Ray Farmers Union Elevator Co. v. Weyrauch

238 N.W.2d 47, 18 U.C.C. Rep. Serv. (West) 683
CourtNorth Dakota Supreme Court
DecidedDecember 22, 1975
DocketCiv. 9132
StatusPublished
Cited by17 cases

This text of 238 N.W.2d 47 (Ray Farmers Union Elevator Co. v. Weyrauch) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ray Farmers Union Elevator Co. v. Weyrauch, 238 N.W.2d 47, 18 U.C.C. Rep. Serv. (West) 683 (N.D. 1975).

Opinions

PEDERSON, Judge.

This is an appeal from a summary judgment entered by the district court of Williams County awarding Ray Farmers Union Elevator Company liquidated damages against Weyrauch Bros, upon the default of grain contracts. Although the judgment is in its favor, the elevator company appeals and asserts that a liquidated damage clause is not to be construed as an exclusive remedy under § 41-02-98, NDCC, unless it is so expressly agreed in the contract. The elevator company claims that summary judgment was improper and that it was entitled to a trial on the question of damage. There is no dispute of material facts. We accept the trial court’s reasoning but remand the case for correction of a mathematical error in the judgment.

In September 1972 the Weyrauchs entered into three grain contracts calling for delivery of wheat and durum to the elevator company on or before April 30, May 15, and May 15,1973, respectively. Each of the contracts provided in part that in case of default in delivery of the grain, the Wey-rauchs agreed to pay the elevator company “as liquidated damages” the difference between the contract price and the market price at Minneapolis (less freight) at the close of the market on a specified date. In two of the contracts delivery dates and damage computation dates were identical. The third contract had a delivery date fifteen days ahead of the damage computation date. Pursuant to these contracts, deliveries of part of the grain called for were made and accepted periodically from January through July 11, 1973. On July 12 the Weyrauchs notified the elevator company that they would make no further deliveries pursuant to the three contracts, or at least indicated that further deliveries depended upon a judicial determination as to their ability to break the contracts. No further deliveries were made. After a written demand for delivery on November 5, the Wey-rauchs refused and tendered payment of liquidated damages in the sum of $18,-623.45, computed in accordance with the three contracts on the basis of the grain contracted for but not delivered, using market prices of April 30, May 15, and May 30.

[49]*49The elevator company sued on the contracts, asking for damages of $137,313.34. In answering, the Weyrauchs demanded a jury trial and admitted that they breached the contracts. After issue was joined and depositions taken, the trial court granted a motion by the Weyrauchs for summary judgment for the elevator company in the amount of the liquidated damages. None of the evidence presented to the trial court indicated that there had been any oral discussion as to whether the liquidated damage clause was or was not intended to be exclusive. No evidence was submitted on the question as to whether time was of the essence — the contracts themselves specifically stated that “time is of the essence.” The contracts further specifically provided that delivery of grain to the elevator was required on or before the specified dates “provided space is available to receive and store the same, and if not, as soon thereafter as space is available.” The evidence is undisputed that the elevator did not have space available to receive all of the grain at the times scheduled in the contracts. Unlike other cases we have had before us, in this case there is no dispute as to which party breached the contracts.

In its argument on appeal the elevator company asserts that it is entitled to present alternative methods of computing-damages, to wit: (1) “cover” damages pursuant to § 41-02-90, NDCC (2-711, UCC), which indicates .total damages of $127,-276.00; (2) damages based on date of repudiation (July 11, 1973, rather than the April and May dates in the contracts), which indicates total damages of $43,647.00, or damages based on a November 5,1973, repudiation which indicates total damages of $127,-678.89; as well as (3) liquidated damages pursuant to the contract which indicates total damages of $19,468.46 (not $18,623.45 as computed by the Weyrauchs and by the trial court). We have made no independent damage computation but the Weyrauchs agree that this correction should be made.

We will first consider the elevator company’s argument thát subsection lb of Section 41-02-98, NDCC (2-719, UCC), applies and, because the contract provision as to liquidated damages was not expressly agreed to be the exclusive remedy, other optional remedies are available. The statutory language upon which the elevator company relies states:

“b. resort to a remedy as provided is optional unless • the remedy is expressly agreed to be .exclusive, in which case it is the sole remedy.”

