Quick Communications, Inc. v. Michigan Bell Telephone Co.

515 F.3d 581, 2008 U.S. App. LEXIS 3101, 2008 WL 373477
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 13, 2008
Docket06-2103
StatusPublished
Cited by10 cases

This text of 515 F.3d 581 (Quick Communications, Inc. v. Michigan Bell Telephone Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quick Communications, Inc. v. Michigan Bell Telephone Co., 515 F.3d 581, 2008 U.S. App. LEXIS 3101, 2008 WL 373477 (6th Cir. 2008).

Opinion

*583 OPINION

BOYCE F. MARTIN, JR., Circuit Judge.

The Michigan Public Services Commission ordered Quick Communications Incorporated and Michigan Bell Telephone Company (d/b/a AT & T) to amend their interconnection agreement to conform with the Commission’s most recently approved service rates. Quick brought suit seeking declaratory and injunctive relief, arguing that the Telecommunications Act of 1996, the terms of the interconnection agreement, the Sierra-Mobile doctrine, and the Contract Clause of the United States Constitution prohibited the Commission’s action. The district court granted defendants’ motion for summary judgment on all of Quick’s claims. Quick now appeals.

I.

The Federal Telecommunications Act of 1996, 47 U.S.C. § 151 et seq. (1996), was intended to deregulate the telecommunications industry and spur competition. Under the Act, there are two types of service providers relevant to this action: (1) Incumbent Local Exchange Carriers (“ILECs”), and (2) Competitive Local Exchange Carriers (“CLECs”). ILECs are entities such as the defendant, AT & T, that held a monopoly on local telephone service. ILECs control the last mile through which every CLEC must access its customers. The Act mandates that ILECs provide access to its network to competitors (CLECs) through interconnection agreements. The ILECs are allowed to charge reasonable and nondiscriminatory rates for this access. 47 U.S.C. § 252(d). Those rates are established by state public utilities commissions — here, the Michigan Public Service Commission— through a cost methodology known as the Total Service Long Run Incremental Cost (“TELRIC”).

In order for the Commission to establish proper TELRIC rates, they require AT & T to conduct cost studies, 47 U.S.C. § 252(c)(2), which the Commission must approve. On August 30, 2002, AT & T filed an application with the Commission seeking a determination of its costs to provide services. AT & T’s application claimed that its then-current costs were significantly higher than those previously set by the Commission, and it sought a new determination.

On September 16, 2002, the Commission dismissed AT & T’s application and ordered AT & T to submit a new application with revised cost studies. Accordingly, on May 2, 2003, AT & T submitted its new application with a revised cost study. The Commission issued a notice directing any interested parties that wished to participate in the proceedings to file a “notice of intent to participate.” Quick never filed a notice.

On September 21, 2004, after a year and a half of extensive proceedings including expert testimony, exhibits, public comments and briefs, the Commission issued an order approving, subject to certain modifications, AT & T’s cost studies. On November 5, 2004, AT & T filed its proposed pricing schedule in compliance with the Commission’s September 21 Order. Quick, along with other CLECs had 45 days to submit comments, and AT & T had 21 days to respond to those comments. On December 20, 2004, Quick filed objections to the Commission’s order requiring the new pricing schedule be incorporated into existing interconnection agreements. Quick argued that incorporation of the new approved rates in its existing interconnection agreement required further negotiation. On January 25, 2005, the Commission rejected Quick’s and the other CLECs’ objections, stating the because it *584 had “substantially revised the costs proposed by AT & T ... there [was] no basis for further dispute resolution, negotiation, or delay.” The January 25 Order also required AT & T to “true-up” all charges billed under its interconnection agreements retroactive to November 6, 2004, the effective date of the new approved rates. On February 25, 2005, Quick and other CLECs petitioned for a rehearing, and on May 17, 2005, the Commission denied the petition.

II.

On June 25, 2005, after the Commission denied its petition for rehearing, Quick filed suit seeking declaratory and injunc-tive relief to prevent the pricing amendment to its interconnection agreement with AT & T from going into effect. Quick claimed the January 25, 2005 order violated its interconnection agreement with AT & T, the federal Telecommunications Act, the Sierrar-Mobile doctrine, and the Contract Clause of the United States Constitution.

On July 19, 2006, the district court granted summary judgment in favor of AT & T and the Commission on all of Quick’s claims. The district court held that (1) Quick had failed to show that the implementation ordered by the Commission was barred by the Telecommunications Act; (2) the Commission’s order did not violate the terms of the interconnection agreement; (3) the Sierrcir-Mobile doctrine was not implicated; and (4) the Contract Clause was not violated.

Quick appeals the district court’s grant of summary judgment.

III.

We must decide whether the Commission’s order to amend the Quick/AT & T interconnection agreement violated not only the agreement, but the Federal Telecommunications Act, the Sierrar-Mobile doctrine, and the Contract Clause of the United States Constitution. The applicable standard of review is more complex than the simple de novo standard that typically governs our review of summary judgment. When a district court’s decision on summary judgment is the result of a review of a state administrative body’s ruling, de novo review requires that the proper standard of review of the underlying state administrative ruling be applied. Mich. Bell Tel. Co. v. MFS Intelenet of Mich., Inc., 339 F.3d 428, 433 (6th Cir.2003).

AT & T argues that we should apply the de novo standard to our review of whether the Commission’s actions complied with the Telecommunications Act, but must apply the more deferential “arbitrary-and-eapricious” standard to our review of the Commission’s analysis of the interconnection agreement. This is incorrect. Because the Telecommunications Act governs the Commission’s interpretation of the interconnection agreement, de novo review applies to the question of whether the Commission’s order violated the Telecommunications Act, and the arbitrary and capricious standard applies to the Commission’s determinations of fact and state law. Id.

1. Does the Telecommunications Act allow the Commission to override terms of interconnection agreements when implementing new rate changes?

In its summary judgment order, the district court laid out the following background:

The Telecommunications Act of 1996 (the “Act”), 47 U.S.C. § 252

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North County Communications Co v. Qwest Corporation
824 F.3d 830 (Ninth Circuit, 2016)
Rochelle Johnson v. Patrick Donahoe
642 F. App'x 599 (Sixth Circuit, 2016)
Shemelia Burdett-Foster v. Blue Cross Blue Shield of MI
574 F. App'x 672 (Sixth Circuit, 2014)
Ohio Bell Telephone Co. v. Public Utilities Commission
844 F. Supp. 2d 873 (S.D. Ohio, 2012)
Firstcom, Inc. v. Qwest Corp.
555 F.3d 669 (Eighth Circuit, 2009)
American Express Travel Related Services, Inc. v. Kentucky
597 F. Supp. 2d 717 (E.D. Kentucky, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
515 F.3d 581, 2008 U.S. App. LEXIS 3101, 2008 WL 373477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quick-communications-inc-v-michigan-bell-telephone-co-ca6-2008.