Reiman Corp. v. City of Cheyenne

838 P.2d 1182, 1992 Wyo. LEXIS 148, 1992 WL 277256
CourtWyoming Supreme Court
DecidedOctober 13, 1992
Docket91-269
StatusPublished
Cited by35 cases

This text of 838 P.2d 1182 (Reiman Corp. v. City of Cheyenne) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reiman Corp. v. City of Cheyenne, 838 P.2d 1182, 1992 Wyo. LEXIS 148, 1992 WL 277256 (Wyo. 1992).

Opinions

GOLDEN, Justice.

Reiman Corporation (Reiman) filed a declaratory judgment action against the City of Cheyenne (City) after the City had awarded Reiman a construction contract on an allegedly “mistaken bid.” Reiman requested the district court to declare that Reiman was entitled to withdraw/rescind its bid without forfeiture of the bid bond, or, in the alternative, to declare that Rei-man was entitled to reform its bid to correct the alleged error. Following a hearing on cross-motions for summary judgment, the district court issued an order which dismissed Reiman’s withdrawal/rescission claim for want of jurisdiction and granted summary judgment to the City on the reformation claim. Reiman appeals from only that portion of the district court’s order which dismissed its withdrawal/rescission claim. We will reverse and remand.

ISSUES

The only issue properly before this court is: Whether the district court erred in dismissing Reiman’s withdrawal/rescission claim on the basis that it lacked subject matter jurisdiction under the Uniform Declaratory Judgments Act.

FACTS

The City published an invitation for bids for the construction of a new fire station headquarters building on October 16 and 23, 1990. The invitation for bids informed all prospective bidders that bids would be accepted until bid opening at 2:00 p.m. on November 6, 1990. Reiman submitted its bid to the City at approximately 1:50 p.m. on November 6, 1990. Reiman’s bid of [1184]*1184$1,910,000, secured by a five percent bid bond, was low bid for the project.

Approximately an hour after the bid opening, Tom Reiman (Mr. Reiman), Vice President of Reiman, allegedly discovered a clerical error of $71,000 in the computation of Reiman’s bid. Mr. Reiman promptly called Marian Black, the City’s Director of Purchasing, and Steve Elliott, the Project Architect, to inform them of the alleged error. Mr. Reiman also wrote a letter to the City Council, in which he explained:

I made an error in adding up my subcontractor bid column. I was adding up my subcontractor bids at approximately 1:35 p.m. when I received a return call from Bob Strasheim of Mechanical Systems concerning his bid and alternate #3. * * * The last item I added in my “Total Sub Bid” column was line item # 12 precast for $4,000.00. When I went back to adding the column after the interruption I started at line item # 21 skylight which was below item # 20 for $4,000.00. As a result I le[f]t out the following:
Line Item # 14 *** $34,300.00
Line Item #15*** 1,500.00
Line Item #16*** 25,200.00
Line Item #19 *** 6,000.00
Line Item # 20 *** 4,000.00
TOTAL $71,000.00

Concluding this letter, Mr. Reiman requested that Reiman be allowed to withdraw its bid without forfeiture of the bid bond and that the contract be awarded to the next lowest bidder.

Mr. Reiman appeared before the City Finance Committee on November 21, 1990 and before the City Council on November 26, 1990. At these meetings, Mr. Reiman reiterated the circumstances leading to the allegedly “mistaken bid” and renewed Rei-man’s request to withdraw its bid without forfeiture of the bid bond. Both the City Finance Committee and the City Council voted to accept Reiman’s bid as originally submitted. Accordingly, the City delivered to Reiman a Notice of Award and a Standard Form of Agreement Between Owner and Contractor on November 28, 1990. The Notice of Award required Reiman to, among other things, execute the contract with the City within ten days. Reiman was advised that failure to execute the contract within the ten-day period would result in a forfeiture of the bid bond. The City issued an amendment to the Notice of Award on December 4, 1990, thereby extending Rei-man’s time for compliance to December 26, 1990.

Reiman filed a petition for declaratory judgment and a motion for preliminary injunction against the City on December 14, 1990. Reiman requested the district court to declare that Reiman was entitled to withdraw/rescind its bid without forfeiture of the bid bond or, in the alternative, to declare that Reiman was entitled to reform its bid to correct the alleged error. Reiman also requested that the district court issue a preliminary injunction to enjoin the City from either requiring Reiman to execute the contract or from taking action to forfeit the bid bond during the pendency of the declaratory judgment action. A hearing on Reiman’s motion for preliminary injunction was set for December 20, 1990.

