Provo River Coalition v. Pena

925 F. Supp. 1518, 1996 U.S. Dist. LEXIS 6553, 1996 WL 250641
CourtDistrict Court, D. Utah
DecidedMay 7, 1996
Docket2:96-cv-00186
StatusPublished
Cited by3 cases

This text of 925 F. Supp. 1518 (Provo River Coalition v. Pena) is published on Counsel Stack Legal Research, covering District Court, D. Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Provo River Coalition v. Pena, 925 F. Supp. 1518, 1996 U.S. Dist. LEXIS 6553, 1996 WL 250641 (D. Utah 1996).

Opinion

MEMORANDUM DECISION AND ORDER

CAMPBELL, District Judge.

On February 29, 1996, plaintiffs filed this suit to challenge various actions taken by the Federal Highway Administration (FHWA) and the Utah Department of Transportation (UDOT) in planning and constructing a highway project in the Provo Canyon. The complaint alleges violations of the National Environmental Policy Act (NEPA), the Clean Air Act (CAA), and the Intermodal Surface Transportation Act (ISTEA). On April 8, 1996, plaintiffs filed a motion for a temporary restraining order and for a preliminary injunction, seeking to halt construction of this project pending completion of a supplemental environmental impact statement. At a hearing held on April 10, 1996, the court denied plaintiffs’ request for a temporary restraining order. A hearing on plaintiffs’ motion for a preliminary injunction was held over several days from April 17, 1996, through May 3, 1996. Having considered the evidence presented at that hearing, the court denies plaintiffs’ motion, and enters the following findings of fact and conclusions of law:

*1520 FINDINGS OF FACT

1. The highway project at issue in this case was originally planned as an improvement to two highway segments, Utah Route 52 (800 North in Orem, Utah) and US-189, which were to form a continuous route connecting 1-15 in Orem with US 40 in Heber (the project). As originally planned, the project was to expand 800 North from two to four lanes and to improve US-189 through the canyon as a two-lane highway with passing lanes. These proposed improvements were examined in an environmental impact statement (EIS) dated October 20, 1978. The 1978 EIS acknowledged that “traffic demand” may at some point require expansion of the canyon highway to four lanes, but stated that a new EIS would have to be prepared in order to evaluate any such expansion.

2. The planned improvements to 800 North in Orem were completed in 1985. The design for the improvements to US-189 at that time had been expanded to include four lanes. On September 12, 1986, a civil action was filed (Magleby et. al. v. Hurley, et. al., Civil No. 86-C-845W) seeking to enjoin further construction on the project. An injunction was issued to stop the project, and a stipulated Order was entered enjoining further work on the project (with certain exceptions) pending completion of a Supplemental Environmental Impact Statement (SEIS).

3. The SEIS was completed and approved by FHWA and UDOT in November, 1989. The project termini for purposes of the SEIS were the same as for the original EIS: the interchange between 1-80 and 800 North in Orem and the intersection of US 189 and US 40 in Heber. The SEIS examined the environmental impacts of construction of a four-lane highway through the canyon. The SEIS considered several alternatives and proposed a “preferred alignment” for the highway. This preferred alignment was conceptual in nature, lacking detailed design.

4. In a Record of Decision (ROD) dated March 21, 1990, FHWA gave its approval of the proposed construction of the SEIS preferred alignment.

5. For purposes of construction, the project was split into several phases; Phase I is the portion of the highway from the intersection with 800 North at the base of the canyon to Upper Falls. Phase II is the portion of the highway from Upper Falls to the county line just above the intersection of Utah Route 92 at Wildwood. Phase III is the portion of the highway from Wildwood to just beyond the Deer Creek Dam.

6. Since the 1989 SEIS, the following steps have been taken toward completion of the project:

a. Approval for construction of Main Line Bridge over Provo River in Phase I, April 6. 1990. Construction of the bridge was completed on July 30,1991.
b. Approval for construction of Phase I, May 31, 1991. Phase I was completed November 25,1994.
c. Approval of contract for final design of Phase II, April 3,1992.
d. Right-of-way acquisition for a portion of Phase II ($140,000), June 1993.
e. Right-of-way acquisition for a portion of Phase II ($480,000), July 1993.
f. Right-of-way acquisition for a portion of Phase II ($525,000), January 1994.
g. Right-of-way acquisition for a portion of Phase II ($3,600,000), July 1995.
h. Approval for construction of Phase II, September 25,1995.
i. Construction contract for Phase II awarded, January 24,1996.

7. During final design for Phase II and Phase III, several issues, including new geologic information and roadway geometric considerations, prompted reconsideration of some elements of the preferred alignment identified in the 1989 SEIS. The proposed designs went through several new configurations, and public hearings were held to consider these changes.

8. Proposed changes to the design of Phase II of the project were considered and evaluated in a document entitled “Re-evaluation of U.S. Highway 189 ... Final Supplemental Impact Statement Covering the Por- ' tion form Upper Falls to Wildwood, Utah County, Utah” (Phase II Re-evaluation). Proposed changes to the design of Phase III *1521 of the project were considered and evaluated in a document entitled “Re-evaluation of U.S. Highway 189 ... Final Supplemental Impact Statement Covering the Portion from Wild-wood to Deer Creek State Park, Wasatch County, Utah” (Phase III Re-evaluation). These re-evaluations were both approved by FHWA and UDOT on July 14,1995.

9. In the course of preparing the re-evaluations, the agencies sought input from a variety of government entities and the public. The proposed modifications were circulated to involved and interested state and federal agencies for review and comment. Public notice and opportunity for comment were provided. Public workshops were held, after publication of notice, in Heber City and in Orem in April, 1994. After publication of notice, public hearings were held in Heber on November 15,1994, and in Orem on November 16, 1994. Newsletters regarding the project were circulated to those who had expressed an interest in the project.

10. Several new design alternatives were considered for both phases of the project as farther study, public input, and budget constraints caused the designers to refine their plans. The design ultimately chosen as the preferred alignment for Phase II differed from the SEIS alignment in several ways, most notably in the redesign of the tunnel arrangement and in the substantially increased use of retaining walls. Due to new information regarding ground stability in the Hoover Slide area, the new alignment of Phase III provided for the new highway to move away from the existing highway along the river, shifting the highway up over the top of the Hoover Slide. In addition, the new Phase III alignment would cross over the top of the Deer Creek Dam instead of crossing the river on a new bridge to be constructed below the dam.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicole v. Slater
148 F. Supp. 2d 1195 (D. Utah, 2001)
Southern Utah Wilderness Alliance v. Dabney
7 F. Supp. 2d 1205 (D. Utah, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
925 F. Supp. 1518, 1996 U.S. Dist. LEXIS 6553, 1996 WL 250641, Counsel Stack Legal Research, https://law.counselstack.com/opinion/provo-river-coalition-v-pena-utd-1996.