Quinn Associates, Inc. v. Borkowski

548 A.2d 480, 41 Conn. Super. Ct. 17, 41 Conn. Supp. 17, 1988 Conn. Super. LEXIS 2
CourtConnecticut Superior Court
DecidedJune 14, 1988
DocketFile 330724
StatusPublished
Cited by3 cases

This text of 548 A.2d 480 (Quinn Associates, Inc. v. Borkowski) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quinn Associates, Inc. v. Borkowski, 548 A.2d 480, 41 Conn. Super. Ct. 17, 41 Conn. Supp. 17, 1988 Conn. Super. LEXIS 2 (Colo. Ct. App. 1988).

Opinion

Satter, J.

In this action the plaintiff, Quinn Associates, Inc., applies for an order confirming an arbitration award, and the defendant, Henry Borkowski, Jr., applies for an order vacating, modifying or correcting the award.

On May 15, 1984, the plaintiff and the defendant entered into a standard form of agreement between owner and architect under which the plaintiff agreed to perform architectural services for the defendant in connection with the design and construction of a professional office building. The contract provided that the plaintiff would be paid a basic compensation equal to 6 percent of construction costs upon the completion of each stipulated phase of the architectural services and a fixed hourly rate for additional services rendered. All outstanding sums payable to the plaintiff were to bear interest from the date due at the rate of 1.5 percent per month (18 percent per year).

The contract also provided: “All claims, disputes and other matters in question between the parties to this Agreement, arising out of or relating to this Agreement or the breaqh thereof, shall be deeided by arbitration in aecordanee with the Construction Industry Arbitration Rules of the American Arbitration Association . . . .”

*19 During the course of the agreement, disputes arose between the parties that resulted in the plaintiff’s exercising a right to terminate the contract and, on April 16, 1985, instituting arbitration proceedings to collect money it claimed was owed. The plaintiffs demand for arbitration, dated April 16,1985, and addressed to the defendant, was exercised under the May 15,1984 contract. The plaintiff identified the nature of the dispute as “contract balance due and owing claimant” and the claim or relief sought as $21,854.06. The defendant answered on May 21, 1985, by denying that any money was owed the plaintiff, and he interposed a counterclaim for $26,000 based on the plaintiffs breach and repudiation of the contract.

Frederick A. Clinton was duly appointed as the arbitrator and a total of five hearings was held between November 4, 1985, and April 10, 1986. During the course of the hearings, the basis of the plaintiff’s claim changed from a demand for compensation for additional services on an hourly rate to a demand for compensation on a percentage of the construction costs. Before the hearings terminated the plaintiff billed the defendant on the latter basis and, in its posthearing brief, demanded $49,889.53 as due it under the contract.

On June 17,1986, before the arbitrator had rendered an opinion, the plaintiff filed an amendment of the amount in demand, increasing the amount in the claim for relief sought section of the original arbitration demand from $21,854.06 to $49,889.53. The arbitrator, pursuant to rule 36 of the Construction Industry Arbitration Rules, reopened the hearings and allowed the defendant ten days in which to comment on the amendment. The defendant objected to the amendment on the ground that it should have been made during the hearings, asked for an opportunity to submit evidence to rebut the claim by showing a detailed accounting of the design expenses he incurred on the project *20 since the plaintiff terminated, and sought to present additional information on his counterclaim. On July 31, 1986, the arbitrator ruled to accept the amended demand and reclosed the hearings.

The arbitrator rendered his award on August 12, 1986. On the plaintiffs claim against the defendant, the arbitrator awarded the plaintiff $29,283, plus interest at the contractual amount of 1.5 percent per month commencing July 1, 1986; he denied the defendant’s counterclaim against the plaintiff; he imposed administrative fees and expenses of the American Arbitration Association and expenses of the arbitrator upon the defendant; and he concluded: “This award in [sic] full and final settlement of any and all claims and counterclaims submitted to this arbitration.”

The plaintiff duly applied to confirm the award, and the defendant applied to vacate, modify or correct it. At argument the defendant abandoned all the bases for his application but two: (1) the arbitrator exceeded his authority within the meaning of General Statutes § 52-418 (a) (4); and (2) the arbitrator was guilty of misconduct, within the meaning of General Statutes § 52-418 (a) (3). .

I

“Arbitration is a creature of contract and the parties themselves, by the agreement of submission, define the powers of the arbitrator.” Board of Education v. Waterbury Teachers’ Assn., 174 Conn. 123, 127, 384 A.2d 350 (1977). The agreement of submission in this case is the May 15,1984 contract between the parties, which provided: “All claims, disputes and other matters in question . . . arising out of or relating to this Agreement or the breach thereof, shall be decided by arbitration . . . .” The demand for arbitration identified the nature of the dispute as the contract balance due the plaintiff.

*21 In deciding the defendant’s claim that the arbitrator exceeded his powers, within the meaning of § 52-418 (a) (4), this court need only examine the submission and the award to determine whether the award conforms to the submission. Ramos Iron Works, Inc. v. Franklin Construction Co., 174 Conn. 583, 587-88, 392 A.2d 461 (1978). Here the submission covered all claims in question under the contract, and the award was in full and final settlement of all such claims. Thus, the award conforms to the submission and is within the authority of the arbitrator.

The defendant contends that the submission is restricted by the amount of $21,854.06 that the plaintiff claimed in the original demand for arbitration and that the arbitrator exceeded his power by awarding $29,283. The defendant cites no authority in Connecticut or elsewhere for this contention, and this court can find none. In Ramos Iron Works, Inc. v. Franklin Construction Co., supra, 586, and in Game-A-Tron Corporation v. Gordon, 2 Conn. App. 692, 693, 483 A.2d 620 (1984), the amount of the claim or relief sought in the demand for arbitration was not held to restrict the submission. In both those cases, however, the amount of the award was less than the amount sought, so the issue was not squarely faced by the court.

In this court’s view, it makes no sense for the amount of the claim or relief sought to constitute a restriction on the arbitrator. If the parties submitted to the arbitrator the question of whether a claimant should be compensated a specified sum, then, by awarding a different sum, the arbitrator exceeds his power. But when the submission is general, as here, and includes an agreement to decide by arbitration all disputes under the contract, the arbitrator is free to award more or less than the amount claimed.

*22 The essence of the submission is that the arbitrator resolve all disputes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lemma v. York & Chapel, Corp.
Connecticut Appellate Court, 2021
Saturn Const. v. State, Dept., Pub. Works, No. Cv97-0567867-S (Oct. 8, 1998)
1998 Conn. Super. Ct. 11918 (Connecticut Superior Court, 1998)
Estate of Brady v. Grosso, No. Cv93-0343254s (May 18, 1993)
1993 Conn. Super. Ct. 4867 (Connecticut Superior Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
548 A.2d 480, 41 Conn. Super. Ct. 17, 41 Conn. Supp. 17, 1988 Conn. Super. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quinn-associates-inc-v-borkowski-connsuperct-1988.