Rackers and Baclesse, Inc. v. Kinstler

497 S.W.2d 549, 1973 Mo. App. LEXIS 1580
CourtMissouri Court of Appeals
DecidedJune 4, 1973
DocketKCD26167
StatusPublished
Cited by16 cases

This text of 497 S.W.2d 549 (Rackers and Baclesse, Inc. v. Kinstler) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rackers and Baclesse, Inc. v. Kinstler, 497 S.W.2d 549, 1973 Mo. App. LEXIS 1580 (Mo. Ct. App. 1973).

Opinion

FRED E. Judge, SCHOENLAUB, Special

This action was brought by appellant to establish and enforce a mechanic’s lien in the sum of $13,035.94 for material used in the construction of a dwelling for John F. Kinstler and Gretta E. Kinstler. The case was tried to the court without a jury. After trial but before judgment, John F. Kinstler died. Judgment was entered in favor of appellant and against respondent Gretta E. Kinstler in the sum of $6,323.11, which was also declared to be a lien on the real estate and prior and superior to an existing mortgage. Appellant’s Motion to Amend Judgment or for a New Trial was overruled, and it appeals.

On October 11, 1967, the Kinstlers entered into a contract with one Henry Ge-meinhardt for the construction of a house ' to be built on a lot owned by J. Raymond Brummet and Freda M. Brummet, Keith W. Major and Gladys Major, and Robert J. Major and Edith Major. Gemeinhardt started construction, but in March, 1968 notified the Kinstlers that he would not complete the house. John F. Kinstler then took over as his own contractor and completed the house. On September 18, 1968, the property was conveyed to the Kinstlers by the Brummets and Majors, and a loan transaction with General American Life Insurance Company was closed. An escrow account in the sum of $14,600.24 was established to cover the mechanic’s lien claim.

After Gemeinhardt abandoned the job, Kinstler contacted each of the subcontractors, inquired of them concerning the work they had done and their bills to date, and asked if they were interested in completing the job. It was agreed that they would continue and that the Kinstlers would pay them in full for their work. Kinstler also talked with Buell Baclesse, appellant’s president. He was advised by Baclesse that the balance due from Gemeinhardt was $5,100.00, Kinstler testified that he told Baclesse he would pay him every pen *552 ny he was legally obligated to pay. He further testified that he was satisfied that the work the subcontractors had bills for was in the house, but that “everything just didn’t smell right” with appellant’s bill, that he had paid out money to Gemein-hardt and thought appellant had been paid, and that other business transactions between Gemeinhardt and Baclesse had created further suspicions. In addition, Kin-stler found that several items furnished to Gemeinhardt and billed to the Kinstler property were not used on the Kinstler home, but on other properties owned by Gemeinhardt.

The trial court found that the items furnished between November 6, 1967 and March 18, 1968, totaling $6,338.56, were sold to Henry Gemeinhardt as the original contractor and that he was a necessary and indispensable party to the action. The Court further held that since Gemeinhardt was not joined as a defendant, judgment for the amount due on these materials could not be entered against any of the named defendants and the real estate could not be impressed with a lien for such items. Judgment was entered in favor of appellant and against respondent Gretta E. Kinstler in the sum of $6,323.11, the amount due for the materials furnished between April 1, 1968 and July 31, 1968, and the property was charged with a lien in that amount. Gretta E. Kinstler, Adminis-tratrix of the estate of John F. Kinstler, was substituted as an additional party defendant after judgment but before this appeal.

Our review of this court-tried case, governed by Rule 73.01(d), V.A.M.R., is upon both the law and the evidence as in suits of an equitable nature, deferring, however, to the trial court’s findings upon controverted factual matters. Madget v. Jenkins, 461 S.W.2d 768, 773 (Mo.1970); Jeff-Cole Quarries, Inc. v. Bell, 454 S.W. 2d 5, 12 (Mo.1970); Schroeder v. Prince Charles, Inc., 427 S.W.2d 414, 420 (Mo.1968). Consideration shall be given by this court to all evidence it deems admissible, excluding from consideration evidence improperly admitted. Madget v. Jenkins, supra.

