Cargill, Inc. v. Kavanaugh

228 N.W.2d 133, 16 U.C.C. Rep. Serv. (West) 1196, 1975 N.D. LEXIS 191
CourtNorth Dakota Supreme Court
DecidedApril 4, 1975
DocketCiv. 9069
StatusPublished
Cited by32 cases

This text of 228 N.W.2d 133 (Cargill, Inc. v. Kavanaugh) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cargill, Inc. v. Kavanaugh, 228 N.W.2d 133, 16 U.C.C. Rep. Serv. (West) 1196, 1975 N.D. LEXIS 191 (N.D. 1975).

Opinion

SAND, Judge.

Plaintiff Cargill appeals from a judgment in its favor on the basis that such judgment is insufficient because improperly predicated, and from the trial court’s denial of its motion for modification of judgment.

The parties are in agreement on the following facts: That

On October 20,1972, the appellant Car-gill entered into a written contract to buy 7,500 bushels of # 1 hard amber durum wheat from the appellee Patrick J. Kava-naugh, a farmer.
The terms of that written contract provided that Kavanaugh was to deliver said wheat to Cargill at its Lakota, North Dakota, elevator between June 1, 1973, and June 15,1973, and that Cargill was to pay for said wheat $1.97 per bushel.
The contract further provided that should Kavanaugh default in delivery, he [Kavanaugh] “ . . . agrees to pay to [Cargill] as damages for default in delivery hereunder the difference between the above specified price [/. e., $1.97 per bushel] and the highest market price ... on the date of default.”
Kavanaugh defaulted in delivery as provided for in this contract.

In his answer and at the pre-trial conference Kavanaugh admitted he was in default on the written contract and offered to settle the matter on the basis of the liquidat *136 ed-damages clause contained in that contract. Cargill refused this offer of settlement and, at trial before the district court, sought to show that the parties had either orally agreed to modify the written contract so as to extend the delivery date (date of default) or that the parties had agreed to a new oral contract differing only from the superseded written contract in terms of a later delivery date (date of default).

The trial judge, after having heard the evidence in the matter, promulgated as one of his findings of fact, in Paragraph VII, the following:

“That the plaintiff [Cargill] has failed to establish that there was an extension of that [written] contract [of October 20, 1972] beyond the 15th day of June, 1973.”

Cargill challenges this finding of fact and requests this court declare the finding of fact to be otherwise.

It is so well settled as not to require citation that the scope of our review as to the findings of fact of a trial judge is limited by rule 52(a), North Dakota Rules of Civil Procedure, which provides, in pertinent part, that “Findings of fact shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge of the credibility of the witnesses.”

In In re Estate of Elmer, 210 N.W.2d 815, 820 (N.D.1973), this court, attempting to elucidate the term “clearly erroneous,” said:

“A finding is ‘clearly erroneous’ only when, although there is some evidence to support it, the reviewing court on the entire evidence is left with a definite and firm conviction that a mistake has been made. United States v. United States Gypsum Co., 333 U.S. 364, 68 S.Ct. 525, 92 L.Ed. 746 (1948). The mere fact that the appellate court might have viewed the facts differently, if we had been the initial trier of the case, does not entitle us to reverse the lower court. Nee v. Linwood Securities Co., 174 F.2d 434 (8th Cir. 1949); Wright & Miller, Federal Rules of Civil Procedure, Sec. 2585, p. 729 et seq.”

With these tenets in mind, we have thoroughly reviewed the record in this case and find that the evidence of record in support of Cargill’s assertion that the date of default was July 27, 1973 (when the relevant market price was $5.82 per bushel), rather than June 15, 1973 (when the relevant market price was $2.70 per bushel), consists of the testimony at trial of Mr. Kavanaugh and of Orville Peterson, Cargill’s Lakota elevator manager. 1

The gist of the testimony, even when we look at it in a light most favorable to Car-gill, which we are not required to do, is as follows:

