Rector v. Tobin Construction Company

377 S.W.2d 409, 1964 Mo. LEXIS 801
CourtSupreme Court of Missouri
DecidedMarch 9, 1964
Docket49318
StatusPublished
Cited by12 cases

This text of 377 S.W.2d 409 (Rector v. Tobin Construction Company) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rector v. Tobin Construction Company, 377 S.W.2d 409, 1964 Mo. LEXIS 801 (Mo. 1964).

Opinion

LEEDY, Judge.

Action to recover double damages under § 236.270, RSMo 1959 and V.A.M.S., for the trespass of backing up water on and overflowing lands of the respective plaintiffs to the injury and damage of growing crops thereon, allegedly in consequence of *411 defendant having dammed and obstructed a watercourse in violation of said statute. Trial to the court without a jury; judgment for defendant; plaintiffs appealed, and the St. Louis Court of Appeals reversed and remanded for new trial. On defendant’s application to this court, the case was ordered transferred here under Art. V, § 10, Mo.Const., V.A.M.S., and Rule 84.05, V.A.M.R.

The facts are stated in the opinion of the Court of Appeals (Rector v. Tobin Construction Co., 351 S.W.2d 816), to which reference is made for a more complete statement thereof than we find necessary to the disposition of what we deem to be the determinative question. That question occasioned transfer of the cause, and it is whether, under the facts in judgment, defendant is entitled to share the immunity from liability enjoyed by the authority with which it contracted for injuries growing out of work incidental to the performance of such contract, there being no charge or claim that the contractor was guilty of negligence.

Defendant, a corporate construction contractor, pursuant to a contract with the State Highway Commission, performed certain grading and other work as part of the relocation of U. S. Highway 36 in Macon County, including the construction of a bridge across Middle Fork of Chariton River, a nonnavigable, natural watercourse, referred to in the evidence as a creek. The stream at that point flows in a southerly direction, and it is approximately 35 or 40 feet in width from bank to bank. The highway runs east and west. The lands of plaintiffs lie upstream, to the north of the highway. Immediately north of the site of the bridge, but wholly within the right-of-way of the highway, defendant, while engaged in constructing the bridge, built a dirt fill or dam across the bed of the stream, the bottom of the bed being 8 to 10 feet below the top of the banks. Except in periods of little or no rainfall the flow of the stream is 6 to 12 inches in depth. The fill was about 14 feet in width (north and south) and extended east and west completely across the bed of the stream (35 or 40 feet). Its height was estimated by plaintiff’s witnesses as being from 8 to 12 feet, and was fixed by defendant’s witnesses at 6 or 7 feet. It sloped from each bank toward the center, where it was 2 feet lower than at the banks. A metal drain pipe 3 feet in diameter ran through the fill parallel with the stream, and this permitted the normal flow of the stream to pass through. Heavy rains occurred over a period of several days, notably from July 15 through July 29. July 21-22 nearly 4 inches fell, and July 27-29 more than 4 inches fell, with the result that the lands in question were overflowed to depths varying up to 3 feet. The lands were low-lying and subject to frequent flooding. Even so, and notwithstanding the fact that lands below the dam or fill were flooded and crops damaged, we shall assume for present purposes (as the trial court found) that the fill materially retarded the flow of water occasioned by the rainfalls above mentioned, and prevented the overflowed water from draining from the lands of plaintiffs for a period of time sufficient to kill and injure substantial portions of the crops, the extent of which, in money, the court found to be a total of $3,667.50.

The contract under which defendant built the bridge made no specific reference to a dam or fill across the creek, but did require “any incidental work necessary to complete” the project contracted. And it was stipulated “that defendant had to move dirt [and machinery] across the creek.” Defendant’s project superintendent, with 23 years’ experience, testified it was reasonably necessary in the performance of the contract to have this crossing placed across the stream; that it was necessary for the movement of equipment, materials and dirt back and forth across the stream, and that he did not know of any practical means of getting equipment, materials and dirt across the stream other than by this crossing.

