Bybee v. Dixon

380 S.W.2d 539, 1964 Mo. App. LEXIS 619
CourtMissouri Court of Appeals
DecidedJune 18, 1964
Docket8257
StatusPublished
Cited by14 cases

This text of 380 S.W.2d 539 (Bybee v. Dixon) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bybee v. Dixon, 380 S.W.2d 539, 1964 Mo. App. LEXIS 619 (Mo. Ct. App. 1964).

Opinion

STONE, Judge.

For materials alleged to have been purchased and work alleged to have been done in connection with the remodeling of a dwelling house, plaintiff O. H. Bybee sought a personal judgment for $1,164.93 with interest against defendants, Fred Dixon and Jennie Dixon, husband and wife, and a lien therefor upon “one square acre” on which the house was situate. Defendants’' counterclaim prayed damages of $10,000 for breach of an alleged oral contract by which (so it was alleged) plaintiff “agreed to furnish all labor and substantially all the materials” for the remodeling at a cost “of not more than $6,500.” Trial by the court sitting as a jury resulted in judgment for defendants on plaintiff’s petition and judgment for plaintiff on defendants’ counterclaim. This appeal is by plaintiff from the adverse-judgment on his petition. Since defendants, did not appeal, we are not concerned with the judgment on the counterclaim. Wilson v. Motors Insurance Corp., Mo.App., 349 S.W.2d 250, 251.

The two-story frame dwelling house under discussion (hereinafter referred to as-the house) was located on a twenty-acre-tract inherited by defendant Jennie Dixon (hereinafter referred to as defendant Jennie) in 1959 or 1960. During the Summer-of 1960, defendants talked with plaintiff, a carpenter for thirty years, about remodeling-the house. At first, defendants wanted to-take off the old roof and the second story, thus converting the house into a one-story structure. Later, they decided to remodel, but not remove, the second story. On the-ground level, the major items were to be a new bedroom, utility room and two-car garage, a new brick fireplace in the living-room, added closets, new windows, floors, and kitchen cabinets, and complete rewiring. These discussions resulted in defendants” employment of plaintiff to do the contemplated remodeling. Two other carpenters,. Holden and Tandy by name, who had worked for plaintiff on other jobs, were to< assist on this one, but plaintiff was to be “in charge on the job.” At the end of each, week, plaintiff, Holden and Tandy were to-be paid by the hour (at wage rates not shown in evidence) for work done during-that week. With respect to materials for the project, plaintiff testified that defendant *541 Jennie “requested we get everything and store it in the barn * * * to have it ready to use when we got to it,” but the record discloses no agreement as to whether the suppliers should charge such materials to plaintiff or to defendants.

Defendant Jennie testified that, prior to entering upon the remodeling, plaintiff had assured her that the entire project “would not cost over $6,000 or $6,500.” Plaintiff conceded that his “first figures estimate” had been “about $5,000,” but he said that neither this nor any other total cost figure had been given to defendant Jennie because she had made changes in the project “before my [plaintiff’s] figures were turned in.” In fact, plaintiff insisted that at the outset defendant Jennie was interested only in “how much * * * it took to last until about the first of the year [1961]” when some funds would be distributed to her from an estate in probate, and that he estimated this interim monetary requirement at $1,500. In any event, there was no oral agreement upon a definite total cost figure, and there was no written contract covering any phase of the project.

Holden and Tandy began work on the project during the latter part of September 1960. Plaintiff himself moved to the project a short time later after finishing another job. Work proceeded until the latter part of March 1961, when defendants ran out of funds and (in plaintiff’s words) defendant Jennie “laid us off.” “She was supposed to tell us when she got the loan to proceed with the work, and then I checked * * * once or twice to see if they had gotten the loan, and they had not, and so * * * it just died down that way, and I [plaintiff] never did hear any more.” When plaintiff, Holden and Tandy were laid off, the project was (to adopt plaintiff’s estimate) “a little over half completed.” At that time, defendants already had expended on the project approximately $4,000 for labor and $4,800 for materials. Of the $4,800 for materials, $4,180.61 had been paid to Carl Junction Lumber Company which plaintiff said “belonged to me.”

