Raytheon Company v. Boccard USA Corporation

369 S.W.3d 626, 2012 WL 1638501, 2012 Tex. App. LEXIS 3690
CourtCourt of Appeals of Texas
DecidedMay 10, 2012
Docket01-10-00950-CV
StatusPublished
Cited by6 cases

This text of 369 S.W.3d 626 (Raytheon Company v. Boccard USA Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raytheon Company v. Boccard USA Corporation, 369 S.W.3d 626, 2012 WL 1638501, 2012 Tex. App. LEXIS 3690 (Tex. Ct. App. 2012).

Opinion

OPINION

LAURA CARTER HIGLEY, Justice.

Boccard USA Corporation sued Ray-theon Company seeking to hold it liable for a breach of contract by Raytheon Company’s former third-tier subsidiary, United *629 Engineers International, Inc. (“United Engineers”) based on the theory of alter ego. A jury found United Engineers had breached its contract with Boccard and made an affirmative finding on Boccard’s alter ego claim against Raytheon Company. Based on the jury’s verdict, the trial court rendered judgment against Ray-theon Company in favor of Boccard.

Of the four issues raised by Raytheon Company on appeal, the dispositive issue we address is whether Boccard had standing to pursue its alter ego claim. Because we hold that Boccard did not have standing to pursue the claim, we vacate the trial court’s judgment and dismiss the case.

Background Summary

In May 1998, United Engineers entered into a turnkey agreement with Atlantic Methanol Production Company LLC (“AMPCO”) in which United Engineers agreed to provide “all design, engineering, procurement, construction, ... [and] other work necessary to build a methanol production facility” for AMPCO in Equatorial Guinea. To build the plant, United Engineers needed fabricated piping spool, and Boccard agreed to supply such material to United Engineers. In June 1999, the two companies entered into a contract, in the form of a purchase order, setting out the terms of the agreement by which Boccard would supply piping spool to United Engineers. The contract stated that the total price of the order was not to exceed $5.5 million.

Over the next year, disputes arose between the two companies regarding the order. Each side accused the other of not sufficiently performing its obligations under the agreement. For example, Boccard asserted that United Engineers failed to timely supply Boccard with drawings and other information necessary for it to complete the order, and United Engineers contended that Boccard was causing unnecessary delays. Over time, the scope and the cost of order incrementally increased. After the last of the product was shipped by Boccard to United Engineers in May 2000, Boccard claimed that United Engineers still owed it over $3.9 million. United Engineers claimed that Boccard had deviated from the agreement and, as a result, owed money to United Engineers.

Around this same time, United Engineers and its parent company, Raytheon Engineers & Constructors, Inc. (“RE & C”), were sold to Morrison Knudsen, a construction company. Before the sale, United Engineers was a wholly-owned subsidiary of RE & C, and RE & C was a wholly-owned subsidiary of Raytheon Engineers and Constructors International, Inc. (“RECI”), which is in turn, was a wholly owned subsidiary of Raytheon Company (“Raytheon”). Following the sale, Raytheon and RECI remained as parent and subsidiary. After purchasing RE & C and its subsidiaries, including United Engineers, Morrison Knudsen and RE & C merged to form Washington Group International, Inc. (“Washington Group”). At that point, United Engineers became a wholly-owned subsidiary of Washington Group.

About a year after the corporate merger, Washington Group and its subsidiaries, including United Engineers, filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code in Reno, Nevada. As a creditor, Boccard filed a proof of claim in the bankruptcy court for the monies it claimed were owed by United Engineers on the AMPCO methanol plant project.

When the bankruptcy petition was filed, Washington Group became the debtor-in-possession, acting in the capacity of a *630 bankruptcy trustee. 1 As debtor-in-possession, Washington Group filed an adversary proceeding in the bankruptcy court against Raytheon and RECI. Among its claims, Washington Group alleged that, before Morrison Knudsen purchased RE & C, Raytheon had depleted RE & C of its working capital rendering it insolvent. It further alleged that Raytheon had misrepresented to Morrison Knudsen the true financial condition of RE & C, failing to disclose a number of RE & C’s liabilities. In January 2002, Raytheon and Washington Group entered into a settlement agreement whereby each party mutually released the other from all claims.

In July 2003, Boccard filed an adversary proceeding seeking to resolve its claim against Washington Group. On January 27, 2004, the bankruptcy court signed a stipulated order dismissing Boccard’s adversary proceeding with prejudice but allowing Boccard a claim in the bankruptcy proceeding in the amount of $3.1 million. The order expressly provided that it had no res judicata or other preclusive effect.

On April 8, 2004, Boccard filed the instant suit against Raytheon. Boccard asserted, inter alia, that United Engineers breached its contract by failing to pay all amounts owed to Boccard for supplying the fabricated piping spool for the construction of the AMPCO methanol plant. Boccard sought to hold Raytheon liable for United Engineers’s breach of contract based on the theory of alter ego. Boccard alleged that, prior to selling RE & C and United Engineers to Morrison Knudsen, Raytheon, and its linear subsidiaries, had disregarded the corporate form to the point that each wholly-owned subsidiary and its respective parent company were the alter egos of one another. In other words, United Engineers and its parent, RE & C, were alter egos of each other; RE & C and RECI were alter egos; and RECI and Raytheon were alter egos. Boccard claimed that Raytheon, as the ultimate parent corporation in the chain, was liable for United Engineers’s breach of contract.

Raytheon filed a motion for partial summary judgment in which it challenged Boc-card’s alter ego claim. Raytheon asserted, inter alia, that Boccard did not have standing to assert an alter ego claim because the claim belonged exclusively to the bankruptcy estate. Raytheon argued that, pursuant to the Bankruptcy Code, only the bankruptcy trustee, or as in this case, the debtor-in-possession, has standing to assert a claim owned by the bankruptcy estate.

The trial court denied Raytheon’s motion for partial summary judgment. The case proceeded to trial before a jury. The jury found in favor of Boccard on its breach of contract and alter ego claims. The trial court rendered judgment on the jury’s verdict, awarding Boccard $3,444,513.62 in damages. 2 This appeal followed.

Standing

In its first issue, Raytheon asserts that Boccard lacked standing to assert its alter ego claim. Without the alter ego claim, Boccard cannot recover against Raytheon for breach of contract.

*631 A. General Legal Principles Regarding Standing

Standing focuses on the question of who may bring an action. See Patterson v. Planned Parenthood, 971 S.W.2d 439, 442 (Tex.1998). Standing is a component of subject-matter jurisdiction, and subject-matter jurisdiction is essential to the authority of a court to decide a case. Tex. Ass’n of Bus. v. Tex. Air Control Bd.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
369 S.W.3d 626, 2012 WL 1638501, 2012 Tex. App. LEXIS 3690, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raytheon-company-v-boccard-usa-corporation-texapp-2012.