Record Corp. v. Logan Construction Co.

22 Pa. D. & C.3d 358, 1982 Pa. Dist. & Cnty. Dec. LEXIS 462
CourtPennsylvania Court of Common Pleas, Clinton County
DecidedJune 3, 1982
Docketno. 1293-79
StatusPublished

This text of 22 Pa. D. & C.3d 358 (Record Corp. v. Logan Construction Co.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Clinton County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Record Corp. v. Logan Construction Co., 22 Pa. D. & C.3d 358, 1982 Pa. Dist. & Cnty. Dec. LEXIS 462 (Pa. Super. Ct. 1982).

Opinion

BROWN, P.J.,

FINDINGS OF FACT

(1) Defendant Logan Construction Company, Inc., is a Pennsylvania corporation engaged in the construction business.

(2) In September of 1977, Logan entered into a [359]*359contract with the Borough of Renovo for the construction of a dam at the Paddy’s Run Reservoir to be completed by November 24, 1978.

(3) In connection with this project defendant needed to purchase sluice gates to be used in its completion.

(4) Plaintiff, Record Corporation, a Maine business corporation is engaged in the business of supplying brass products and related items and was a manufacturer of sluice gates.

(5) In August of 1977, Logan contacted Record with regard to its submitting a written proposal to supply Logan with sluice gates and other accessories for the Paddy Run Project.

(6) On August 23, 1977, Record sent Logan a written offer to provide the needed sluice gates with a proposed delivery date of 16 to 18 weeks following the approval of Record’s drawings.

(7) On October 7,1977, Logan accepted Record’s offer to furnish the five sluice gates as well as certain accessories with the delivery to be as previously stated 16 to 18 weeks after approval of the drawings.

(8) The drawings were approved on January 30, 1978 and forwarded to Record on February 4,1978; some minor changes were made in the drawings in July of 1978 involving a shear gate which was in addition to the five gates originally ordered.

(9) In producing the sluice gates, Record required extruded bronze which had been supplied to it by Anaconda Brass since 1968.

(10) In mid October of 1977, Record was advised that its supply of extruded bronze from Anaconda would be interrupted because of a labor strike. This disruption in supply of extruded bronze lasted for a period of approximately six months.

(11) In December of 1977, Record advised Logan [360]*360of the Anaconda strike but also advised that it would not affect production of the cast iron gates ordered by Logan and it did not advise Logan of any delay in delivery.

(12) By a form letter dated April 28, 1978, Record allegedly notified all sluice gate customers of possible delays in delivery; however, the court finds that it has not been proven that Logan received a copy of this letter.

(13) In April of 1978 Logan was advised by plaintiff that the Anaconda strike was over and that the gates would be delivered in June of 1978.

(14) Throughout the summer of 1978 there were numerous inquiries by Logan of Record as to why the gates had not been delivered but there was no delivery throughout this time period.

(15) On September 18, 1978, Record’s Vice President Robert Hay advised Logan that plaintiff was experiencing financial difficulties and could not get the iron castings from its supplier Seaboard Foundry, Inc. without first paying for them.

(16) On September 21, 1978, Hay advised Logan that if it would forward the sum of $3,775.55 to Seaboard, Record could pick up the iron castings and begin production of the gates. Logan agreed to do this and on September 25, 1978 sent the requested amount to Seaboard.

(17) The gates were finally machined and finishedin December of 1978, and on December 15, 1978, Logan picked up three of the smaller gates and on December 29,1978 picked up the remaining two gates.

(18) Because of the delay in delivery Logan had to call personnel back to work in December of 1978 and January of 1979 to install the gates after the project had been completed (except for the gates). If the gates had been delivered in June of 1978 [361]*361Logan could have installed them without additional labor.

(19) Logan also had to move additional machinery and equipment such as bulldozers and backhoes to the job site for the installation of the gates.

(20) Logan incurred $1,500 in transportation expenses in picking up the sluice gates on December 15,1978 and on December 29,1978 against which Record gave a $401.17 credit because of reduced shipping costs.

(21) Logan incurred a loss of interest on the $3,775.55 advanced to Seaboard on Record’s behalf in the amount of $79.44.

(22) Logan incurred labor expenses in December, 1978, and January, 1979 in installing the sluice gates as follows:

462.5 labor hours at $8.64 $ 3.996.00

113.5 labor hours at $11.27 1,279.15

279.0 operator hours at $11,935 3,329.87

151.0 supervisory hours at $18.00 2.718.00

Total $11,323.02

Payroll taxes and insurance 2.830.76

Total $14,153.78

(23)Logan incurred machinery and equipment expenses in December, 1978 and January, 1979 in installing the sluice gates as follows:

Backhoe: 151 hours at $16.00 $ 2,416.00

Dozer: 64 hours at $26.00 1.664.00

Front end loader: 64 hours at $26.00 1.664.00

Water pump: 10 days at $13.50 135.00

Pick up trucks (2): 21 days at $20.00 840.00

Lowboy: 32 hours at $25.00 800.00

Generator: 21 days at $25.00 525.00

Electric tools: 21 days at $10.00 210.00

Total $ 8,254.00

[362]*362(24) Logan incurred miscellaneous expenses in December, 1978 and January, 1979 in installing the sluice gates as follows:

Gas Heaters (2)— $ 50.00

100 pound bottles of gas (4)— 100.00

Straw (50 bales)— 50.00

Visqueen (1 roll)— _7.40

Total $ 207.70

DISCUSSION AND CONCLUSIONS OF LAW

(A) Plaintiff’s Claim

The parties have stipulated that the unpaid balance due Record on its claim for the sluice gates is $11,286.28. This figure apparently takes into account the $3,775.55 advanced to Seaboard by Logan as well as a credit of $401.17 with regard to reduced shipping costs because of Logan’s having picked up the sluice gates in question. Accordingly, the court will find in favor of plaintiff on plaintiff’s claim in the amount of $11,286.28.

(B) Defendant’s Counterclaim

Logan’s counterclaim for damages is predicted upon Record’s delay in delivery of the ordered sluice gates. In accordance with the parties’ contract, the drawings for the sluice gates were approved which was communicated to Record on February 4, 1978 and therefore, the gates would have been due in Logan’s possession sometime in late May or early June of 1978. The damages that Logan claims are consequential or incidental damages arising out of the delay.

Initially, Record contends that it is not hable for the delay because of its interruption in supply of extruded bronze which was essential to the manufacture of the sluice gates. This defense known as the doctrine of “commercial impracticability” [363]*363arises from 13 Pa.C.S.A. §2615 which provides as follows:

(1) “Delay in delivery ... by a seller who complies with paragraphs (2) and (3) is not a breach of his duty under a contract for sale if performance as agreed has been made impracticable by the occurrence of a contigency the non-occurrence of which was a basic assumption on which the contract was made . . .

(2) (inapplicable)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Exton Drive-In, Inc. v. Home Indemnity Co.
261 A.2d 319 (Supreme Court of Pennsylvania, 1969)
Luria Engineering Co. v. Aetna Casualty & Surety Co.