Reliable Electric Co., Inc. v. Olson Construction Company

726 F.2d 620
CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 28, 1984
Docket82-1328
StatusPublished
Cited by203 cases

This text of 726 F.2d 620 (Reliable Electric Co., Inc. v. Olson Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliable Electric Co., Inc. v. Olson Construction Company, 726 F.2d 620 (10th Cir. 1984).

Opinion

BARRETT, Circuit Judge.

Reliable Electric Company (Reliable), the debtor, appeals from a final order of the federal district court affirming a decision of the United States Bankruptcy Court for the District of Colorado that the prepetition unsecured claim of Olson Construction Company (Olson), the creditor, is not subject to Reliable’s confirmed Plan of Reorganization. The bankruptcy court found that although Olson possessed actual knowledge of the reorganization proceeding in general, it did not receive adequate notice of the con *621 firmation hearing. Thus, Olson’s claim was found not to be discharged pursuant to the provisions of the Plan as provided by 11 U.S.C. § 1141. The pertinent facts are undisputed, but a detailed presentation of them is necessary to adequately address the question before us.

Between June, 1979, and December, 1979, Reliable was the electrical subcontractor on a construction project; Olson was the general contractor. On December 26,1979, Reliable withdrew from the project because it felt Olson had breached the subcontract. On January 30, 1980, Reliable filed a petition for voluntary Chapter 11 reorganization in the United States Bankruptcy Court. Reliable filed a schedule of creditors on February 14,1980, and amended that schedule on August 28, 1980. Within the schedule, Olson was listed under “Accounts Receivable,” but never as a “Creditor.”

Sometime between January, 1980, and November, 1980, Jon Clarke, Reliable’s attorney, telephoned Charles H. Haines, Jr., Olson’s attorhey, and informed Mr. Haines that Reliable had instituted Chapter 11 proceedings. However, Olson did not receive any further information from Reliable concerning the proceedings. On November 9, 1980, Reliable filed suit against Olson in Colorado State District Court seeking damages for breach of the subcontract. On or about December 16, 1980, Olson removed the cause to federal bankruptcy court. Thereafter, on December 28, 1980, Olson responded to Reliable’s complaint through an Answer and Counterclaim for damages based upon Reliable’s alleged prepetition breach of the subcontract.

On January 6, 1981, Reliable filed its Third Amended Plan of Reorganization. The Disclosure Statement attached to this Plan stated that both documents were sent to all of Reliable’s known creditors. 1 On January 13, 1981, the bankruptcy court mailed a notice to the scheduled creditors informing them of the time for filing acceptances or rejections of the Plan, of the confirmation hearing, and of the time for filing objections to confirmation. The confirmation hearing was conducted on March 9, 1981, after which the court entered an order confirming Reliable’s Third Amended Plan. On March 12, 1981, the court mailed to the scheduled creditors notice of the confirmation order and discharge of Reliable. Because Olson was not a scheduled creditor, it did not receive any of these notices. 2

On August 6, 1981, trial was held on the subcontract dispute between Reliable and Olson. On August 10,1981, the bankruptcy court entered judgment dismissing Reliable’s complaint and granting Olson recovery against Reliable in the amount of $10,-378.00. Reliable then filed a claim in the Chapter 11 proceeding on behalf of Olson for $10,378.00 pursuant to Bankruptcy Interim Rule 3004. Reliable also filed a motion in the same proceeding to allow the claim of Olson. Further, Reliable filed a motion in the subcontract litigation to amend the judgment, requesting that the court specifically find the $10,378.00 judgment for Olson be determined a prepetition debt subject to compromise and payment as a general unsecured claim under the confirmed Plan of Reorganization and, thus, subject to discharge. The bankruptcy court issued an order, containing findings of fact and conclusions of law, denying Reliable’s motions. The court found that because Reliable failed to schedule Olson as a creditor and failed to notify Olson of the confirmation hearing and because Olson’s claim would be substantially impaired without due process of law if it were forced to comply with the Plan, Olson’s claim was not *622 subject to the confirmed Plan and, therefore, not discharged. The district court denied Reliable’s petition for review of the bankruptcy court’s ruling.

