Republic Steel Corp. v. Train

557 F.2d 91, 10 ERC 1306
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 23, 1977
DocketNo. 76-1557
StatusPublished
Cited by18 cases

This text of 557 F.2d 91 (Republic Steel Corp. v. Train) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Republic Steel Corp. v. Train, 557 F.2d 91, 10 ERC 1306 (6th Cir. 1977).

Opinion

CELEBREZZE, Circuit Judge.

This case of first impression arises under the 1972 amendments to the Federal Water Pollution Control Act, P.L. 92-500.1 The question presented is whether failure of the Administrator of the United States Environmental Protection Agency (EPA) to define interim effluent limitations reflecting a given level of pollution control technology, as required by the Act, frees an authorized state agency to issue a discharge permit which sanctions noncompliance with the statutory deadline for achieving that degree of effluent abatement.

The law in the case consists of three interdependent provisions of the Act which are at the crux of the regulatory scheme to control point sources of water pollution. [93]*93Section 301(b)2 defines an inflexible schedule for achieving two interim levels of effluent abatement in furtherance of “the national goal that the discharge of pollutants into the navigable waters be eliminated by 1985.” Section 101(a)(1). Key to this litigation is the subsection 301(b)(l)(A)(i) requirement of conformity by July 1, 1977 with “effluent limitations for point sources * * * which shall require the application of the best practicable control technology currently available [BPT] as defined by the Administrator pursuant to section [304(b)] of [the Act] * * *.” Section 304(b)(1),3 in turn, obligates the Administrator to publish by October 18, 1973, regulations establishing effluent guidelines reflecting BPT for categories of dischargers including iron and steel manufacturing. See section 306(b)(1)(A).4

Pollution control standards promulgated pursuant to sections 301 and 304 are implemented nationally through a decentralized permit granting mechanism defined in section 4025 as the National Pollutant Discharge Elimination System (NPDES). Subsection 402(a)(1) empowers EPA in the normal course to issue permits which impose industry-wide effluent limitations which it has already defined. In addition, EPA may define these limitations on a case by case basis “prior to the taking of necessary implementing actions relating to all such requirements” (i.e., while rule making is still in progress). Id.

Subsection 402(b) directs the Administrator to delegate permit granting authority to states which have proposed self-regulatory programs which are operationally compatible with uniform administration of the Act. To ensure that qualifying state environmental agencies apply effluent limitations evenhandedly, subsection 402(d)(2)(B) empowers the Administrator to block issuance of any proposed NPDES permit which he deems to be “outside the guidelines and requirements of [the Act].” Id. Whether federal or state in origin, all NPDES permits must ensure compliance with “applicable requirements” of six enumerated provisions of the Act including section 301. In addition, all permits must issue on or before December 31,1974, pursuant to subsection 402(k).6

In July, 1972, Republic Steel Corporation (Republic) applied for a federal permit to continue discharging effluents from its Canton, Ohio steel mill into Nimishillen Creek. The Canton mill is an integrated steel manufacturing operation engaged primarily in the processing of alloy and stainless steel. In March, 1974, Ohio received approval from EPA under section 402(b) to begin issuing NPDES permits, and Republic immediately commenced to negotiate with the Ohio Environmental Protection Agency (Ohio EPA).

In June, 1974, Ohio EPA issued a draft permit7 for the Canton mill which incorporated state defined effluent limitations under state estimates of BPT. The permit provided for a 24 month compliance schedule compatible with the Act’s July 1, 1977 interim implementation deadline. At that time EPA had failed to promulgate any section 304(b) effluent limitation guidelines for iron and steel manufacturing.8 As of [94]*94the present date no final regulations exist covering alloy and stainless steel operation.9

Understandably, in the absence of controlling federal regulations, Republic sought to exploit available state administrative procedures to secure the most favorable permit terms and conditions. Prolonged hearings and negotiations with Ohio EPA resulted in redefinition of the originally proposed effluent limitations. On August 1, 1975, eight months after the last date envisioned by Congress for routine issuance of NPDES permits, final agreement was reached and the implementation period commenced to run. However, Republic continued to assert that full compliance within 24 months was physically impossible.10 This prompted further adjudication hearings at which Republic presented unchallenged engineering and procurement data which convinced Ohio EPA to modify the permit to allow 42 months for development and installation of antipollution devices. Ohio EPA was aware that this change extended compliance beyond the July 1, 1977, date imposed by section 301(b)(l)(A)(i). However, the state administrator believed that the special circumstances of the case legally justified this deviation.

In January, 1976, Ohio EPA transmitted the final NPDES permit to EPA’s Region V office as required by section 402(d)(1). Within 90 days the Director of the Enforcement Division of Region V objected to its issuance, exercising his authority under section 402(d)(2)(B). He did not expressly question the reasonableness of the' state’s BPT effluent standards or the 42 month implementation schedule. Rather, he concluded that the permit violated section 301 because full compliance would not be achieved until after July 1, 1977. Republic filed a timely petition for judicial review, pursuant to section 509(b)(1)(F),11 challenging this determination.

We do not question EPA’s good faith in attempting to discharge the ambitious and often ambiguous duties imposed upon it by a “poorly drafted and astonishingly imprecise statute.” E. I. du Pont de Nemours & Company v. Train, 541 F.2d 1018, 1026 (4th Cir. 1976). Many factors, some admittedly beyond EPA’s control, have conspired to frustrate its legitimate compliance efforts. In particular, virtually every exercise of the agency’s discretion has precipitated protracted litigation challenging the legitimacy of its authority or the substance of its “final” regulations. See American Petroleum Institute v. Environmental Protection Agency, 540 F.2d 1023, 1027 (10th Cir. 1976) (thirteen relevant cases cited).

The fact remains, however, that the imperative nature of EPA’s rule making responsibilities under the Act has been confirmed through litigation. In 1975, the United States Court of Appeals for the District of Columbia affirmed the authority of a federal district court to compel the agency to adhere to a remedial, court imposed timetable for the publication of guidelines for all point source effluent discharges. Natural Resources Defense Council, Inc. v. Train, 166 U.S.App.D.C. 312, 510 F.2d 692 (1975). Unfortunately, judicial intervention did not avert the regrettable situation which confronts us here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hughey v. JMS Development Corp.
Eleventh Circuit, 1996
ITT Rayonier Inc. v. Department of Ecology
586 P.2d 1155 (Washington Supreme Court, 1979)
Republic Steel Corporation v. Costle
581 F.2d 1228 (Sixth Circuit, 1978)
Republic Steel Corp. v. Costle
581 F.2d 1228 (Sixth Circuit, 1978)
Republic Steel Corporation v. Train
557 F.2d 91 (Sixth Circuit, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
557 F.2d 91, 10 ERC 1306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/republic-steel-corp-v-train-ca6-1977.