E. E. Baker, an engineer with the Missouri State Highway Department since *412 1926, whose duties included supervising, approval and disapproval of work done by-contractors with the Highway Department, testified to this effect: That the project in question was assigned to him as Resident Engineer; that he was at the site about every day; that he saw and was familiar with the earthen crossing; that the erection of the crossing was a customary and normal procedure in that kind of work— “it was the general practice and I made no objection. I think I could have stopped him if that was unusual.” He further testified that he did not know of any other way of getting the dirt, machinery and materials across “without going to elaborate bridging to cross on, which has never been practiced before;” and that it was “reasonably necessary and incidental to the performance by defendant of its contract with the state,” and that he approved its use.

Another of defendant’s witnesses was also an engineer for the Highway Department and an inspector, as well, working under the witness Baker. He testified that he had had 11 years’ experience in the type of bridge construction here involved, and he was present at the site of construction daily; that he was familiar with the plans and construction requirements for the project, and also with the earthen crossing; that the latter was reasonably necessary and incidental to the performance of the contract; that the use and erection of such a crossing is a normal and customary procedure, and that in this case there was no other way to move the heavy equipment across the stream. In the latter connection he was corroborated by another witness with engineering experience.

No countervailing proof was offered by plaintiffs. And on the basis of the foregoing, the trial court made these specific findings, which we think the evidence abundantly warranted: “The earthen fill in evidence was not specifically directed by the plans and specifications in evidence; it was constructed by the defendant, was incidental to the performance by defendant of its contract with the State Highway Commission; was reasonably necessary for the purpose for which it was intended and was used, and was a reasonable, customary and approved method of moving machinery and fill materials across a watercourse.” And that “any method of conveying machinery and fill materials across the Middle Fork of the Chariton River (even by pontoon bridge) which the defendant could have employed would have resulted in some obstruction to the flow of water.” Upon such hypotheses the court concluded (contrary to the theory advanced by plaintiffs), “Therefore liability of the defendant cannot be predicated upon the theory that the obstruction here was ‘for the convenience’ of the defendant [within the rule applied by the Supreme Court of Arkansas in Foohey Dredging Co. v. Mabin, 118 Ark. 1, 175 S.W. 400, and Kochtitzky v. Bond, 128 Ark. 255, 194 S.W. 8] * *

The Court of Appeals was “not impressed by the contention that the fill was essential to the work being done under the contract,” and declined to give effect to the trial court’s finding in that regard (which finding we regard as correct and unassailable).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blair v. City of Hannibal
179 F. Supp. 3d 901 (E.D. Missouri, 2016)
Trout v. General Security Services Corp.
8 S.W.3d 126 (Missouri Court of Appeals, 1999)
Foremost Insurance Co. v. Public Service Commission
985 S.W.2d 793 (Missouri Court of Appeals, 1998)
Aylward v. Baer
745 S.W.2d 692 (Missouri Court of Appeals, 1987)
State Ex Rel. Missouri Highway & Transportation Commission v. Appelquist
698 S.W.2d 883 (Missouri Court of Appeals, 1985)
State Ex Inf. Ashcroft v. Kansas City Firefighters Local No. 42
672 S.W.2d 99 (Missouri Court of Appeals, 1984)
Phegley v. Porter-DeWitt Construction Co.
501 S.W.2d 859 (Missouri Court of Appeals, 1973)
Bounds v. Scott Construction Co.
498 S.W.2d 765 (Supreme Court of Missouri, 1973)
Smith v. Lockheed Propulsion Co.
247 Cal. App. 2d 774 (California Court of Appeal, 1967)
Maryland Casualty Co. v. State Highway Commission
256 F. Supp. 666 (W.D. Missouri, 1966)
Ferrell v. Topp
386 S.W.2d 33 (Supreme Court of Missouri, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
377 S.W.2d 409, 1964 Mo. LEXIS 801, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rector-v-tobin-construction-company-mo-1964.