Raylaine Worsteds, Inc. v. United States

146 F. Supp. 723, 137 Ct. Cl. 54, 1956 U.S. Ct. Cl. LEXIS 195
CourtUnited States Court of Claims
DecidedDecember 5, 1956
DocketNo. 49550
StatusPublished
Cited by10 cases

This text of 146 F. Supp. 723 (Raylaine Worsteds, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raylaine Worsteds, Inc. v. United States, 146 F. Supp. 723, 137 Ct. Cl. 54, 1956 U.S. Ct. Cl. LEXIS 195 (cc 1956).

Opinion

Laramore, Judge,

delivered the opinion of the court:

The plaintiff makes its claim under the War Contract Hardship Claims Act, popularly called the Lucas Act, 60 Stat. 902, 903, as amended by 62 Stat. 992, 41 U. S. C. § 106 note (1952 Ed.), to recover an alleged net loss of $43,238.93 sustained by the plaintiff in the performance of Government contracts between September 16, 1940, and August 14, 1945.

During the above period, the plaintiff, a corporation engaged in the operation of a mill at Manchester, New Hampshire, performed under 12 contracts with the Army Quartermaster Corps. Sis of the contracts, entered into between June 19, 1940, and April 1, 1941, contained a liquidated-damages clause under which the Government could withhold specified sums per day for each day the delivery of prescribed shipments of cloth under the contracts was late. The other six contracts entered into between February 5, 1942, and April 26,1943, did not contain liquidated-damages clauses and are not in any way subject to litigation in this suit. Pursuant to the liquidated-damages clause in the above contracts, liquidated damages were assessed by the Government against the plaintiff and withheld from payments made by the Government to the plaintiff.

The aforementioned damages clause also contained a provision that the contractor could obtain an extension in its date of delivery when the cause of a delay in delivery was due to unforeseeable causes beyond the control and without the fault or negligence of the contractor if the contractor notified the contracting officer in writing of the cause of the delay within 10 days from the beginning thereof.

Deliveries on contract number W 669 qm-10270 were first due on May 4,1941, but were not forthcoming. On May 6, 1941, the contracting officer, by letter, notified the plaintiff of the delinquency. Plaintiff answered by letter on May 12, 1941, indicating the causes of delay but not making a request for an extension of the time of delivery. On July 9, 1941, [56]*56however, the plaintiff did make such a request but it was later denied by the contracting officer on October 15, 1941, because the plaintiff did not make its request within the 10 days specified in the contract and because the causes assigned by it were not unforeseeable causes beyond the control and without the fault or negligence of the plaintiff. There is some question as to whether the plaintiff appealed from this decision within the 30 days specified therefor in the contract, but the record does reveal a letter by the plaintiff to the contracting officer giving notice of appeal on November 13,1941. The case was subsequently forwarded to the Quartermaster General in Washington with another more-detailed letter from the plaintiff dated December 11, 1941, which the contracting officer in its letter classified as the letter of appeal. The letter of November 13, 1941, was not mentioned to the Quartermaster General and was evidently not forwarded to him. The forwarding letter assigned an additional reason for refusing to grant relief to the plaintiff on appeal, it being that plaintiff did not file its appeal within the 30-day period specified in the contract. The letter of December 11, 1941, was evidently treated as an adequate appeal, however, and the Quartermaster General denied recovery to the plaintiff for only the first two causes mentioned above.

Upon the passage of the War Contract Hardship Claims Act, and pursuant thereto, the plaintiff on February 5,1947, sought remission of losses due to the assessments of the liquidated damages by request to the Quartermaster Purchasing Office, New York, N. Y. This claim was denied by the War Contract Hardship Claims Board on December 22,1949, upon the ground that no written request under the First War Powers Act had been made by plaintiff of the War Department. The Board, upon reconsideration, again denied plaintiff’s claim on February 16,1950.

Plaintiff filed its petition with this court on March 21,1950, requesting a remission of the liquidated damages assessed alleging that it is entitled to recovery because it meets the prerequisites of the act, to wit, it suffered an overall net loss on all its Government contracts, performance of which occurred within the period of September 16,1940, and August 14, 1945, and that such loss was not due to its own fault or [57]*57negligence. Plaintiff also avers that a proper written request for relief within the purview of section 3 of the Lucas Act was filed on behalf of plaintiff with the War Department of the United States prior to August 14, 1945, contrary to the decision of the War Contract Hardship Claims Board.

This court has jurisdiction to award recovery to claimants under the Lucas Act only in those cases where a proper request for relief was filed prior to August 14, 1945, pursuant to section 3 of that act.

Section 3 of the Lucas Act is as follows:

Claims for losses shall not be considered unless filed with the department or agency concerned within six months after the date of approval of this Act, and shall be limited to losses with, respect to which a written request for relief was filed with such department or agency on or before August 14-, 194-S, but a previous settlement under the First War Powers Act, .1941, or the Contract Settlement Act of 1944 shall not operate to preclude further relief otherwise allowable under this Act. [Emphasis added.]

The Supreme Court in Fogarty v. United States, 340 U. S. 8 (1950), has construed that section “to mean written notice presented prior to August 14, 1945, to an agency which was authorized to grant relief under § 201 of the First War Powers Act.” In that connection the Court therein went on to say at page 13:

* * * Since there is no definition of the term in the Act or regulations, and since the legislative history of the Act does not show that any settled usage of the term was brought to the attention of Congress, no particular form of notice is required. But whatever the form of notice, it must be sufficient to apprise the agency that it was being ashed to grant extra-legal relief under the First War Powers Act for losses sustained in the performance of war contracts. [Emphasis added.]

Thus, in order for a claimant in this court to recover for losses incurred in the performance of Government contracts between September 16, 1940, and August 14, 1945, it must show that it made a written request for extralegal relief with the department or agency concerned before August 14,1945.

This we think the plaintiff has not done in this case.

[58]*58In support of its contention that it did file a proper written request for extralegal relief the plaintiff points to the fact that this court on July 9, 1951, overruled, without opinion, the defendant’s motion of May 2,1951, to dismiss plaintiff’s petition on the ground that no proper request for relief had been filed. Raylaine Worsted Inc. v. United States, 119 C. C. Cls. 838. The plaintiff contends that notwithstanding the fact that no opinion was filed, the decision of a case is the court’s judgment thereon, its opinion being only a statement of the reasons on which the judgment rests.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tindall v. United States
Federal Claims, 2026
Fillmore Equipment of Holland, Inc. v. United States
105 Fed. Cl. 1 (Federal Claims, 2012)
Alabama-Coushatta Tribe of Texas v. United States
28 Fed. Cl. 95 (Federal Claims, 1993)
Design & Production, Inc. v. United States
35 Cont. Cas. Fed. 75,718 (Court of Claims, 1989)
Ulmet v. United States
17 Cl. Ct. 679 (Court of Claims, 1989)
Gindes v. United States
5 Cl. Ct. 947 (Federal Circuit, 1984)
Department of Natural Resources & Conservation v. United States
30 Cont. Cas. Fed. 70,906 (Court of Claims, 1983)
Denton v. Ellis
258 F. Supp. 223 (E.D. North Carolina, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
146 F. Supp. 723, 137 Ct. Cl. 54, 1956 U.S. Ct. Cl. LEXIS 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raylaine-worsteds-inc-v-united-states-cc-1956.