pacific Power and Light
734 P.2d 364 (Court of Appeals of Oregon, 1987)
Lawrence v. Underwood
726 P.2d 1189 (Court of Appeals of Oregon, 1986)
Banks v. Martin
717 P.2d 1192 (Court of Appeals of Oregon, 1986)
Reynolds v. Tyler
670 P.2d 223 (Court of Appeals of Oregon, 1983)
Western Alliance Corp. v. Western Reliance Corp.
643 P.2d 1382 (Court of Appeals of Oregon, 1982)
Carter v. Wolf Creek Highway Water District
635 P.2d 1036 (Court of Appeals of Oregon, 1981)
Holmes v. Oregon Ass'n of Credit Management, Inc.
628 P.2d 1264 (Court of Appeals of Oregon, 1981)
Fitch v. Adler
627 P.2d 36 (Court of Appeals of Oregon, 1981)
Taylor v. Gaudry
611 P.2d 336 (Court of Appeals of Oregon, 1980)
Resser v. Boise Cascade Corp.
587 P.2d 80 (Oregon Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
587 P.2d 80, 284 Or. 385, 1978 Ore. LEXIS 1175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/resser-v-boise-cascade-corp-or-1978.