Farmers Union Grain Terminal Association v. Keith Hermanson and Gordon McEvers

549 F.2d 1177, 21 U.C.C. Rep. Serv. (West) 61, 1977 U.S. App. LEXIS 14591
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 24, 1977
Docket76-1372
StatusPublished
Cited by6 cases

This text of 549 F.2d 1177 (Farmers Union Grain Terminal Association v. Keith Hermanson and Gordon McEvers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farmers Union Grain Terminal Association v. Keith Hermanson and Gordon McEvers, 549 F.2d 1177, 21 U.C.C. Rep. Serv. (West) 61, 1977 U.S. App. LEXIS 14591 (8th Cir. 1977).

Opinion

BRIGHT, Circuit Judge.

The parties to this appeal entered into grain sales contracts specifying certain delivery periods, but not providing that time was “of the essence.” We are presented with the question of whether the appellee grain sellers (Keith Hermanson and Gordon McEvers, farming partners) may cancel the contracts without notice because the appellant grain buyer (Farmers Union Grain Terminal Association) refused to accept delivery of the grain within a reasonable period of time. The district court (Judge Bruce M. VanSickle) held the sellers were entitled to cancel and dismissed the buyer’s suit for breach of contract. These contracts are governed by provisions of the Uniform Commercial Code, as adopted in North Dakota. We affirm that dismissal for reasons set forth in this opinion.

I.

The facts found by the district court stand essentially unchallenged on this appeal. In late 1972, the grain buyer, at its Lignite, North Dakota, elevator, entered into five separate grain purchase contracts with the grain sellers. The contracts called for delivery at the Lignite elevator of a total of 99,000 bushels of grain (wheat and durum) at certain dates through April 30, 1973, at a contract price of $2.05 per bushel for all grain except 19,000 bushels called for by the contract executed November 6,1972, which stipulated a price of $1.80 per bushel. The contracts specified periods of time for delivery as follows:

Contract No. Date of Execution Contracted Delivery Dates
5039013 11/6/72 Apr. 1 thru 30, 1973
5042109 & 5042111 12/18/72 Mar. 1 thru 31, 1973
5042110 12/18/72 ' Apr. 1 thru 30, 1973
5042112 12/18/72 Dec. 18 thru 31, 1972
(The contracts each characterize the last date for contract delivery as the "Expiration Date".)

The grain sellers made deliveries of more than 24,000 bushels of grain against these contracts through March 30, 1973. These deliveries substantially satisfied the obligation to deliver the December grain and satisfied almost 60 percent of the requirement for grain to be delivered in March. From March 30, 1973 — the date of the last actual delivery under the contracts — until the end of July 1973, grain sellers repeatedly asked Mr. Hill, the elevator manager, when they could make the remaining deliveries under the contracts. Repeatedly, Hill gave them the same response — that he would let them know when they could make their deliveries.

Finally, on August 1, 1973, the farmers, after consulting an attorney, wrote the grain buyer at its St. Paul office: “You are hereby notified that do [sic] to your breach of grain contracts, we have declared these contracts terminated: [identifying the pertinent contracts in question by number, date, quantity and delivery date].” Although the letter recited “termination,” the parties and the district court recognized the letter as a cancellation of the agreement.

*1180 Each contract contained the following provisions material to- this lawsuit:

Buyer shall not be liable in any respect for failure or delay in the fulfillment or performance of this contract if hindered or prevented directly or indirectly by Acts of God, freight embargoes, or other causes reasonably beyond the control of Buyer.
If any part of this contract remains unfilled at Expiration Date, Buyer reserves the right, without further notice to Seller, to extend the time of delivery or to declare Seller in default of the unfilled portion of the contract. In the event of default on the part of Seller, Seller agrees to pay to Buyer, as liquidated damages, any loss resulting from the difference between the contract price herein and the market price of grain of like grade at the close of the market on the Expiration Date.

We herein refer to the second paragraph quoted above as an “extension clause.” The district court discussed the buyer’s contention that an existing boxcar shortage excused buyer’s failure to accept delivery of the grain on prescribed delivery dates or reasonably thereafter and found buyer’s delay to be unreasonable.

Sellers claim that Buyer first breached the respective contracts by failing to accept deliveries at the Lignite elevator within the respective contractually prescribed delivery dates — or reasonable times thereafter. Buyer, denies that it first breached the respective contracts, claiming that boxcar shortages, well known to Sellers and reasonably beyond the control of Buyer, prevented Buyer from transporting its grain to market. Thus, due to a lack of storage space, Buyer claims it was precluded from accepting further deliveries from Sellers through July of 1973.
Did the Buyer unreasonably delay in accepting grain under the contracts involved in this action?
First of all, under the respective contracts, the risk of any loss of, or damage to, undelivered grain remained with the Sellers.
Secondly, on cross-examination, Mr. Hill admitted that during the months of May — July, 1973, he accepted for delivery a total of over 69,000 bushels of grain under contracts whose delivery dates were after April 30, 1973. In addition, cash purchases of grain by the elevator from January — July of 1973 were in excess of 39,000 bushels, and amounted to more than 22,000 bushels in June alone. In explaining his actions, Mr. Hill said that he was trying to be fair to all his customers and made his decisions as to what grain to accept for delivery without looking back to the contracts.
Thirdly, although Mr. Hill claimed to have made a reasonable effort to arrange for trucks — in addition to boxcars- — to transport the elevator’s grain to market, this claim was undercut by the testimony of Mr. Johnson, Hill’s successor as elevator manager. Johnson took over from Hill in August of 1973 and was successful in obtaining 28 trucks in that month alone, equaling the number Hill had obtained for the whole previous 7 months.

The district court concluded:

Since Buyer unreasonably delayed in accepting deliveries under the contracts, and since such delays were not the result of “causes reasonably beyond the control of Buyer,” Buyer breached the contracts by not calling for deliveries prior to August 1, 1973. Thus, Sellers were within their rights under N.D.C.C. § 41-02-82(6) in cancelling the contracts and selling their grain in the open market.

Appellant grain buyer contends here as it did in the district court that the elevator extended the March and April delivery dates for grain to an indefinite time pursuant to the extension clause in these contracts and, therefore, in the absence of notification of termination under UCC § 2-309 (N.D.Cent.Code § 41-02-26), the farmers, not the elevator, breached the contract. The district court rejected this contention on the assumption that the duration of any extension under the contracts lasted only *1181

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hansen-Mueller Co. v. Gau
838 N.W.2d 138 (Court of Appeals of Iowa, 2013)
Smith v. Palm Beach Eurocar, Inc.
15 Fla. Supp. 2d 48 (Florida County Courts, 1986)
KLT Industries, Inc. v. Eaton Corp.
505 F. Supp. 1072 (E.D. Michigan, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
549 F.2d 1177, 21 U.C.C. Rep. Serv. (West) 61, 1977 U.S. App. LEXIS 14591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farmers-union-grain-terminal-association-v-keith-hermanson-and-gordon-ca8-1977.