Saturn Const. v. State, Dept., Pub. Works, No. Cv97-0567867-S (Oct. 8, 1998)

1998 Conn. Super. Ct. 11918
CourtConnecticut Superior Court
DecidedOctober 8, 1998
DocketNos. CV97-0567867-S, CV 96-0556963-S
StatusUnpublished

This text of 1998 Conn. Super. Ct. 11918 (Saturn Const. v. State, Dept., Pub. Works, No. Cv97-0567867-S (Oct. 8, 1998)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saturn Const. v. State, Dept., Pub. Works, No. Cv97-0567867-S (Oct. 8, 1998), 1998 Conn. Super. Ct. 11918 (Colo. Ct. App. 1998).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION CONFIRMING ARBITRATION AWARD
The above-captioned matters arise out of a contract dispute between Saturn Construction Company ("Saturn") and State of Connecticut Department of Public Works ("the State") for the construction of a substantial portion of a medium-high security prison facility to house over seven hundred prisoners in Newtown, Connecticut. After completion of the project the State commenced arbitration proceedings pursuant to an arbitration clause in its contract with Saturn. It sought damages for Saturn's alleged failure to timely and properly perform its duties under the construction contract. Saturn in turn asserted a number of counterclaims against the State for its performance on the project. Following an extensive schedule of hearings over a period of four years an arbitration panel consisting of three individuals selected by the parties issued an arbitration award which found that Saturn was entitled to a net award against the State in the amount of $5,048,722.13.

Saturn now seeks an order confirming the arbitration award, and the State seeks an order vacating, modifying and/or correcting the award. CT Page 11919

The following issues have been raised:

1. Was the submission to arbitration restricted or unrestricted?

2. If the submission was unrestricted, are there grounds to permit vacating the award under General Statute § 52-418(a)(4) or modifying the award under General Statutes § 52-419?

First: The Court finds that the arbitration submission was unrestricted. The arbitration clause in the contract provides:

"Any dispute arising out of the awarding of the contract for this project by the Commissioner of Administrative Services, or performance thereunder, shall be submitted to arbitration under the rules of the American Arbitration Association. Hartford, Connecticut shall be the locale where the arbitration is to be held."

The State's claims for arbitration were as follows:

"Nature of Dispute:

Breach of a contract for the construction of a prison facility in Newtown, Connecticut. Particularly, Respondent failed to perform its work in a timely and workmanlike manner, failed to complete portions of its work, failed to pay certain subcontractors and unjustifiably delayed other contractor's project work. Furthermore, Respondent submitted numerous non-meritorious claims for extra work allegedly performed in connection with the project. Finally, Respondent failed to provide future promised consideration in connection with Claimant's approval of Change Order No. 107 in the amount of $958,724.90."

"Claim or Relief sought:

All damages arising out of the Respondents failure to perform and/or complete its work including actual damages, liquidated damages and consequential damages. In addition, Claimant seeks an order directing Respondent to complete and/or correct its work, pay its subcontractors and reimburse the claimant for all expenditures associated with Claimants completion and/or correction of Respondents work. Finally, Claimant seeks an order directing the Respondent to refund all monies paid to Respondent CT Page 11920 in connection with Change Order No. 107."

The claims of Saturn also concerned its claims that the State had violated the terms of the contract.

Clearly, this was an unrestricted submission, which provides the arbitration panel with unlimited authority to resolve all of the parties' claims and defenses. "When the scope of the submission is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission . . . Thus, we have previously held that the parties should be bound by a decision that they contracted and bargained for, even if it is regarded as unwise or wrong on the merits." Saturn Construction Co. v. Premier Roofing Co.238 Conn. 293, 296, 304 (1996), quoting American Universal Ins. Co.v. Delgreco, 205 Conn. 178, 186-87 (1987) Garrity v. McCaskey,223 Conn. 1, 5-6 (1992).

Second: Even in the case of an unrestricted submission, the courts have recognized three grounds for vacating an award; (1) the award rules on the constitutionality of a statute; (2) the award violates clear public policy; (3) the award contravenes one or more of the statutory proscriptions of General Statutes § 52-418.

The State claims that the award of the arbitrators in this case contravenes subsection (4) of § 52-418. It claims that the arbitrators "have exceeded their powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made."

The State claims that the arbitrators exceeded their powers or imperfectly executed them because they disregarded Judge Sheldon's decision dated October 17, 1994 (No. CV-93-0704690-S). Judge Sheldon had been asked to interpret the liquidated clause set forth in Article 8, paragraph 1 of the General Conditions of the Contract. That clause provided that liquidated damages were to be assessed for Saturn's delay in completing its work under the contract on schedule. The measure of such damages was set at $1,000 per day for each calendar day beyond the 470-day contract completion period that Saturn's work remained uncompleted. Saturn had claimed that by including this language in the contract the State waived any right it might otherwise have had to recover other types of delay damages against Saturn. The State, on the other hand, claimed that the liquidated damages clause did not CT Page 11921 apply to delay damages to other contractors which Saturn might cause and the State might pay before the contract completion expired. Judge Sheldon held that the liquidated damages clause covered only damages "for each additional day beyond the time agreed for completion of the contract." He further held, however, that the liquidated damages clause did not cover other delay damages. He stated, "(u)nder this contract inter-contractor delay damages were to be fully paid by Saturn whenever it caused them to occur . . ."

In light of Judge Sheldon's decision, it is now the State's position that the arbitrators imperfectly executed their powers because they failed to award inter-contractor delay damages. The Court disagrees. Judge Sheldon merely decided that inter-contractor delay damages could be awarded. He did not say theymust be awarded if they were not found proven by the arbitrators.

In any event, the arbitrators did in fact receive evidence presented by the State in regard to its delay claims #s 6, 11 and 12. Under claim #12 the arbitrators found that there were 245 total days of delay of which 198 days were excusable and the balance of 47 days were inexcusable and were Saturn's responsibilities. It therefore awarded the State $47,000 in accordance with the liquidated damages clause. It did not award inter-contractor delay damages, but they were not required to do so if such delay damages were not proven to their satisfaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pratt, Read & Co. v. United Furniture Workers of America
70 A.2d 120 (Supreme Court of Connecticut, 1949)
Quinn Associates, Inc. v. Borkowski
548 A.2d 480 (Connecticut Superior Court, 1988)
American Universal Insurance v. DelGreco
530 A.2d 171 (Supreme Court of Connecticut, 1987)
Garrity v. McCaskey
612 A.2d 742 (Supreme Court of Connecticut, 1992)
Saturn Construction Co. v. Premier Roofing Co.
680 A.2d 1274 (Supreme Court of Connecticut, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
1998 Conn. Super. Ct. 11918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saturn-const-v-state-dept-pub-works-no-cv97-0567867-s-oct-8-connsuperct-1998.