Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In re Redondo Construction Corp.)

513 B.R. 772
Procedural entryThis page is a short order in Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In re Redondo Construction Corp.). Read the opinion of the Court — 505 B.R. 388
United States Bankruptcy Court, D. Puerto Rico·Decided July 14, 2014·No. Bankruptcy No. 02-02887(ESL); Adversary Nos. 03-00192 (ESL), 03-00194 (ESL), 03-00195 (ESL)·Published

Opinion

OPINION AND ORDER

ENRIQUE S. LAMOUTTE, Bankruptcy Judge.

These adversary proceedings are before the court upon the Brief as to [] Extended Home Office Overhead Damages filed by Plaintiff Redondo Construction Corp. (“Redondo”) (Adv. Proc. No. 03-00192 Docket No. 333, Adv. Proc. No. 03-00194 Docket No. 293 and Adv. Proc. No. 03-00195 Docket No. 265). Each adversary proceeding corresponds to a different project where Redondo intervened as a contractor: Adv. Proc. No. 03-00192 corresponds to project Desvío Sur de Patillas (“Desvío Sur de Patillas”), Adv. Proc. No. 03-00194 corresponds to PR 2 Mayaguez (“PR 2 Mayaguez”), and Adv. Proc. No. 03-00195 corresponds to Dorado-Toa Alta (“Dorado-Toa Alta”). Also before the court is Puerto Rico Highway and Transportation Authority’s (“PRHTA”) Brief on the home-office overhead damages, but only in regards to the PR 2 Mayaguez Project (Adv. Proc. No. 03-00194 Docket No. 209). PRHTA did not file briefs in Adv. Proc. Nos. 03-00192 and 03-00195. For the reasons stated below, Redondo’s claims for home-office overhead damages are only allowed under the percentage-of-direct-costs approach.

Procedural Background

On January 13, 2014, this court entered an Opinion and Order (Lamoutte, B.J.) in the instant adversary proceedings granting Redondo pre-judgment interest at six percent (6%) under Article 1061 of the Civil Code of Puerto Rico, 31 L.P.R.A. § 3025, with an accrual period starting from the stipulated dates of substantial completion until PRHTA’s final payment on the principal of the principal amounts for each project. In regards to the home-office overhead damages, the court ordered as follows:

Because the Joint Stipulations filed by the parties do not address whether the extra work performed by Redondo in the three projects were the result of “necessary but unanticipated work” or whether the delay did not arise from a need to perform extra work as mandated by the [Court of Appeals for the] First Circuit [the “First Circuit”], the court orders the parties to file additional stipulations to that effect or separate briefs making specific references to the evidence submitted during the trial to that effect and attaching copies of the same.
If the extra work performed by Redon-do in the three projects was the result of “necessary but unanticipated work” and the percentage-of-direct-costs method is [774]*774applicable, the parties shall stipulate and/or brief the court on the percentage to be applied to the corresponding costs (via change orders and/or extra work orders) making specific references to the evidence submitted during the trial to that effect and attaching copies of the same.
If the Eichleay [1] formula is to be applied, the court further orders the parties to stipulate the calculation of such damages and/or file separate briefs that include specific references to the evidence submitted during the trial to that effect and attaching copies of the same.

See Adv. Proc. No. 03-00192 Docket No. 321, Adv. Proc. No. 03-00194 Docket No. 282 and Adv. Proc. No. 03-00195 Docket No. 279. The Opinion and Order (Lam-outte, B.J.) is published at 505 B.R. 388 (Bankr.D.P.R.2014) and contains a detailed procedural background of these adversary proceedings. The court granted the parties thirty (30) days to file the joint stipulations or briefs on the issue of home-office overhead damages.

On February 12, 2014, PRHTA filed its Brief in compliance with the Opinion and Order for the PR 2 Mayaguez Project. See Adv. Proc. 03-00194 Docket No. 290. It did not file a brief for the other two projects (Adv. Proc. Nos. 03-00192 and 03-00195) claiming that it “was [not] able to prepare [them] within the strict time constraints set by the [] court” (Adv. Proc. 03-00194 Docket No. 307, p. 5, ¶ 16). PRHTA did not request an extension of time to file such briefs in those adversary proceedings. In its only Brief PRHTA sustains that the extra work performed in the PR 2 Mayaguez Project was the result of 39 change orders and 32 extra work orders agreed by the parties, and therefore, Redondo has already been compensated for home-office overhead damages through the direct-cost method, which excludes Eichleay damages according to the parameters established by the First Circuit. In addition, PRHTA avers that there is no evidence that Redondo was stopped (totally or partially) from construction or that it was put in any kind of standby during the completion of additional work performed for the PR 2 Mayaguez Project.

On February 14, 2014, Redondo filed a consolidated Brief for all three projects in each of the instant adversary proceedings. See Adv. Proc. No. 03-00192 Docket No. 333, Adv. Proc. No. 03-00194 Docket No. 293 and Adv. Proc. No. 03-00195 Docket No. 265. Redondo’s Brief offers a lengthy description of the problems and mishaps it confronted during the construction of each project. Regarding the Desvío Sur de Pa-tillas Project, Redondo contends that “some of the problems [it] experienced [ ] consisted of an under-run in the installation of the piles, with the surveying, the elevation of the decks, and design problems, such as the diaphragms and the beams” (Adv. Proc. 03-00192 Docket No. 333, p. 22, ¶ 68). Redondo further stated that it had to submit “a revised claim to the PRHTA for $34,072.27 for the unrecov-ered expenses.” Id. at p. 24, ¶ 74. Redon-do also submitted its final claim on February 21, 1995 to PRHTA “including the under-run on the piles and the additional expenses incurred in the construction ... as evidenced by 15 change orders and 22 extra work orders.... [s]aid Claim includes a net $254,252.36, plus a 10% profit factor of extended home-office overhead.” Id. at p. 24, ¶ 75. Redondo also notified the PRHTA of all the problems related to the worksite and admits that the site condition “could not be predetermined prior to perfuming the activity” and that at the end [775]*775of the activity it would submit a request for payment. Id. at p. 25, ¶ 80.

For the Dorado-Toa Alta Project, Re-dondo sustains that the major problem was the “de-watering problem in building the pier” (Adv. Pr. 03-00195 Docket No. 288, p. 26, ¶ 84). Redondo avers that it relied on the information provided by PRHTA and did not inspect the job site before placing a bid for it. Id. at p. 28, ¶ 96. Upon realizing the actual site conditions of the project, Redondo hired a consultant to evaluate the situation. Id. at p. 28-29. Redondo ultimately submitted a “claim for extended home-office overheard for $23,814.00 plus 10% profit factor ... following the Eichleay formula.” Id. at pp. 29-30, ¶ 106.

For the PR 2 Mayaguez Project, Redon-do acknowledges that “[t]he required change order and extra work orders were of such magnitude that the PRHTA agreed to extensions of almost three (3) times of the original contract time” (Adv. Pro. 03-00194, Docket No. 293, p. 15, ¶ 36). According to Redondo, the cause of the change orders and extra work orders, included: incomplete technical plans, insufficient technical information provided by PRHTA, and that the original plans did not comply with certain requirements set forth by other government agencies and differences in the terrain. Id. at 15, ¶ 38. Redondo asserts it had to subcontract Continental Lord, Inc. (“Lord”) to perform the electrical work on this project.

Free access — add to your briefcase to read the full text and ask questions with AI

Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In re Redondo Construction Corp.), 513 B.R. 772 (prb 2014).

513 B.R. 772 (Redondo Construction Corp. v. Puerto Rico Highway & Transportation Authority (In re Redondo Construction Corp.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related