Friends of the Payette v. Horseshoe Bend Hydroelectric Co.

988 F.2d 989, 23 Envtl. L. Rep. (Envtl. Law Inst.) 20
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 19, 1993
DocketNo. 92-36611
StatusPublished
Cited by30 cases

This text of 988 F.2d 989 (Friends of the Payette v. Horseshoe Bend Hydroelectric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Friends of the Payette v. Horseshoe Bend Hydroelectric Co., 988 F.2d 989, 23 Envtl. L. Rep. (Envtl. Law Inst.) 20 (9th Cir. 1993).

Opinion

EUGENE A. WRIGHT, Senior Circuit Judge:

Two environmental groups allege that the Army Corps of Engineers violated the National Environmental Policy Act by issuing a dredge-and-fill permit for a hydroelectric project without preparing an environmental impact statement. Because we conclude that the Corps’ action was not arbitrary and capricious, we affirm the district court’s dismissal of the action.

I

On March 10, 1992, the Horseshoe Bend Hydroelectric Company began construction of a 9.5-megawatt hydroelectric generating facility on the Payette River near Horseshoe Bend, Idaho. When completed, the facility will work as follows: An inflatable [992]*992bladder diversion dam will divert up to 3,500 cubic feet of water per second from a four-and-a-half-mile stretch of the river, routing the water down a diversion canal to a power house. The water will then pass over the powerhouse turbines before returning to the river. A minimum flow of 400 cfs will remain in the river channel, also known as the bypass stretch.

The facility is being built at the site of a decommissioned run-of-the-river hydroelectric project, which operated from 1902 to 1954. The new project will expand and use the old project’s diversion canal, which had contained valuable wetlands. Project construction has almost completely destroyed those wetlands.

Before starting construction, HBHC and its predecessor in interest, the Boise Cascade Corporation, had to obtain the approval of several state and federal agencies. In July 1986, the Federal Energy Regulatory Commission issued a license for the project to Boise Cascade. Before doing so, FERC prepared an environmental assessment in August 1984 and a supplemental EA in April 1986. Both concluded that the project would not significantly affect the environment. In April 1987, FERC approved Boise Cascade’s transfer of its license to HBHC.

HBHC then obtained the necessary state permits allowing it to appropriate water from the river, gain construction access to state-owned lands and build the dam. Lastly, HBHC needed to secure a dredge- and-fill permit from the Army Corps of Engineers. The permit, required by section 404 of the Clean Water Act, would allow HBHC to place dredged or fill material in the river. See 33 U.S.C. § 1344 (1988). HBHC applied for the permit on December 9, 1991. The Corps issued it on March 30, 1992. Although interested parties requested a public hearing, the Corps did not hold one.

Like FERC, the Corps found that the project would not significantly impact the environment within the meaning of the National Environmental Policy Act. Therefore, the agency did not prepare an EIS, but issued instead an EA and a finding of no significant impact. The § 404 permit has 17 conditions designed to mitigate environmental harm.

Friends of the Payette and Idaho Rivers United, Inc., two environmental organizations, filed suit, claiming that the Corps’ actions violated NEPA and the Clean Water Act.1 They sought a declaration that the Corps had not complied with NEPA and the CWA and an injunction halting the project pending preparation of an EIS.

The district court set the case for trial. Because it found that admission of almost all extra-record evidence was unwarranted, however, the court disallowed the testimony of 13 of Payette’s 14 proposed witnesses. It reviewed the Corps’ actions based solely on the administrative record and the testimony of William McDonald, the Corps employee who prepared the EA. The court dismissed the suit, holding that the Corps’ decision was reasonable.

Payette raises four issues on appeal: (1) whether the Corps’ failure to prepare an EIS was reasonable, (2) whether the court erred in holding that the agency’s jurisdiction over wetlands in the diversion canal was moot, (3) whether the Corps’ permit-granting procedure was flawed for failure to allow adequate public comment and (4) whether the court erred by refusing to allow extra-record evidence. Payette also asks for attorneys fees.

II

A. Decision Not to Prepare EIS

NEPA requires federal agencies to prepare a detailed EIS for “major Federal actions significantly affecting the quality of the human environment.” 42 U.S.C. § 4332 (1988). The Corps concedes that the project constitutes a major Federal action. The issue is whether the Corps properly determined that the project will not significantly affect the environment.