Appellant contends first that, by agreeing and assuming to pay outstanding claims for materials and labor of some subcontractors, and by knowingly availing themselves of the acts and retaining the benefits of the transactions between Ge-meinhardt and appellant, the Kinstlers made and constituted Gemeinhardt their agent, and were bound and concluded by his transactions, or that by agreeing to pay the claims of the subcontractors they became from that time the principal contractor, both as to the materials already furnished and to those subsequently furnished.

The relation of principal and agent is created by manifestation of consent of one person to another that the other shall act on his behalf and subject to his control, and consent by the other so to act. Utlaut v. Glick Real Estate Company, 246 S.W.2d 760, 763 (Mo.1952). One cannot be an independent contractor and at the same time be an agent for the same purposes, and the very existence of a contract establishing an owner independent contractor relationship and performed by the contractor is wholly inconsistent with the existence of an agency. Jeff-Cole Quarries, Inc. v. Bell, 454 S.W.2d 5, 14 (Mo.1970).

The contract between the Kinstlers and Gemeinhardt provided that Gemeinhardt was to furnish all of the materials and perform all of the work shown on the working drawings and described in the specifications. Gemeinhardt did in fact commence performance under the contract as a general contractor by employing all the subcontractors and purchasing all the materials. Respondents’ evidence further established that although the Kinstlers knew where the materials were being purchased, and on a number of occasions met with Gemeinhardt at appellant’s lumberyard to pick out items for the house, the choice of subcontractors and materialmen was made *553 by Gemeinhardt alone. Buell Baclesse also testified that although the Kinstlers were in his store and lumberyard many times, they did not personally order any items or materials. He further testified that it was customary for the property owner to consult with the material supplier from time to time with regard to materials to be used in construction.

The contract clearly established an owner independent contractor relationship. There was no evidence of any actions on the part of the Kinstlers or Gemeinhardt consistent with a principal agency relationship, nor was there any evidence that Bac-lesse considered or treated Gemeinhardt as the agent of the Kinstlers. He looked to Gemeinhardt for payment, billing him on a monthly basis. No statements were sent to the Kinstlers. He dealt with and regarded Gemeinhardt as an independent contractor and did not rely upon any claimed agency. He cannot now reverse his position. Jeff-Cole Quarries, Inc. v. Bell, supra. The materials furnished between November 6, 1967 and March 18, 1969 were sold to Ge-meinhardt as the general contractor for the Kinstlers and must be considered as having been sold under a contract separate from that under which materials were later furnished directly to the Kinstlers. As to these materials, Gemeinhardt was a necessary and indispensable party to any suit to enforce a lien against the Kinstlers. Section 429.190 RSMo 1969, V.A.M.S.; Macklind Inv. Co. v. Ferry, 341 Mo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parshall v. Buetzer
195 S.W.3d 515 (Missouri Court of Appeals, 2006)
East v. Galebridge Custom Builders, Inc.
839 S.W.2d 720 (Missouri Court of Appeals, 1992)
Collegiate Enterprises, Inc. v. Otis Elevator Co.
650 F. Supp. 116 (E.D. Missouri, 1986)
Grgic v. Cochran
689 S.W.2d 687 (Missouri Court of Appeals, 1985)
Green Quarries, Inc. v. Raasch
676 S.W.2d 261 (Missouri Court of Appeals, 1984)
Pillsbury Co. v. Pike Grain Co.
527 F. Supp. 1013 (E.D. Missouri, 1981)
Emcasco Insurance Co. v. Donnelly
607 S.W.2d 460 (Missouri Court of Appeals, 1980)
George v. Lemay Bank & Trust Co.
618 S.W.2d 671 (Missouri Court of Appeals, 1980)
Crist Sod Co. v. Bruce
599 S.W.2d 43 (Missouri Court of Appeals, 1980)
State Ex Rel. State Highway Commission v. City of St. Louis
575 S.W.2d 712 (Missouri Court of Appeals, 1978)
State v. Davis
557 S.W.2d 41 (Missouri Court of Appeals, 1977)
Pelligreen v. Century Furniture & Appliance Co.
524 S.W.2d 168 (Missouri Court of Appeals, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
497 S.W.2d 549, 1973 Mo. App. LEXIS 1580, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rackers-and-baclesse-inc-v-kinstler-moctapp-1973.