Punton v. Sapp Bros. Construction Co.

300 P.2d 271, 143 Cal. App. 2d 696
CourtCalifornia Court of Appeal
DecidedAugust 6, 1956
DocketCiv. 5174
StatusPublished
Cited by6 cases

This text of 300 P.2d 271 (Punton v. Sapp Bros. Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Punton v. Sapp Bros. Construction Co., 300 P.2d 271, 143 Cal. App. 2d 696 (Cal. Ct. App. 1956).

Opinion

MUSSELL, J.

This is an action in which plaintiff secured a judgment for $7,822.02 and costs and a decree of foreclosure of a mechanic’s lien for work and labor done and performed and for materials furnished in the construction of an office building in San Diego. On June 25, 1954, plaintiff submitted a bid to the defendants (owner-builders) to furnish all labor and materials for the installation of suspended ceilings and acoustic tile work on the first and *697 second floors and on the penthouse in the building, using %-inch sheetrock and United States Gypsum Quietone ceilings. The amount of this bid was $8,795. After its submission, Walter Lee Berry, Jr., plaintiff’s authorized agent, had a conversation with David Sapp, one of the defendants, in which Sapp informed Berry that he had “cheaper prices” and that he would like to use gypsum tile but that Berry would have to get his price down. Berry then went to the building inspection department of the city of San Diego and talked with Mr. C. M. Bartholomew, a plan checker employed by the city. Berry asked for information as to the use of acoustical tile on the job without sheetrock and Bartholomew “checked back in the code—as he took it from the code, to see if it was permissible” to put up such an installation. Bartholomew concluded that it would be all right and so informed Berry, who then, on July 21,1954, submitted another bid proposing to furnish and install the ceilings with United States Gypsum perforated “Auditone,” mill finished with United States Gypsum flame resistant paint, all in accordance with the city building inspection regulations, outlined as Auditone, first and penthouse ceilings. ½" Auditone, second floor ceiling ... all interlocking edges stapled. ’ ’ The sum bid for the work and materials was $7,655. No mention was made in this bid of the installation of sheetrock and it was eliminated by Berry on the basis of the authorization by the building department.

On July 21, 1954, plaintiff and defendants entered into a subcontract agreement in writing wherein plaintiff agreed to do the acoustical tile work, including suspended ceilings, in all areas shown on the plans, and to furnish and install United States Gypsum perforated Auditone, mill finished with fire resistant paint, for the sum of $7,845. The use of sheetrock was not mentioned in the contract or in the second bid submitted by plaintiff and he had no knowledge of plans containing a specification that such sheetrock was required in the construction of the suspended ceilings when he started work on the contract on or about August 10, 1954.

On or about September 10,1954, after plaintiff had installed about 2,500 square feet of acoustical tile without the use of sheetrock, he was notified by the city that no further work was to be performed until the city had released the stop order. Berry then had a conversation with Sapp in which Berry informed Sapp of the stop order and Sapp said “Get down *698 there and get it squared away, because the job has got to keep going. We can’t stop it.” Berry then went to the building department and was there informed that it was necessary to put ⅝-inch sheetrock under the acoustical tile and that their previous advice to the contrary was wrong. Berry was advised that he could complete a small portion of the first floor of the building without the use of sheetrock and that it would be necessary to put %-inch sheetrock under the balance of the tile, an area of approximately 1,000 square feet. Berry then informed Sapp as to what had happened at the city building department office and stated to Sapp that he had to stop work unless sheetrock was used. Berry testified at the trial that Sapp then told him to “get the job going” and that they would have to install the sheetrock; that Sapp ordered the tile that was already erected torn down and stated that he had a deadline on the building; that Sapp told him to go ahead and put the sheetrock up if that was what it took to get the job done; that he, Berry, objected to the cost of the removal of the tile already in place and Sapp stated that he did not care about the cost, that he was interested in getting the job done so that they could move in on the first of November ; that he, Berry, then said “Well, will you give us a purchase order for what he have talked about here?” and Sapp replied, “Yes, I will, but get the job started. Get it rolling again.”

Berry purchased sheetrock for the job and installed it throughout under the acoustical tile, pursuant to the building department’s orders, and when he again asked Sapp for a purchase order for the installation of the sheetrock, Sapp stated that he would talk to his brother about it and would then give him the order. When the work was completed on September 28, 1954, Berry presented his bills to Sapp covering $1,881.60 for %-inch sheetrock, $56 for sheetrock on a partition, $110 for 40 hours overtime, and $84.50 for sheet-rock on an equipment room ceiling, a total of $2,132.10. The defendants refused to pay for these items, claiming that it was not their responsibility to have the sheetrock installed. Defendants paid $2,000 on the original contract and refused to pay the balance or the extra items covering the sheetrock installation. Plaintiff then filed a notice of mechanic’s lien on November 10, 1954, and his amended complaint for foreclosure of this lien was filed February 3, 1955.

The trial court found, among other things, that the installation of sheetrock was not called for in the agreement of July *699 21, 1954; that defendants Avere apprised of the requirement by the city of San Diego and ordered plaintiff to proceed in compliance with the building code of said city and to install sheetrock on all ceilings contracted for the installation of acoustical tile; that said installation of sheetrock was extra work on the building and was done with the knowledge and consent of defendants and that they waived the requirement of the contract that extras be ordered in writing by the contractor ; that defendants represented to plaintiff that a written purchase order would be given to plaintiff for said extra work and materials; that plaintiff, relying on said representation and upon demand of defendants that the said work be performed, did perform said extra work and install said extra material, all of the reasonable value of $1,881.60; that in addition to the installation of sheetrock, plaintiff, at the request of the defendants, performed other work and installed other material, all of the reasonable value of $250.50; that defendants refused to execute a written purchase order for said extra work and material; that plaintiff fully performed all of the conditions of the agreement of July 21, 1954, and fully complied with the demand of defendants in the performance of said extra work and the installation of said extra materials; that defendants contracted to pay for said extra work and materials and for the work performed pursuant to the contract of July 21, 1954, for the total sum of $9,977.10; that the sum of $2,000 had been paid, leaving a balance of $7,977.10 unpaid; that the defendants were entitled to offsets in the sum of $155.08, leaving a balance due of $7,822.02. Judgment was entered against the defendants for this amount and the foreclosure of the mechanic’s lien and they have appealed from the judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silbermann v. Shangri-La Construction CA2/7
California Court of Appeal, 2020
Kelly v. Teeters CA1/2
California Court of Appeal, 2015
Children's Hospital Central California v. Blue Cross of California
226 Cal. App. 4th 1260 (California Court of Appeal, 2014)
Meredith v. Marks
212 Cal. App. 2d 265 (California Court of Appeal, 1963)
1st Olympic Corp. v. Hawryluk
185 Cal. App. 2d 832 (California Court of Appeal, 1960)
C. F. Bolster Co. v. J. C. Boespflug Construction Co.
334 P.2d 247 (California Court of Appeal, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
300 P.2d 271, 143 Cal. App. 2d 696, Counsel Stack Legal Research, https://law.counselstack.com/opinion/punton-v-sapp-bros-construction-co-calctapp-1956.