The issues on appeal are (1) whether Reliable’s failure to give Olson reasonable notice of the bankruptcy confirmation hearing constituted a denial of due process, and (2) if we find a denial of due process, whether the district court erred by finding Olson’s claim not to be subject to the Plan and, thus, not dischargeable.

I.

11 U.S.C. § 1128(a) provides: “After notice, the court shall hold a hearing on confirmation of a plan.” This section requires notice to be given to all parties in interest. 5 Collier on Bankruptcy Para. 1128.01[2] (15th ed. 1988). After Olson filed the counterclaim against Reliable on December 23, 1980, Reliable was put on notice of Olson’s status as a potential creditor. Despite this, no formal notice of any kind regarding the reorganization proceedings, or the time and manner of filing a claim, was ever given to Olson prior to the confirmation hearing. The apparent notice given to Olson prior to the counterclaim filing was inadequate notice of the confirmation hearing. 3 Although Olson’s attorney was generally aware of Reliable’s involvement in reorganization proceedings, Olson was essentially denied the opportunity to be heard at the confirmation hearing.

The Supreme Court has repeatedly held that “[a]n elementary and fundamental requirement of due process in any proceeding which is to be accorded finality is notice reasonably calculated, under all the circumstances, to apprise interested parties of the pendency of the action and afford them an opportunity to present their objections.” Mullane v. Central Hanover Trust Co., 339 U.S. 306, 314, 70 S.Ct. 652, 657, 94 L.Ed. 865 (1950) (citing Milliken v. Meyer, 311 U.S. 457, 61 S.Ct. 339, 85 L.Ed. 278 (1940); Grannis v. Ordean, 234 U.S. 385, 34 S.Ct. 779, 58 L.Ed. 1363 (1914); Priest v. Las Vegas, 232 U.S. 604, 34 S.Ct. 443, 58 L.Ed. 751 (1914); Roller v. Holly, 176 U.S. 398, 20 S.Ct. 410, 44 L.Ed. 520 (1900)). As specifically applied to bankruptcy reorganization proceedings, the Court has held that a creditor, who has general knowledge of a debtor’s reorganization proceeding, has no duty to inquire about further court action. The creditor has a “right to assume” that he will receive all of the notices required by statute before his claim is forever barred. New York v. New York, New Haven & Hartford R.R. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deanna Williams
N.D. Illinois, 2020
Neighbors' Consejo
District of Columbia, 2019
In re Temsco NC Inc.
537 B.R. 108 (D. Puerto Rico, 2015)
Van Sickle v. Hallmark & Associates, Inc.
2013 ND 218 (North Dakota Supreme Court, 2013)
In Re St. James Mechanical, Inc.
434 B.R. 54 (E.D. New York, 2010)
Sanchez v. Northwest Airlines, Inc.
432 B.R. 803 (D. Minnesota, 2010)
Herring v. Texaco, Inc.
165 P.3d 4 (Washington Supreme Court, 2007)
In Re Craft
321 B.R. 189 (N.D. Texas, 2005)
In Re Nahat
315 B.R. 368 (N.D. Texas, 2004)
In Re Swanson
312 B.R. 153 (N.D. Illinois, 2004)
In Re Eagle-Picher Industries, Inc.
216 B.R. 611 (S.D. Ohio, 1997)
In Re O'Neal
214 B.R. 405 (N.D. Alabama, 1997)
Corman v. Morgan (In Re Morgan)
197 B.R. 892 (N.D. California, 1996)
Maxwell v. K Mart Corp.
880 F. Supp. 1323 (D. Minnesota, 1995)
In Re Dartmoor Homes, Inc.
175 B.R. 659 (N.D. Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
726 F.2d 620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reliable-electric-co-inc-v-olson-construction-company-ca10-1984.