Earle Industries, Inc. v. Circuit Engineering, Inc. (In Re Earle Industries, Inc.)

88 B.R. 52, 1987 WL 47722
CourtDistrict Court, E.D. Pennsylvania
DecidedMarch 29, 1988
DocketBankruptcy No. 86-00869G, Adv. No. 86-0382G, Misc. No. 87-0598
StatusPublished
Cited by3 cases

This text of 88 B.R. 52 (Earle Industries, Inc. v. Circuit Engineering, Inc. (In Re Earle Industries, Inc.)) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earle Industries, Inc. v. Circuit Engineering, Inc. (In Re Earle Industries, Inc.), 88 B.R. 52, 1987 WL 47722 (E.D. Pa. 1988).

Opinion

ORDER

CAHN, District Judge.

AND NOW, this 28 day of March, 1988, upon consideration of the Recommendation and Memorandum Opinion of the Bankruptcy Court, IT IS ORDERED that the findings of fact and conclusions of law submitted by the Bankruptcy Court are ADOPTED by the District Court.

JUDGMENT is ENTERED in favor of the plaintiff and against the defendant in the amount of $4000.00.

*53 The Memorandum Opinion of the Bankruptcy Court is approved in its entirety, except as to footnote 3.

The clerk of this court is directed to close the docket of this case.

MEMORANDUM OPINION

BRUCE I. FOX, Bankruptcy Judge:

This is an adversary proceeding to determine plaintiff’s right to collect “cancellation charges” of $4,000.00 based on defendant’s cancellation of an alleged sales contract for failure to make timely delivery. The parties dispute whether a contract existed at all and if so, whether time of delivery was a material term of that contract. Because I have previously ruled that this adversary proceeding is non-core within the meaning of 28 U.S.C. § 157(c)(1), 1 I recommend the following Findings of Fact and Conclusions of Law for consideration by the District Court:

FINDINGS OF FACT

1. Earle Industries, Inc. (“Earle”) the debtor/plaintiff, is a Pennsylvania corporation which designs and produces technical equipment for use in construction.

2. Circuit Engineering, Inc. (“CE”) is a Florida corporation which performs engineering work associated with construction projects.

3. In the middle of October, 1985, CE and Earle conducted preliminary discussions by telephone related to production by Earle of equipment necessary for a bridge project in which CE was involved.

4. Based on the discussions, Earle produced two diagrams of the proposed equipment which it forwarded to CE. Earle quoted CE a price of $17,800.00 and indicated that the equipment would take approximately ten weeks to produce.

5. On or about November 18, 1985, CE returned the diagrams to Earle with a letter to Earle president Bob Cragg which stated: “Please proceed with fabrication of this order at once. We need shipment ... in the first week of January, 1986. Let us know if there is any problem with that delivery date.” See Exhibit D-2.

6. At approximately the same time CE sent Earle a purchase order labeled Ac-knowledgement which set forth the $17,-800.00 price which had been quoted to CE by Earle. A box on the purchase order labeled “delivery date” was left blank. See Exhibit D-l.

7. Although the purchase order is dated October 16, 1985, undisputed testimony of Earle’s president, Bob Cragg, established that the purchase order was not received by Earle until after the letter requesting “fabrication.” This testimony was supported by a notation on the purchase order which read “confirming to Bob Cragg”.

8. Earle responded to the CE letter and purchase order with a form labelled “Acknowledgment” which again set forth the purchase price and which prominently featured a notation which indicated “To be shipped — end of January”. Earle’s acknowledgment also provided: “see attached Terms and Conditions of Sale”. See Exhibit D-3.

9. The “Terms and Conditions of Sale” referred to in Earle’s “Acknowledgment” stated inter alia:

GENERAL:
... We will use our best efforts to make delivery within the time specified, but it must be understood that causes beyond our control such as government priorities and allocations, difficulties in obtaining materials, strikes, accidents and default by subcontractors or suppliers may cause delay. We therefore cannot guarantee delivery as specified and your order will be accepted by us only on this condition. LIABILITY
Orders are accepted by us under the condition that we are not to be liable for losses, detentions or delays occasioned by accident, strikes, fire affecting our operations or the operations of our suppliers or any other cases beyond our control and no damages for delay in delivery will be allowed.
*54 CANCELLATION AND DEFERRED DELIVERIES
Orders placed cannot be cancelled ... except with our written consent and upon terms which shall indemnify us against all loss.

See Exhibit P-2.

10. Although no evidence was offered by either party regarding the reason for the delay in shipment, Earle was apparently unable to deliver the equipment by the end of January, 1986. Having not received delivery by January 31, 1986, CE sent Earle a letter cancelling its order. See Exhibit D-5.

11. Earle’s president, Mr. Cragg, estimated that as of January 31, 1986, Earle had spent approximately $1,500.00 on materials and 155 hours of labor at $20.00 per hour on the project, for total expenditures of $4,600.00. Earle nevertheless billed CE in early February, 1986 for $4,000.00 in “cancellation charges”, and seeks only $4,000.00 in its complaint. No other evidence of damages was presented by either party.

12. The equipment which was the subject of the contract was unique and could not be resold by Earle.

13. At trial, the parties agreed that the law of the Commonwealth of Pennsylvania applies to this dispute.

14. At trial, the only witness was Mr. Cragg. CE presented no witnesses and neither party presented any evidence as to a course of dealings between the parties or usages of trade as defined by 13 Pa.C.S.A. § 1205.

CONCLUSIONS OF LAW

1. The law governing this case is the Uniform Commercial Code governing sales, as adopted in Pennsylvania, 13 Pa.C.S.A. § 2101 et seq.

2. During the oral communications of the parties commencing in October, 1985, Earle conveyed an offer to design and produce certain equipment for CE at a price of $17,800.00. In support of the offer Earle generated two diagrams of the equipment which were forwarded to CE for inspection. No precise time of delivery was included as a component of the offer.

3. CE’s letter dated November 18, 1985, (D-2), stating “Please proceed with fabrication of this order at once” together with its purchase order dated October 16, 1985, (D-1), constitute “a definite and seasonable expression” accepting Earle’s offer within the meaning of 13 Pa.C.S.A. § 2207(a). By that acceptance, a contract was formed for sale of equipment at a $17,800.00 purchase price.

4. Since Earle’s offer contained no precise time of delivery, CE’s request for delivery “in the first week of January, 1986” constituted a proposal for an “additional term” within the meaning of 13 Pa.C.S.A. § 2207(b).

5. CE’s proposal for a specific time of delivery did not become part of the contract by operation of 13 Pa.C.S.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
88 B.R. 52, 1987 WL 47722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earle-industries-inc-v-circuit-engineering-inc-in-re-earle-paed-1988.