Rebman v. San Gabriel Valley Land & Water Co.

30 P. 564, 95 Cal. 390, 1892 Cal. LEXIS 835
CourtCalifornia Supreme Court
DecidedJuly 23, 1892
DocketNo. 14708
StatusPublished
Cited by7 cases

This text of 30 P. 564 (Rebman v. San Gabriel Valley Land & Water Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rebman v. San Gabriel Valley Land & Water Co., 30 P. 564, 95 Cal. 390, 1892 Cal. LEXIS 835 (Cal. 1892).

Opinion

Vanclief, C

This is an appeal by defendant from a judgment of $8,263.24 against it for a balance found to be due the plaintiff for work and labor and materials furnished in building a hotel, a laundry, a gas-house, and for repairing the hotel. The appeal is upon the judgment roll containing a bill of exceptions, raising questions of law and fact.

A distinct written contract was signed and delivered by the parties for the construction of each of the buildings above mentioned, and for the repairing of the hotel, before the work was commenced. The contract price for furnishing materials and building the hotel was $48,900; for the laundry it was $1,100; for the gas-house it was $484; and for repairing the hotel it was $595. None of these contracts was ever filed or recorded in the office of the county recorder of the county in which the buildings are situated. They were made at different times, the contract for the hotel being first in order of time.

The complaint consists of five counts: 1. To recover the reasonable value of the labor and material in building the hotel, alleged to be $53,602.76, less $47,000 paid thereon; 2. To recover the reasonable value of labor and materials in building the laundry, alleged to be $1,100, less $863.50 paid; 3. A special count upon the written contract for building the hotel, to recover a balance of $1,900 alleged to be unpaid; 4. A special count upon the gas-house contract, to recover a balance of $104.06, alleged to be due and unpaid; and 5. A special count upon the written contract for repairing the hotel, to recover an alleged balance of $127.95. The prayer of the complaint is, that plaintiff recover the sum of these several balances, with interest. The complaint is not verified.

The answer of defendant, — 1. Denies each and every [392]*392allegation in the complaint; 2. Alleges payment in full; 3. Alleges, in answer to the first count, that all the labor done and materials furnished for the hotel were done and furnished under and in pursuance of the written contract, and that defendant has fully performed its part of said contract; 4. Alleges, in answer to the second count, that the labor and materials done and furnished for the laundry were done and furnished under a written contract, which defendant had fully performed on its part; 5. In further answer to the third count, alleges that by the contract therein mentioned, the plaintiff was required to complete the hotel by the eighth day of December, 1887, but failed to complete it until April, 1888, by reason whereof defendant sustained damages in the sum of six thousand dollars, which is pleaded as a counterclaim; 6. In answer to the fourth and fifth counts, alleges full performance of the contracts therein mentioned on its part; and 7. Alleges, in answer to the entire complaint, a settlement of all matters mentioned therein, and payment in full of the balance agreed upon in the settlement, which payment was accepted by plaintiff in full satisfaction of all claims against defendant on account of all matters mentioned in the complaint.

The defendant also filed an unverified cross-complaint, claiming damages for non-performance of the written contract for the building of the hotel within the time limited by, or in accordance with, the specifications of that contract, which cross-complaint was answered by a general denial thereof.

The court found for the plaintiff upon all the issues, except those arising upon the third count of the complaint, as to which it found that the hotel contract, upon which that count was based, had not been filed in the recorder’s office, and was therefore void.

1. Counsel for appellant contend that the first count of the complaint does not state facts sufficient to constitute a cause of action, because it does not show that the implied contract, upon which it rests, was filed in the re-[393]*393Border’s office in accordance with section 1183 of the Code of Civil Procedure, although it appears that the amount agreed to be paid thereunder exceeds one thousand dollars.

But the first count does not show that any particular amount was agreed to be paid for the labor and materials expended in building the hotel; but only that such labor and materials “were reasonably worth $53,602.76.” Nor does the code provide for recording an implied contract, even conceding that it would be possible and practicable to record such a contract.

But the real question intended to be presented under this head is expressed by counsel for 'appellant as follows: “ Can parties who have failed to put their contract in writing avoid the force and penalty of the statute by suing on a quantum meruit or quantum valebat?

Of course, no party can evade the force or penalty of the statute. Counsel’s question, however, assumes that the statute applies to implied contracts, and that the penalty is incurred by a failure to record an implied contract, and thus evades the only question in dispute, viz.: What are the force and the penalty of the statute?

The statute literally applies only to express contracts stating the mutual obligations of the parties thereto, thereafter to be performed; and requires such contracts to be reduced to writing, and filed in the recorder’s office “before the work is commenced.” Yet no implied contract for labor or materials is complete until after the labor is done or the materials furnished at the request of the owner of the contemplated structure. Neither the mere request of such owner for the performance of labor, or the furnishing of materials, nor the mere performance of labor, or the furnishing of materials without such request, express or implied, constitutes a complete contract by implication. An implied contract arises only from the request of one party and performance by the other, though the request is often inferred from the circumstances attending the performance. It follows that the legislature could not have intended to require implied [394]*394contracts for labor and materials to be written and recorded before the commencement of the work.

Nor does the statute expressly, or by necessary implication, prohibit an action upon such implied contracts, to recover the value of the labor or materials, though such value may exceed one thousand dollars. (See Kiessig v. Allspaugh, 91 Cal. 234.) On the contrary, section 1197 of the chapter on liens seems to except such contracts from the penalty of a failure to record.

Sec. 1197. Nothing contained in this chapter shall be construed to impair or affect the right of any person to whom any debt may be due for work done or materials furnished to maintain a personal action to recover such debt against the person liable therefor.”

In Holland v. Wilson, 76 Cal. 434, the complaint was similar to the first count of the complaint in this action; and the answer thereto alleged as a defense “ that the work and materials were done and furnished in pursuance of a written agreement, executed by the defendant and the plaintiff . . . . before the work was commenced.” The plaintiff demurred to this answer, on the ground that the written contract was void because it did not appear to have been recorded, as required by section 1183 of the Code of Civil Procedure. The lower court sustained the demurrer, and gave judgment for plaintiff on the implied contract, and this court affirmed the judgment, on the ground that the written contract was void because not recorded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Randono
32 Cal. App. 3d 164 (California Court of Appeal, 1973)
City of Pasadena v. County of Los Angeles
258 P.2d 28 (California Court of Appeal, 1953)
Prince v. Hill
149 P. 578 (California Supreme Court, 1915)
Hickman v. Freiermuth
132 P. 772 (California Court of Appeal, 1913)
John Rapp & Son v. Kiel
115 P. 651 (California Supreme Court, 1911)
Laidlaw v. Marye
65 P. 391 (California Supreme Court, 1901)
White v. Fresno National Bank
32 P. 979 (California Supreme Court, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
30 P. 564, 95 Cal. 390, 1892 Cal. LEXIS 835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rebman-v-san-gabriel-valley-land-water-co-cal-1892.