Raines Brothers, Inc. v. H. Michael Chitwood

CourtCourt of Appeals of Tennessee
DecidedJuly 3, 2014
DocketE2013-02232-COA-R3-CV
StatusPublished

This text of Raines Brothers, Inc. v. H. Michael Chitwood (Raines Brothers, Inc. v. H. Michael Chitwood) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raines Brothers, Inc. v. H. Michael Chitwood, (Tenn. Ct. App. 2014).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE May 15, 2014 Session

RAINES BROTHERS, INC. v. H. MICHAEL CHITWOOD ET AL.

Appeal from the Circuit Court for Hamilton County No. 11C286 Jacqueline S. Bolton, Judge

No. E2013-02232-COA-R3-CV - Filed July 3, 2014

This contract action stems from the defendant’s, H. Michael Chitwood’s, failure to pay for construction work that was performed by the plaintiff, Raines Brothers, Inc. (“Raines”). The work was performed on a home that was occupied by Mr. Chitwood but owned by a trustee, James Dreaden, who was also named as a defendant. Following a bench trial, the trial court awarded Raines a judgment against Mr. Chitwood and Mr. Dreaden (collectively “Defendants”) in the amount of $66,762.71. The trial court also awarded pre-judgment interest at the rate of eighteen percent per annum, beginning August 14, 2007. The trial court denied Raines’s claim for attorney’s fees. Defendants timely appealed the trial court’s ruling. Having determined that Raines adequately proved its entitlement to this amount pursuant to the parties’ contract, we affirm the trial court’s judgment of $66,762.71 against Mr. Chitwood. We reverse the trial court’s judgment against Mr. Dreaden. We modify the trial court’s award of the rate of interest from eighteen percent per annum to ten percent in accordance with relevant statutory and case law. We also reverse the trial court’s denial of Raines’s claim for attorney’s fees pursuant to the parties’ contract and remand for a determination of the proper amount of interest to be charged, as well as a reasonable award of attorney’s fees.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed in Part, Reversed in Part; Case Remanded

T HOMAS R. F RIERSON, II, J., delivered the opinion of the Court, in which C HARLES D. S USANO, J R., C.J., and D. M ICHAEL S WINEY, J., joined.

R. Wayne Peters and Gary L. Henry, Chattanooga, Tennessee, for the appellants, H. Michael Chitwood and James S. Dreaden. Sheri A. Fox and Marcie Kiggans Bradley, Chattanooga, Tennessee, for the appellee, Raines Brothers, Inc.

OPINION

I. Factual and Procedural Background

On July 31, 2006, Mr. Chitwood signed a written agreement with Raines to have construction work performed on his home. The contract constituted a “cost plus” agreement, providing that Mr. Chitwood would pay the cost of the work plus a fee of ten percent. Although Mr. Dreaden as trustee is the record owner of the home occupied by Mr. Chitwood, he was not a party to the construction contract. Instead, Mr. Chitwood signed the contract as “owner.”

Several provisions of the contract are pertinent to the issues presented in this appeal. The contract provides that Raines will maintain detailed accounting records regarding the project and that Mr. Chitwood will be afforded access to the records upon request. Further, the contract states that Mr. Chitwood will be billed on a monthly basis by Raines and that he will pay the monthly invoices within ten days of receipt. As expressed in the contract:

If the Owner does not intend to pay an Invoice within the required period, the Owner agrees to notify RBI as soon as possible but no later than 10 days of receipt of the Invoice. In the event the Owner fails to pay any payment, in whole or in part, due hereunder, RBI may cease work without breach of this contract pending payment. The Owner agrees to pay any costs to RBI associated with the collection of any past due payments due RBI including interest.

The contract also contains an attachment, which incorporates additional provisions, including the following:

The Owner and RBI agree to resolve all claims or disputes arising out of or relating to the Contract by working together until an agreeable solution is found. In the event a mutual resolution cannot be found and the dispute results in litigation, the prevailing party shall be entitled to reimbursement by the other party for reasonable costs, expenses, and fees incurred.