Plaintiff’s lien account included (a) a multitude of bathroom and plumbing items (covering four pages of the transcript) furnished by Joplin Supply Company on twelve different dates from November 1, 1960, to February 22, 1961, billed by Joplin Supply to plaintiff for the aggregate sum of $730.89, and in the lien account rebilled by plaintiff to defendants for the aggregate sum of $924.18, (b) formica furnished by H & H Manufacturing Company on November 29 and December 6, 1960, and March 10, 1961, billed by H & H to plaintiff for the aggregate sum of $66.75, and in the lien account rebilled by plaintiff to defendants for the aggregate sum of $86.77, (c) a pilot burner for a hot water tank furnished by Nance Hardware Company on January 16, 1961, billed by Nance to plaintiff at $3.06, and in the lien account rebilled by plaintiff to defendants at 3.98, (d) “bricks” (quantity, quality and size not given) furnished by Carl Junction Lumber Company to plaintiff on a date and at a price not shown, and in the lien account rebilled by plaintiff to defendants at $55, and (e) “labor” (for “about 46 hours,” so plaintiff stated upon trial) billed in the lien account at $95. Both defendants testified that plaintiff had assured them that they were to have all materials at his (plaintiff’s) cost; but, denying that, plaintiff’s explanation of the prices at which materials were charged in the lien account was that “I get 25 per cent [additional] which is regular retail price * * * plus 5 per cent for installing it.”

Finding that “a material portion of the work done by the plaintiff was not done in a good and workmanlike manner” and that “not all the materials in the lien statement were used in the defendants’ house,” the trial court entered judgment for defendants on plaintiff’s petition. Both of the quoted findings were supported by substantial evidence. Defendants’ witness Allmendinger, an experienced residential contractor who *542 had inspected the house after plaintiff, Holden and Tandy had been laid off, summed up his detailed testimony concerning specific items by stating that the quality of workmanship in the remodeling project had been very poor, that 1 it was “all poorly constructed,” and that he had seen nothing which was “skillfully done, good workmanship.” Plaintiff himself conceded that most of the bathroom and plumbing items furnished by Joplin Supply Company, which (as we have noted) accounted for $924.18 of the $1,164.93 billed in the lien account, had not been actually used before he and his fellow-workmen had been laid off, and he likewise admitted that he had no personal knowledge as to whether those items had been incorporated into the house later.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phipps v. Shelter Mutual Insurance Co.
715 S.W.2d 930 (Missouri Court of Appeals, 1986)
McCardie & Akers Const. Co., Inc. v. Bonney
647 S.W.2d 193 (Missouri Court of Appeals, 1983)
Dampier v. Nichols
593 S.W.2d 260 (Missouri Court of Appeals, 1980)
Kranz v. Kansas City
573 S.W.2d 88 (Missouri Court of Appeals, 1978)
Stockman v. Estate of Shelton
526 S.W.2d 349 (Missouri Court of Appeals, 1975)
Rackers and Baclesse, Inc. v. Kinstler
497 S.W.2d 549 (Missouri Court of Appeals, 1973)
Rolla Lumber Company v. Evans
482 S.W.2d 519 (Missouri Court of Appeals, 1972)
Tegethoff v. Charlestown, Inc.
466 S.W.2d 164 (Missouri Court of Appeals, 1971)
Buxton v. Horn
452 S.W.2d 250 (Missouri Court of Appeals, 1970)
M.F.A. Central Cooperative v. Harrill
405 S.W.2d 525 (Missouri Court of Appeals, 1966)
Hardin v. Ray
404 S.W.2d 764 (Missouri Court of Appeals, 1966)
Holman v. Fincher
403 S.W.2d 245 (Missouri Court of Appeals, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
380 S.W.2d 539, 1964 Mo. App. LEXIS 619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bybee-v-dixon-moctapp-1964.