Ramos v. SimplexGrinnell LP

740 F.3d 852, 21 Wage & Hour Cas.2d (BNA) 1488, 2014 WL 243404, 2014 U.S. App. LEXIS 1225
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 23, 2014
DocketDocket 12-4901-cv
StatusPublished
Cited by11 cases

This text of 740 F.3d 852 (Ramos v. SimplexGrinnell LP) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ramos v. SimplexGrinnell LP, 740 F.3d 852, 21 Wage & Hour Cas.2d (BNA) 1488, 2014 WL 243404, 2014 U.S. App. LEXIS 1225 (2d Cir. 2014).

Opinion

CALABRESI, Circuit Judge:

' This ease raises two questions of New York State law that are unsettled and of importance to the relationship between the State’s administrative agencies and its courts, as well as to the functioning of New York’s labor law. It asks, first, whether a court should give deference not only to an agency’s substantive interpretation of a statute arising from an unrelated proceeding but also to its decision to enforce that interpretation only prospectively. And it asks, second, whether contracts committing parties to pay prevailing wages pursuant to section 220 of the New York Labor Law (“NYLL”) need to specify — when the scope of the statute’s coverage is unclear to the parties — what particular work the prevailing wages will be paid for. At oral argument, the Appellees stated that certification would be useful and appropriate. We agree, and we certify two questions to the New York Court of Appeals. See N.Y.C.R.R. § 500.27(a).

BACKGROUND

This case was brought by workers who installed, maintained, repaired, tested, and inspected fire alarm and suppression systems in public and private buildings in *854 New York for SimplexGrinnell LP (“Simplex”). They claimed that, since at least February of 2001, Simplex did not pay them “prevailing wages” for their labor on “public works” in violation of NYLL section 220.

Though the case was initially brought in New York State court in 2007, it was removed to the United States District Court for the Eastern District of New York, where the parties consented to the jurisdiction of Magistrate Judge Steven Gold. Among other things, the plaintiffs brought third-party breach of contract claims based on Simplex’s failure to pay prevailing wages.

Because the plaintiffs had chosen to bring a third-party breach of contract suit in court, rather than in an Article 78 proceeding before the Department of Labor (“DOL”), see N.Y. C.P.L.R. § 7803, that agency had no formal role in the proceeding. However, while the litigation was ongoing, Simplex turned to the DOL and, on its own, asked for clarification. The plaintiffs were not privy to these communications between Simplex and the DOL.

As part of these communications, Simplex provided the DOL with matrices reflecting its views of what work was “covered” by the statute and therefore entitled to the payment of prevailing wages, and what work was not. In the matrices provided by Simplex, testing and inspection work was not listed as covered. The DOL posted the matrices on its website.

Subsequently, however, then-Commissioner of the DOL, Patricia Smith, ordered the matrices removed, and decided to issue an opinion letter on the matter. In that letter, the DOL concluded that testing and inspection work was “covered” work under section 220 of the NYLL and hence entitled to payment of the prevailing wage. Joint App’x at 330-33. The DOL reached this conclusion because, inter alia, testing and inspection work was a form of “maintenance work” a category that is covered under the statute. Id. at 330-31. The opinion letter noted that both New York State and Simplex’s own documents had treated testing and inspection work as within the category of “maintenance” work. Id. at 331-32.

But the DOL also stated that there had been “much confusion” as to whether it had earlier interpreted testing and inspection work as being covered and, for this reason, decided to enforce its decision prospectively only. Id. at 332. The opinion letter, issued on December 31, 2009, went into effect on the following day: January 1,2010. Id.

After the DOL issued its opinion letter to Simplex, the parties completed discovery in the Eastern District and filed cross-motions for summary judgment. Simplex relied on the DOL’s opinion letter in its motion.

The district court granted Simplex’s motion to dismiss the plaintiffs claims relating to testing and inspection work. Ramos v. SimplexGrinnell LP, 796 F.Supp.2d 346, 367-69 (E.D.N.Y.2011). 1 The court focused principally on the DOL’s opinion letter, and ruled that deference was due both to the conclusion reached in the letter — that testing and inspection work was to be paid prevailing wages— and to its decision to enforce that conclusion prospectively only. Id. at 368. That *855 is, the district court held that the plaintiffs’ testing and inspection claims for the period of the litigation could not proceed since the agency, in its own enforcement subsequent to its December 31, 2009 ruling, was requiring that prevailing wages only be paid prospectively. The district court reached this result because “[t]here was nothing irrational or unreasonable about the Commissioner’s decision to classify [testing and inspection] work as covered but to require that prevailing wages be paid only prospectively.” Id.

The district court also held that, under the circumstances, the plaintiffs’ third-party breach of contract claim could not be brought for the testing and inspection work. Id. at 368-69. Here, its reasoning was more complicated. The court stated that when it allowed the plaintiffs’ claims to proceed on their wore-testing and inspection work, see footnote 1, it had reasoned that since Simplex had contracted to pay a prevailing wage for such covered work, the plaintiffs could bring a third-party breach of contract claim for unpaid prevailing wages for such work. Id. at 365. The district based this conclusion on: (1) the notion that it is typically understood by parties such as Simplex, when they take on public works projects, that they need to pay the prevailing wages mandated by law; and (2) the fact that some of Simplex’s contracts did, in fact, contain provisions binding it to pay the prevailing wage. Id. at 362-65.

While the district court found that Simplex had generally agreed to pay prevailing wages in entering into its contracts, it nonetheless held that in light of the uncertainty at the time surrounding testing and inspection work, Simplex could not have had “reason to believe it would be required to pay prevailing wages for testing and inspection work it contracted to perform.” Id. at 368. “Thus, absent a provision in a particular contract explicitly requiring that testing and inspection work” be covered, there was “no basis for concluding” that Simplex had agreed to pay prevailing wages for such work. Id. The district court’s reasoning therefore appeared to be that a general agreement to pay the wages required by the statute applied only to work that was clearly understood by the parties to be covered by the statute at the time the contract was made and not to work subsequently held to be covered.

The plaintiffs appeal the district court’s grant of summary judgment against them on the testing and inspection claims. We review that grant de novo. See Mullins v. City of New York,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walton v. Comfort Systems
Second Circuit, 2025
Machuca v. Collins Bldg. Servs., Inc.
2024 NY Slip Op 30816(U) (New York Supreme Court, New York County, 2024)
Johnson v. Carlo Lizza & Sons Paving, Inc.
160 F. Supp. 3d 605 (S.D. New York, 2016)
Ramos v. SimplexGrinnell LP
Second Circuit, 2014
Roberto Ramos v. SimplexGrinnell LP
21 N.E.3d 237 (New York Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
740 F.3d 852, 21 Wage & Hour Cas.2d (BNA) 1488, 2014 WL 243404, 2014 U.S. App. LEXIS 1225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ramos-v-simplexgrinnell-lp-ca2-2014.