Raines began construction activities for Mr. Chitwood on August 3, 2006, utilizing a job number of 6069. The work for this first phase of the construction was substantially completed by October 2008, but not all of the work was completed to Mr. Chitwood’s

-2- satisfaction. In September 2009, Mr. Chitwood began transmitting letters to Matt Brown, Raines’s project manager, detailing various problems with the construction. Mr. Brown responded to Mr. Chitwood’s concerns and addressed the issues raised. At that time, Mr. Chitwood had not fully paid all charges relating to job number 6069, and after certain credits were applied by Raines, the remaining balance was calculated to be $76,762.71. According to Mr. Brown, a meeting was held with Mr. Chitwood on October 27, 2008, wherein Mr. Chitwood was provided with a full accounting of the cost of the project. Mr. Chitwood stated that he would pay the balance due in full. He further requested that Raines undertake additional work on another part of the residence.

The additional work ensued, designated for billing purposes as job number 8100. Although Mr. Chitwood paid the charges for job number 8100 in full, he did not pay the balance due regarding job number 6069. Various letters were exchanged between Mr. Chitwood and Mr. Brown. Eventually, a meeting was conducted in January 2010 with Mr. Chitwood, Mr. Brown, David Hammel (chief operating officer of Raines), and John Steele (Mr. Chitwood’s comptroller) in attendance. At this meeting, Mr. Chitwood again agreed to pay the outstanding balance of $76,762.71 by April 2010. He also asked Raines to perform additional work. This subsequent agreement was memorialized in an email sent to Mr. Chitwood by Mr. Brown. Raines thereafter began the additional work, utilizing a billing job number of 0023. Mr. Chitwood paid in full the charges for job number 0023 but only paid $10,000.00 concerning job number 6069, leaving a balance due of $66,762.71.

Raines filed the instant action to recover the monies owed by Mr. Chitwood. He also named Mr. Chitwood’s wife, Deborah Chitwood,1 and Mr. Dreaden as defendants. The claims alleged included breach of contract, breach of duty of good faith and fair dealing, unjust enrichment, quantum meruit, and conversion. Raines also sought attorney’s fees and injunctive relief to prevent Mr. Dreaden from selling the real property or otherwise interfering with Raines’s ability to establish a lien upon its title.

Defendants filed a motion to dismiss, which was denied by the trial court. Defendants subsequently filed answers denying liability. Mr. Chitwood filed a counterclaim for breach of contract, promissory fraud, defective work, and violations of the Tennessee Consumer Protection Act. Following discovery, Defendants moved for partial summary judgment as to the claim for injunctive relief and all claims against Mr. Dreaden. The trial court granted partial summary judgment on the claim for injunctive relief, finding that Raines had failed to demonstrate that injunctive relief was necessary to prevent immediate and irreparable harm. The trial court denied the motion as to the claims against Mr. Dreaden, however,

1 Mrs. Chitwood passed away during the pendency of this litigation, and Raines entered a voluntary nonsuit regarding the claims against her.

-3- finding that he was an essential party to the action at bar.

A trial was conducted on July 25, 2013. Raines’s witnesses included Mr. Brown; Tim Hall, the on-site job superintendent; Marvin Cornelison, president and CEO of Raines; Mr. Hammel; and Mr. Steele. These witnesses established that the work requested by Mr. Chitwood on the residence had been timely completed and conformed to a high standard of quality. Mr. Brown and Mr. Hammel testified that many of the concerns Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re CALEB L.C.
362 S.W.3d 581 (Court of Appeals of Tennessee, 2011)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Cracker Barrel Old Country Store, Inc. v. Epperson
284 S.W.3d 303 (Tennessee Supreme Court, 2009)
Allstate Insurance Co. v. Watson
195 S.W.3d 609 (Tennessee Supreme Court, 2006)
Citizens Real Estate & Loan Co. v. Mountain States Development Corp.
633 S.W.2d 763 (Court of Appeals of Tennessee, 1982)
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
McNeil v. Nofal
185 S.W.3d 402 (Court of Appeals of Tennessee, 2005)
Paschall's, Inc. v. Dozier
407 S.W.2d 150 (Tennessee Supreme Court, 1966)
Kerner v. Gilt
296 So. 2d 428 (Louisiana Court of Appeal, 1974)
Brunswick Acceptance Co., LLC v. MEJ, LLC
292 S.W.3d 638 (Court of Appeals of Tennessee, 2008)
McCarty v. McCarty
863 S.W.2d 716 (Court of Appeals of Tennessee, 1992)
Brewer v. Lawson
569 S.W.2d 856 (Court of Appeals of Tennessee, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Raines Brothers, Inc. v. H. Michael Chitwood, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raines-brothers-inc-v-h-michael-chitwood-tennctapp-2014.