RCN Telecom Services, Inc. v. 202 Centre Street Realty LLC

419 F. Supp. 2d 553, 2006 U.S. Dist. LEXIS 10754, 2006 WL 585587
CourtDistrict Court, S.D. New York
DecidedMarch 8, 2006
Docket02 CIV. 2766(JES)
StatusPublished
Cited by1 cases

This text of 419 F. Supp. 2d 553 (RCN Telecom Services, Inc. v. 202 Centre Street Realty LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RCN Telecom Services, Inc. v. 202 Centre Street Realty LLC, 419 F. Supp. 2d 553, 2006 U.S. Dist. LEXIS 10754, 2006 WL 585587 (S.D.N.Y. 2006).

Opinion

MEMORANDUM OPINION AND ORDER

SPRIZZO, District Judge.

The primary issue before the Court, as raised by a panel of the Second Circuit in a Summary Order dated November 17, 2005 (“Remand Order”), is the apportionment of damages in an action for breach of contract. Because this Court is bound by the Second Circuit’s directive in the Remand Order, this Court finds that plaintiff is *554 solely responsible for all damages it incurred and therefore orders that judgment be entered for defendant. The following shall constitute the Court’s findings of fact and conclusions of law as required by Federal Rule of Civil Procedure 52(a).

BACKGROUND

Plaintiff, RCN Telecom Services, Inc. (“plaintiff’ or “tenant”), and defendant, 202 Centre Street Realty LLC (“defendant” or “landlord”), entered into a lease “made as of July 31, 2000.” 1 See Supplemental Joint Pre-Trial Order, dated Mar. 22, 2004 (“JPTO”), at 4. The lease, which concerned the second and third floors of the building located at 202-204 Centre Street (“the premises”), had an initial term of fifteen years and provided that such period would commence on the “Commencement Date,” which was defined to mean the date on which “actual possession of the demised premises.. .is delivered to Tenant; and... Landlord’s Work (as hereinafter defined) is completed.” Pl.’s Trial Ex. 1 (“Lease”), at 1. “Landlord’s Work” was defined as “deliver[y][ofj possession of the demised premises to Tenant equipped with electrical capacity of at least 2000 Amps @ 208 volts.” Lease at Ex. B. The lease also provided that “[i]f the Commencement Date has not occurred by September 1, 2000, Tenant shall have the right to terminate this lease.” Lease at 3. Prior to the commencement date tenant had no obligations under the lease, see Pl.’s Post-Trial Mem. at 18 n. 7, and owed no rent payments to landlord, see Lease at 1; Tr., dated Apr. 13, 2004 (“Trial Tr.”) at 65-66; Remand Order at 2.

Neither of the parties expected that landlord could complete its work by September 1, 2000, see Trial Tr. at 67-68, 115— 18, 145-46, and, in fact, landlord did not complete its work by that date, JPTO at 6. Nevertheless, both parties moved forward with the project, and tenant, with the knowledge of landlord, see Trial Tr. at 154-56, 182-86, began to renovate and build out the premises, see id. at 71-74, 179-80.

Although minor problems arose along the way, see, e.g., id. at 133-36, 187-89, tenant’s renovations proceeded swiftly. According to status reports generated by tenant’s construction manager, Barney Skanska Construction Co., sixty-five percent of tenant’s build-out work was completed by October 30, 2000, see id. at 192; JPTO at 8, Pl.’s Trial Ex. 8, and ninety-two percent had been completed by December 8, 2000, see Trial Tr. at 194; JPTO at 9, Pl.’s Trial Ex. 10. The December 8, 2000 status report, however, also contained news of a troubling development. That report indicated that another tenant in the premises (“the recalcitrant tenant”) had denied plaintiff and defendant access to the basement — an area where work needed to be completed by both parties. See PL’s Trial Ex. 10; Trial Tr. at 88-93, 194-202, 232; JPTO at 9.

Over the next month landlord achieved a degree of success in forcing the recalcitrant tenant to provide access to the basement. JPTO at 10. As a result, plaintiff was able to gain the access that it needed and by January 26, 2001 it was ninety-seven percent done with its build-out work and had completed all of its work in the basement. See Trial Tr. at 93-94, 196— 200; PL’s Trial Ex. 14; JPTO at 11.

The victory over the recalcitrant tenant, however, proved to be short-lived. Although plaintiff was able to finish its work in the basement, defendant could not maintain access long enough to complete its *555 work. See Trial Tr. at 93. In addition, defendant was not granted the emergency relief it sought in the courts and the litigation brought against the recalcitrant tenant dragged on without resolution. See JPTO at 10-12,16-17; Trial Tr. at 240-48; Pl.’s Trial Ex. 18. Having ceased building out the property, plaintiff waited to see if defendant would complete its work and upgrade the power as stipulated in the lease. See JPTO at 16-17; Trial Tr. at 98-99.

Landlord was never able to complete its work in the basement. See Trial Tr. at 101, 232-33, 249. Finally, by letter dated February 26, 2002, tenant terminated the lease. See JPTO at 17; Trial Tr. at 101-02; Pl.’s Trial Ex. 30.

Plaintiff brought this action by Complaint dated April 10, 2002 seeking to recover for defendant’s breach of the lease. Compl. ¶¶ 16-19. This Court conducted a bench trial on April 13 and 14, 2004. Following trial, the parties submitted post-trial memoranda of law, and this Court heard Summations on July 20, 2004. See Tr., dated July 20, 2004 (“Summ.Tr.”). At a February 14, 2005 conference, this Court made findings of fact and conclusions of law on the record. This Court found that both parties caused fifty percent of the damages incurred by plaintiff and therefore entered judgment awarding plaintiff fifty percent of its losses plus prejudgment interest. 2 See Tr., dated Feb. 14, 2005 (“Conf.Tr.”), at 2.

Both parties appealed the Court’s ruling, and the Second Circuit vacated the judgment and remanded the case by Summary Order. See Remand Order. The Second Circuit ordered this Court to specify findings of fact and to “dispose of this ease in accordance with this summary order.” Id. at 2.

DISCUSSION

Although the Remand Order raised a number of issues, this case concerns essentially the issue of causation. See Trial Tr. at 4-5; Summ. Tr. at 17-19, 27-47; Conf. Tr. at 2-4.

As the Second Circuit has stated, “Causation is an essential element of damages in a breach of contract action; and, as in tort, a plaintiff must prove that a. defendant’s breach directly and proximately caused his or her damages.” Nat’l Mkt. Share, Inc. v. Sterling Nat’l Bank, 392 F.3d 520, 525 (2d Cir.2004). Therefore, in order to prevail on a breach of contract claim, a plaintiff has the burden, as part of its “prima facie case,” to show that the damages it seeks “are ‘directly and proximately’ caused by a defendant’s breach of contract” since causation is a “crucial” element of its case. Id. at 526 (quoting Wakeman v. Wheeler & Wilson Mfg. Co., 101 N.Y. 205, 209, 4 N.E. 264, 266 (1886)); see also Krauss v. Greenbarg, 137 F.2d 569, 572 (3d Cir.1943); Point Prods. A.G. v. Sony Music Entm’t, Inc., 215 F.Supp.2d 336, 341-44 (S.D.N.Y.2002); Krofft Entm’t, Inc. v. CBS Songs, 653 F.Supp. 1530, 1534-35 (S.D.N.Y.1987).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
419 F. Supp. 2d 553, 2006 U.S. Dist. LEXIS 10754, 2006 WL 585587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rcn-telecom-services-inc-v-202-centre-street-realty-llc-nysd-2006.