Reliance Insurance v. City of Boston

884 N.E.2d 524, 71 Mass. App. Ct. 550
CourtMassachusetts Appeals Court
DecidedApril 14, 2008
DocketNo. 07-P-66
StatusPublished
Cited by26 cases

This text of 884 N.E.2d 524 (Reliance Insurance v. City of Boston) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliance Insurance v. City of Boston, 884 N.E.2d 524, 71 Mass. App. Ct. 550 (Mass. Ct. App. 2008).

Opinion

Cowin, J.

Reliance Insurance Company (Reliance), having provided performance and payment bonds to EJ. Sciaba Contracting Co., Inc. (Sciaba), a general contractor, in connection with a project of the department of neighborhood development of the city of Boston (city), paid Sciaba’s debt to CJM Services, Inc. (CJM), a subcontractor.4 Reliance, as subrogee of Sciaba, sought to recover the payment from the city. The city in turn asserted third-party claims against the remaining parties. Acting on a motion to dismiss pursuant to Mass.R.Civ.P. 12(b)(6), 365 Mass. 754 (1974), filed by the city and the other third-party defendants, a judge of the Superior Court dismissed two counts of Reliance’s action on the grounds that (1) an anti-assignment clause in the construction contract entered into by the city and Sciaba precluded Reliance, as Sciaba’s surety, from asserting subrogation claims against the city; and (2) the failure of CJM to file a timely proof of claim in Sciaba’s bankruptcy proceeding rendered it impossible for CJM to collect against Sciaba, thus eliminating Reliance’s subrogation claim. Following the judge’s decision on the motion, separate and final judgment entered pursuant to Mass.R.Civ.P. 54(b), 365 Mass. 820 (1974).

Contrary to the motion judge, we conclude that (1) the anti-assignment clause was not intended to eliminate subrogation rights otherwise enjoyed by a surety;-and (2) once Reliance paid CJM, CJM’s ability to recover in bankruptcy against Sciaba became irrelevant to Reliance’s right as subrogee to pursue Sciaba’s claim against the city. Accordingly, we reverse the judgment and direct that the counts in question be restored for further proceedings.

1. Background. The underlying facts and procedural history are not disputed. Engaged in a project to renovate the Vine Street Community Center on Dudley Street in Boston (Vine Street center), the city in late 1998 selected Sciaba to be the general contractor. On January 4, 1999, Sciaba obtained both [552]*552performance and payment bonds from Reliance as required by G. L. c. 149, § 29. The city and Sciaba executed the contract on January 26,1999. On July 21,1999, Sciaba and Reliance executed a continuing agreement of indemnity, effective November 4, 1998, whereby Sciaba agreed “[t]o assign, transfer and convey [to Reliance] ... as collateral security for the full performance of the covenants and agreements herein contained . . . [a]ll rights, actions, causes of action, claims and demands of [Sciaba] in, or arising from or out of” the general contract entered into between Sciaba and the city.

However, the general contract contains three provisions that limit the right of Sciaba to assign rights or obligations under the contract. In the standard general conditions, art. 10.1 provides that “[t]he Contractor (Sciaba) shall not assign, delegate, subcontract or in any way transfer any interest in this Contract without prior written consent of the Official.”5 Elsewhere in the contract, among its miscellaneous terms, it is provided in art. 7.16 that “[n]o assignment by a party to this Contract of any rights under or interests in the Contract Documents will be binding on the other party without the written consent of the party sought to be bound; and specifically, but without limitation, monies that may become due and monies that are due may not be assigned without such consent . . . .” The restriction is reiterated in article 7.12: “The Contractor shall not sell, assign, transfer or otherwise convey any of his rights and shall not delegate any of his duties under this Agreement without the prior and express written consent of the City and the Surety. In its sole discretion the City may refuse to consent to any proposed assignment or delegation.”

On February 2, 1999, Sciaba subcontracted with CJM for the performance of certain abatement services for the project. These [553]*553services involved the removal and disposal of asbestos, lead, avian fecal matter, and contaminated soil from the Vine Street center at which the contemplated renovations would take place. Relying on specifications and plan documents created by the city, ICON, Pratt, and the joint venture, CJM agreed to perform the required services for a lump sum payment of $80,000. Prior to commencing the work, however, CJM and Sciaba conducted a visual inspection of the site and found far greater deterioration than originally contemplated in the design documents.

