Republic Steel Corporation v. Costle

581 F.2d 1228
CourtCourt of Appeals for the Sixth Circuit
DecidedSeptember 20, 1978
Docket76-1557
StatusPublished

This text of 581 F.2d 1228 (Republic Steel Corporation v. Costle) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Republic Steel Corporation v. Costle, 581 F.2d 1228 (6th Cir. 1978).

Opinion

581 F.2d 1228

11 ERC 2041, 8 Envtl. L. Rep. 20,686

REPUBLIC STEEL CORPORATION, Petitioner,
v.
Douglas M. COSTLE, Administrator, U. S. Environmental
Protection Agency,
George R. Alexander, Jr., Regional Administrator, U. S.
Environmental Protection Agency,
Ned E. Williams, Director, Ohio Environmental Protection
Agency, Respondents.

No. 76-1557.

United States Court of Appeals,
Sixth Circuit.

Argued June 6, 1978.
Decided Aug. 21, 1978.
Rehearing Denied Sept. 20, 1978.

Eben H. Cockley, Ronald R. Janke, Jones, Day, Reavis & Pogue, Cleveland, Ohio, for petitioner.

Robert V. Zener, Gen. Counsel, Environmental Protection Agency, Washington, D. C., Ray E. McDevitt, Barry L. Malter, Thomas A. Pursley, III, Dept. of Justice, Edward J. Shawaker, Washington, D. C., E. Dennis Muchnicki, Columbus, Ohio, for respondents.

George R. Alexander, Jr., pro se.

Before CELEBREZZE, LIVELY and KEITH, Circuit Judges.

CELEBREZZE, Circuit Judge.

This case is before the Court on remand from the Supreme Court for further consideration in light of the Clean Water Act of 1977, P.L. 95-217. In our previous decision we held that the Administrator of the United States Environmental Protection Agency (EPA) had improperly vetoed issuance of a water pollution permit to petitioner Republic Steel Corporation (Republic) for its Canton, Ohio, mill. Republic Steel Corp. v. Train, 557 F.2d 91 (6th Cir. 1977) (hereinafter referred to as Republic Steel I ).1 Contra, United States Steel Corp. v. Train, 556 F.2d 822, 854-55 (7th Cir. 1977).

The Administrator had objected to the permit, originally proposed by the Ohio Environmental Protection Agency (OEPA), on the ground that it improperly waived a July 1, 1977, statutory deadline for compliance with federal effluent standards. Under § 301(b)(1)(A)(i)2 of the Federal Water Pollution Control Act as amended in 1972 (FWPCA) industrial dischargers were required to comply "not later than July 1, 1977" with "effluent limitations for point sources (requiring) the application of the best practicable control technology currently available, as defined by the Administrator pursuant to § 304(b)" of the Act. At the time of our previous decision EPA had not yet promulgated final regulations defining "best practicable technology currently available" (BPT) for categories of dischargers including iron and steel manufacturing, despite a requirement in § 304(b)(1)3 of the Act that such regulations be published by October 18, 1973.4

We reluctantly concluded that EPA's failure to timely define BPT precluded the Administrator from imposing a July 1, 1977, compliance deadline, since Congress had apparently established promulgation of regulations under § 304(b) as a necessary precondition for imposition of the deadline in § 301(b)(1)(A)(i). Our decision was designed "to relieve the discharger of the unfair consequences" of being forced to comply with the deadline in the absence of applicable standards for guidance. 557 F.2d at 97.

This Court stayed its mandate in Republic Steel I pending the EPA's petition for a writ of certiorari from the Supreme Court. Shortly after EPA filed its petition for certiorari, Congress enacted the Clean Water Act of 1977, which substantially revised FWPCA. In the wake of that enactment, the Supreme Court granted EPA's petition, vacated our judgment in Republic Steel I, and remanded the case to this Court for further consideration in light of the new law. Costle v. Republic Steel Corp., 434 U.S. 1030, 98 S.Ct. 761, 54 L.Ed.2d 778 (1978).

We have reviewed the 1977 Act and conclude that its provisions have effectively overruled our previous decision. Although neither § 301(b)(1)(A) (i), requiring industrial dischargers to achieve BPT no later than July 1, 1977, nor § 304(b), requiring EPA to define BPT by October 18, 1973, were amended by the 1977 Act, Congress did add a new § 309(a)(5)(B)5 providing as follows:

(B) The Administrator may, if he determines (i) that any person who is a violator of, or any person who is otherwise not in compliance with, the time requirements under this Act or in any permit issued under this Act, has acted in good faith, and has made a commitment (in the form of contracts or other securities) of necessary resources to achieve compliance by the earliest possible date after July 1, 1977, but not later than April 1, 1979; (ii) that any extension under this provision will not result in the imposition of any additional controls on any other point or nonpoint source; (iii) that an application for a permit under section 402 of this Act was filed for such person prior to December 31, 1974; and (iv) that the facilities necessary for compliance with such requirements are under construction, grant an extension of the date referred to in section 301(b)(1)(A) to a date which will achieve compliance at the earliest time possible but not later than April 1, 1979.

The legislative history of this provision makes it abundantly clear that Congress intended the procedure outlined therein to be the exclusive avenue of relief from the dictates of a mandatory and unconditional July 1, 1977, deadline. The Senate Report expressly rejected the rationale of Republic Steel I :6

Under existing law there are no circumstances that justify a time for compliance extending beyond July 1, 1977. The Administrator can only issue an enforcement order requiring compliance within 30 days or initiate civil or criminal action. Thus, the decision of the U.S. Court of Appeals for the Sixth Circuit in Republic Steel Corporation v. Train et al. and Williams, 557 F.2d 91, (6th Cir. 1977) was an incorrect interpretation of existing law. This amendment responds to the legitimate concern of dischargers who, despite good faith efforts, will not comply with the 1977 requirements. To accommodate this objective, the committee amended section 309(a) of the act to authorize the Administrator in his discretion, to pursue one of two new options with regard to a discharger out of compliance.

The committee believes that a case has been made in our hearings on this bill that some relief from penalties must be granted for those sources which have made a good faith attempt to comply with the deadlines in the statute but for justifiable reasons have been unable to do so. The committee considered but rejected the alternative of providing a case-by-case extension of the deadline set out in the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Chemical Foundation, Inc.
272 U.S. 1 (Supreme Court, 1926)
United States v. Morgan
313 U.S. 409 (Supreme Court, 1941)
Markham v. Cabell
326 U.S. 404 (Supreme Court, 1946)
Clark v. Uebersee Finanz-Korp., AG
332 U.S. 480 (Supreme Court, 1947)
Bradley v. School Bd. of Richmond
416 U.S. 696 (Supreme Court, 1974)
Withrow v. Larkin
421 U.S. 35 (Supreme Court, 1975)
Dobbert v. Florida
432 U.S. 282 (Supreme Court, 1977)
Republic Steel Corporation v. Train
557 F.2d 91 (Sixth Circuit, 1977)
United States Steel Corp. v. Train
556 F.2d 822 (Seventh Circuit, 1977)
Republic Steel Corp. v. Train
557 F.2d 91 (Sixth Circuit, 1977)
Republic Steel Corp. v. Costle
581 F.2d 1228 (Sixth Circuit, 1978)
Costle v. Republic Steel Corp.
434 U.S. 1030 (Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
581 F.2d 1228, Counsel Stack Legal Research, https://law.counselstack.com/opinion/republic-steel-corporation-v-costle-ca6-1978.