In May 1973, Orville Peterson [hereinafter Peterson] told Kavanaugh that he could bring in the grain provided for in the contract at any time as there was elevator space available to handle it. Kavanaugh asked how much it would cost to buy his way out of the October 20, 1972, contract and Peterson quoted an approximate figure.
In early June and on June 10, 1973, Peterson told Kavanaugh he could begin delivering the wheat. Kavanaugh’s response of June 10 was that he was busy with Spring’s work and, implicitly, couldn’t deliver the wheat at that time or in the near future.
After June 15,1973 (the last day Kava-naugh could deliver the wheat contracted for without being in default under the written contract) Peterson contacted Ka-vanaugh several times about beginning to deliver the wheat but Kavanaugh was either noncommittal about doing so or had some excuse such as the fact that he was doing summer-fallowing or that he could not deliver in the rain.
*137 Finally, on July 24, 1973, after Peterson contacted Kavanaugh and requested him to deliver the grain, Kavanaugh, for the first time, said that he could not deliver the grain for the contract price and would like to see if things could be settled out somehow. Kavanaugh asked Peterson to contact his superior so some sort of settlement could be worked out. Cargill states that this was the first inkling that it had that Kavanaugh did not intend to honor the contract.
On July 25, 1973, Kavanaugh went to the office of Orville Peterson, where the latter asked him to sign an extension of the delivery date specified in the original contract. Kavanaugh refused to do so. Peterson also asked him to start delivering the grain but Kavanaugh said that he couldn’t do so while it was raining. Peterson then gave Kavanaugh until July 27 to deliver the grain.
On July 27, Kavanaugh said he would not deliver the grain for the original contract price and he was advised by Peterson that the contract was to be considered canceled.

We will examine these facts to determine whether the contentions of the appellant Cargill that the delivery date specified on the written contract was extended pursuant to an oral agreement to modify the written contract or whether (and this point seems to be more strongly contended by the appellant) the written contract was superseded by a later oral contract between the parties to deliver the grain have any substantial basis in law.

But because of appellant’s contention that the written contract was modified in part, we must first take cognizance of an applicable statute not cited by either of the parties, to wit, Section 9-09-06, North Dakota Century Code, which reads as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dale Exploration, LLC v. Hiepler
2018 ND 271 (North Dakota Supreme Court, 2018)
Lagerquist v. STERGO
2008 ND 138 (North Dakota Supreme Court, 2008)
BTA Oil Producers v. MDU Resources Group, Inc.
2002 ND 55 (North Dakota Supreme Court, 2002)
Felco, Inc. v. Doug's North Hill Bottle Shop, Inc.
1998 ND 111 (North Dakota Supreme Court, 1998)
Texaco, Inc. v. Mercury Exploration Company
994 F.2d 463 (Eighth Circuit, 1993)
Wagner v. Peterson
430 N.W.2d 331 (North Dakota Supreme Court, 1988)
Gorsuch v. Gorsuch
392 N.W.2d 392 (North Dakota Supreme Court, 1986)
Lohse v. Atlantic Richfield Co.
389 N.W.2d 352 (North Dakota Supreme Court, 1986)
First Trust Co. of North Dakota v. Conway
375 N.W.2d 160 (North Dakota Supreme Court, 1985)
Mitchell v. Barnes
354 N.W.2d 680 (North Dakota Supreme Court, 1984)
Dvorak v. Dvorak
329 N.W.2d 868 (North Dakota Supreme Court, 1983)
Storebo v. Foss
325 N.W.2d 223 (North Dakota Supreme Court, 1982)
Cooke v. Blood Systems, Inc.
320 N.W.2d 124 (North Dakota Supreme Court, 1982)
Trauger v. Helm Bros., Inc.
279 N.W.2d 406 (North Dakota Supreme Court, 1979)
Fiebiger v. Fischer
276 N.W.2d 241 (North Dakota Supreme Court, 1979)
Tower City Grain Co. v. Richman
262 N.W.2d 22 (North Dakota Supreme Court, 1978)
Halverson v. Pet, Inc.
261 N.W.2d 887 (North Dakota Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
228 N.W.2d 133, 16 U.C.C. Rep. Serv. (West) 1196, 1975 N.D. LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cargill-inc-v-kavanaugh-nd-1975.