CJM and Sciaba informed the city of their findings, emphasizing that increased funds would be required for proper amelioration of the site’s condition. While initially reluctant to increase its expenditures, the city eventually authorized payment for the increased work on a time and materials basis. Ultimately, the total cost for abatement services reached $1,518,154.25. The city refused to pay Sciaba a substantial portion of this amount, and Sciaba in turn refused to pay CJM a total of $770,532.74 for the work in question.

CJM then initiated what evolved into this proceeding by filing a complaint under G. L. c. 149, § 29, in Superior Court against both Sciaba and Reliance seeking recovery under the payment bond. See note 4, supra. Sciaba thereafter filed a third-party complaint against the city asserting claims for breach of contract, contribution, and indemnification arising out of the city’s alleged fault in underestimating the scope of required abatement services and then in failing to pay Sciaba for the expanded services of its subcontractor. The city in turn filed what it denominated its own third-party complaint claiming that any liability to Sciaba that it might have incurred was caused by the negligent preparation of design documents by ICON, Pratt, and the joint venture.

On December 18, 2003, Sciaba filed a bankruptcy petition under chapter 7 of the Bankruptcy Code, see 11 U.S.C. § 301 (2000). CJM did not file a proof of claim by the deadline, instead seeking and obtaining leave from a bankruptcy judge to proceed solely against Reliance.7 On October 8, 2004, the city, ICON, Pratt, and the joint venture filed a motion to dismiss [554]*554Sciaba’s third-party complaint.8 Reliance opposed the motion in its capacity as Sciaba’s surety. As indicated, a judge dismissed the counts of Sciaba’s third-party complaint that claimed rights of contribution and indemnification by the city, but denied the motion with respect to Sciaba’s breach of contract claim. Reliance voluntarily dismissed that claim, thereby rendering the dismissal of the remaining counts ripe for appeal.

In November, 2005, Reliance paid CJM the full amount of CJM’s claim against Sciaba.9 This appeal now turns on whether Reliance is entitled to recover on Sciaba’s claim against the city notwithstanding the anti-assignment provisions of the general contract and the failure of CJM to file a timely proof of claim in the Sciaba bankruptcy.

2. The motion to dismiss. While the joint motion to dismiss Sciaba’s third-party complaint, and thereby also eliminate Reliance’s right of recovery, was filed pursuant to Mass.R.Civ.R 12(b)(6), the third-party defendants nevertheless attached to their motion copies of a bankruptcy court docket sheet and an affidavit of CJM’s counsel establishing that CJM had in fact filed no proof of claim in the Sciaba bankruptcy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joanne Mistler v. Lockheed Martin Corporation.
Massachusetts Appeals Court, 2025
Richard Dibiasio v. William Barabino.
Massachusetts Appeals Court, 2025
MARITA E. HYMAN v. ROGER STANFORD & Others.
Massachusetts Appeals Court, 2025
Jerry Thomas v. Jane Cunningham.
Massachusetts Appeals Court, 2025
Legalbriefs, Inc. v. Foley & Lardner LLP
Massachusetts Superior Court, 2025
Pisano v. Thunberg
Massachusetts Land Court, 2021
Chang v. Winklevoss
123 N.E.3d 204 (Massachusetts Appeals Court, 2019)
Doe v. American Guaranty and Liability Co.
Massachusetts Appeals Court, 2017
Baker v. Wilmer Cutler Pickering Hale & Dorr, LLP
33 Mass. L. Rptr. 267 (Massachusetts Superior Court, 2016)
Boyle v. Zurich American Insurance
32 Mass. L. Rptr. 352 (Massachusetts Superior Court, 2014)
Pierre v. Chase Home Finance, LLC
31 Mass. L. Rptr. 696 (Massachusetts Superior Court, 2013)
Adorno v. Barclay
30 Mass. L. Rptr. 329 (Massachusetts Superior Court, 2012)
Weiss v. Grolman
30 Mass. L. Rptr. 295 (Massachusetts Superior Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
884 N.E.2d 524, 71 Mass. App. Ct. 550, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliance-insurance-v-city-of-boston-massappct-2008.