The alternatives argued by the elevator company are not alternative remedies within, the portent of § 41-02-98, NDCC (2-719, UCC), but are alternative forms of the same .remedy — damages.1 Any other conclusion would negate the purpose of § 41-02-97, NDCC (2-718, UCC).

“The Code (U.C.C.) does not purport to affect the rules governing the extent of damages recoverable, * * 1 Anderson, Uniform Commercial Code, 2d Ed., § 1-106:6, at 51.

We need not consider whether a liquidated damage clause would be the sole remedy in a case where the alternative remedies urged are specific performance [as was the case in Carolinas Cotton Growers Association, Inc. v. Arnette (D.C.S.C.1974), 371 F.Supp. 65, and in Miller Yacht Sales, Inc. v. Scott, 311 So.2d 762 (Fla.App.1975)], or injunction, rescission, or other judicial remedy.2

[50]*50When the elevator company urged the trial court, and now this court, to allow it to present alternative methods of computing damages, the concern shifted to § 41-02-97, NDCC (2-718, UCC), relating to limitation of damage, to § 9-08-04, NDCC, relating to the validity of an agreement for liquidated or other limited damages, and to § 41-02-19, NDCC (2-302, UCC), to test its unconscionability.3 The elevator company challenges the adequacy of liquidated damages, claiming that, in this case, the course of performance of the Wey-rauchs, in effect, prevented it from taking steps on the contract performance dates to protect itself from incurring considerably greater losses than contemplated by the contract in providing for liquidated damages on specified dates. It also claims that course of performance constituted a modification of the written contract.

Although courts have been receptive to pleas of unconscionability raised by consumers, they have been reluctant to do so in commercial transactions. In any event, § 41-02-19, NDCC (2-302, UCC), assigns the issue of unconscionability exclusively to the court as a matter of law and requires the challenger to show that the clause was unconscionable at the time the contract was made, not just that it was unconscionable by hindsight. See White and Summers, Uniform Commercial Code, § 4-2, at 114— 116.

This court held recently: “When parties make a valid stipulation of damages, they are bound by it, regardless of the amount of actual damages incurred.” Bottineau Public Sch. Dist. No. 1 v. Zimmer, 231 N.W.2d 178, 180 (N.D.1975). Even if we were to agree with the elevator company that a liquidated damage clause is a separate remedy from other methods of computing damages [as this court may have treated it in Farmers Union Grain Terminal Ass’n v. Nelson, 223 N.W.2d 494

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Coach Works of Virginia v. Detroit Diesel Corp.
128 F. Supp. 2d 821 (D. Maryland, 2001)
Fisher v. Schmeling
520 N.W.2d 820 (North Dakota Supreme Court, 1994)
Constr. Assocs., Inc. v. CompaNy
446 N.W.2d 237 (South Dakota Supreme Court, 1989)
Construction Assoc. v. Fargo Water Equip. Co.
446 N.W.2d 237 (North Dakota Supreme Court, 1989)
Northern Illinois Gas Co. v. Energy Cooperative, Inc.
461 N.E.2d 1049 (Appellate Court of Illinois, 1984)
Pfizer Genetics, Inc. v. Williams Management Co.
281 N.W.2d 536 (Nebraska Supreme Court, 1979)
Buckley Towers Condominium, Inc. v. Buchwald
48 Fla. Supp. 14 (Miami-Dade County Circuit Court, 1978)
Boone v. Estate of Nelson
264 N.W.2d 881 (North Dakota Supreme Court, 1978)
Peoples Bank and Trust v. Reiff
256 N.W.2d 336 (North Dakota Supreme Court, 1977)
Albers v. NoDak Racing Club, Inc.
256 N.W.2d 355 (North Dakota Supreme Court, 1977)
Zuraff v. Empire Fire & Marine Insurance Co.
252 N.W.2d 302 (North Dakota Supreme Court, 1977)
Jamestown Farmers Elevator, Inc. v. General Mills, Inc.
413 F. Supp. 764 (D. North Dakota, 1976)
Farmers Cooperative Ass'n of Churchs Ferry v. Cole
239 N.W.2d 808 (North Dakota Supreme Court, 1976)
Ray Farmers Union Elevator Co. v. Weyrauch
238 N.W.2d 47 (North Dakota Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
238 N.W.2d 47, 18 U.C.C. Rep. Serv. (West) 683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ray-farmers-union-elevator-co-v-weyrauch-nd-1975.