[993]*993 After the district court's June 1992 order dismissing the action, we adopted a new standard for reviewing an agency's decision not to prepare an EIS. We no longer employ a "reasonableness" standard. In Greenpeace Action v. Franklin, 982 F.2d 1342, 1350 (9th Cir.1992), we held that "when a litigant challenges an agency determination on grounds that, in essence, allege that the agency's `expert review ... was incomplete, inconclusive, or inaccurate,' ... the arbitrary and capricious standard is appropriate." (quoting Marsh v. Oregon Natural Resources Council, 490 U.s. 360, 376-77, 109 S.Ct. 1851, 1860-61, 104 L.Ed.2d 377 (1989)). We still must ensure that an agency has taken a "hard look" at the environmental consequences of its action and that its decision is "founded on a reasoned evaluation `of the relevant factors.'" Id. at 1350 (quoting Marsh, 490 U.S. at 378, 109 S.Ct. at 1861). If we are convinced that its discretion is truly informed, however, we must defer to that discretion. Id.

Fayette cites ten bases for its contention that the Corps' decision not to prepare an EIS was erroneous. We reject the contention, but will discuss each basis in turn.

1. Wetlands

Fayette contends that the Corps erroneously determined that wetlands will not be affected significantly. The Corps concluded that the mitigation measures required by the permit compensated for any adverse impacts.

We can consider the effect of mitigation measures in determining whether preparation of an EIS is necessary. Friends of Endangered Species, Inc. v. Jantzen, 760 F.2d 976, 987 (9th Cir.1985). If significant measures are taken to "`mitigate the project's effects,' they need not completely compensate for adverse environmental impacts." Id. (quoting Preservation Coalition, Inc. v. Pierce, 667 F.2d 851, 860 (9th Cir.1982)).

The Corps verified an environmental consultant's estimate that 69.45 acres of wetlands were within the project area. Without mitigation, 30.99 acres of riparian habitat would be lost. Strategic placement of boulders to raise the river stage and irrigation flows from uphill mitigation lands would reduce the loss to 24.69 acres. To compensate for this loss, the Corps required HBHC to implement a mitigation plan that would create 66.64 acres in new wetlands through use of water channels, grass seeding, and tree and shrub planting. The plan also requires monitoring and supplemental mitigation measures if revegetation goals are not met.

Although the measures may not compensate completely for adverse impacts, they are significant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parks v. Ethicon, Inc.
S.D. California, 2021
Town of Abita Springs v. U.S. Army Corps of Engineers
153 F. Supp. 3d 894 (E.D. Louisiana, 2015)
Antioco v. Comm'r
2013 T.C. Memo. 35 (U.S. Tax Court, 2013)
Umpqua Watersheds v. United States Forest Service
725 F. Supp. 2d 1232 (D. Oregon, 2010)
Border Power Plant Working Group v. Department of Energy
467 F. Supp. 2d 1040 (S.D. California, 2006)
United States v. Washington Department of Transportation
450 F. Supp. 2d 1207 (W.D. Washington, 2006)
United States v. Washington Dept. of Transp.
450 F. Supp. 2d 1207 (W.D. Washington, 2006)
Port of Seattle v. PCHB
90 P.3d 659 (Washington Supreme Court, 2004)
Port of Seattle v. Pollution Control Hearings Board
90 P.3d 659 (Washington Supreme Court, 2004)
Texas Committee on Natural Resources v. Van Winkle
197 F. Supp. 2d 586 (N.D. Texas, 2002)
Hawai'i County Green Party v. Clinton
980 F. Supp. 1160 (D. Hawaii, 1997)
United States v. Iron Mountain Mines, Inc.
987 F. Supp. 1250 (E.D. California, 1997)
Hoefler v. Babbitt
952 F. Supp. 1448 (D. Oregon, 1996)
Inland Empire Public Lands Council v. Glickman
88 F.3d 697 (Ninth Circuit, 1996)
Provo River Coalition v. Pena
925 F. Supp. 1518 (D. Utah, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
988 F.2d 989, 23 Envtl. L. Rep. (Envtl. Law Inst.) 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friends-of-the-payette-v-horseshoe-bend-hydroelectric-co-ca9-1993.