On December 20, 1990, Reiman and the City entered into an agreement which provided, among other things, that Reiman would withdraw its pending motion for a preliminary injunction, that the declaratory judgment action would remain pending, and that Reiman would sign the contract and proceed with construction. The agreement provided that the contract price would be determined as follows:

d. If the parties cannot agree in writing as to a contract price, the price shall be determined as set forth in this Agreement based upon the decision of the District Court in the action currently pending in Laramie County District Court.
# * * * * *
f. If Reiman prevails, and the District Court finds that Reiman is entitled to rescind its bid, Reiman shall be entitled to a contract price of $1,981,000.00.
g. If the City of Cheyenne prevails in such litigation, and the District Court finds that Reiman is not entitled to re[1185]*1185scind its bid, the City shall be entitled to a contract price as stated in Reiman’s original bid, $1,910,000.00.

Following discovery proceedings, the City filed a motion for summary judgment in the underlying declaratory judgment action on October 7, 1991. Reiman responded with a cross-motion for summary judgment on October 17, 1991. A hearing was then held after which the district court issued an order on October 24, 1991. The district court dismissed Reiman’s withdrawal/rescission claim for want of jurisdiction and granted summary judgment to the City on Reiman’s reformation claim. The district court specifically determined that the withdrawal/rescission issue was rendered moot by the parties’ agreement of December 20, 1990 and that reformation was available only in instances of mutual mistake. This appeal ensued.

DISCUSSION

On appeal, Reiman challenges only that portion of the district court’s order which dismissed its withdrawal/rescission claim. Reiman contends that the district court erred in determining that the withdrawal/rescission claim failed to present a justi-ciable controversy within the meaning of the Uniform Declaratory Judgments Act. Reiman concedes that withdrawal/rescission of its bid is no longer an option, but contends that a justiciable controversy remains in that resolution of the withdrawal/rescission claim will have the collateral effect of establishing the contract price. Thus, the crux of the instant case concerns whether, as a jurisprudential matter, the district court erred in dismissing Reiman’s rescission/withdrawal claim on the ground that the parties’ December 20, 1990 agreement had rendered the issue moot.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Center, LLC v. Lexington Charles Ltd. Partnership
92 A.3d 400 (Court of Appeals of Maryland, 2014)
William F. West Ranch, LLC v. Tyrrell
2009 WY 62 (Wyoming Supreme Court, 2009)
Catamount Construction v. Timmis Enterprises
2008 WY 122 (Wyoming Supreme Court, 2008)
Cathcart v. Meyer
2004 WY 49 (Wyoming Supreme Court, 2004)
Cox v. City of Cheyenne
2003 WY 146 (Wyoming Supreme Court, 2003)
In Re SNK
2003 WY 141 (Wyoming Supreme Court, 2003)
Northern Arapaho Tribe v. State
2003 WY 141 (Wyoming Supreme Court, 2003)
Heilig v. Wyoming Game & Fish Commission
2003 WY 27 (Wyoming Supreme Court, 2003)
Williams v. State
2002 WY 184 (Wyoming Supreme Court, 2002)
Lieberman v. Wyoming. Com LLC
11 P.3d 353 (Wyoming Supreme Court, 2000)
Southwestern Public Service Co. v. Thunder Basin Coal Co.
978 P.2d 1138 (Wyoming Supreme Court, 1999)
Bird v. Rozier
948 P.2d 888 (Wyoming Supreme Court, 1997)
Hirschfield v. Board of County Commissioners
944 P.2d 1139 (Wyoming Supreme Court, 1997)
Barber v. City of Douglas
931 P.2d 948 (Wyoming Supreme Court, 1997)
State Ex Rel. Bayou Liquors, Inc. v. City of Casper
906 P.2d 1046 (Wyoming Supreme Court, 1995)
Amb v. State
892 P.2d 799 (Wyoming Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
838 P.2d 1182, 1992 Wyo. LEXIS 148, 1992 WL 277256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reiman-corp-v-city-of-cheyenne-wyo-1992.