PROTEC GmbH

Armed Services Board of Contract Appeals·Decided June 3, 2019·No. ASBCA No. 61161, 61162·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) PROTEC GmbH ) ASBCA Nos. 61161, 61162 ) Under Contract No. W912CM-14-D-0007 )

APPEARANCES FOR THE APPELLANT: Paul D. Reinsdorf, Esq. Attorney at Law Frankfurt/Main, Germany

Steven J. Kmieciak, Esq. Seyfarth Shaw LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney Dana J. Chase, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SWEET

These appeals involve a contract between the Regional Contracting Office, Wiesbaden (government) and appellant PROTEC GmbH (PROTEC) to maintain and repair fire alarms, sprinklers, and suppression systems at the U.S. Army Garrison, Wiesbaden. The government issued an unsatisfactory Contractor Performance Assessment Reporting System (CP ARS) rating and refused to pay some invoices. PROTEC submitted claims seeking to have the government revisit the CPARS assessment and pay the unpaid invoices. The contracting officer (CO) issued a final decision (COFD) denying those claims, which PROTEC appeals. The Board has previously issued decisions regarding motions filed in the subject appeals. PROTEC GmbH, ASBCA Nos. 61161, 61162, 61185, 18-1 BCA ,r 37,010, and 18-1 BCA ,r 37,064. The Board conducted a three-day hearing on entitlement.

PROTEC claims that the assessment inaccurately stated that PROTEC failed to follow the schedule, and that PROTEC used inadequately trained personnel. PROTEC also argues there were errors in the procedure the government used to create the report. PROTEC also claims that the government improperly refused to pay the unpaid mvmces. As discussed in greater detail below, the substance of the CPARS assessment was accurate because PROTEC did not follow the schedule, and some of its personnel did not possess contractually-required Gesellenbrief diplomas certifying their training. Moreover, PROTEC has not established standing to raise its procedural claims because PROTEC has not shown prejudice from any procedural errors. Finally, the government properly refused to pay the unpaid invoices because PROTEC did not follow the schedule, performed the work with personnel who lacked Gesellenbriefs, and submitted late invoices. 1 Thus, the appeals are denied.

FINDINGS OF FACT

I. Background on German Vocational Certifications

1. In Germany, the Handwerkskammer, or Chamber of Crafts, issues a Gesellenbrief Electrician (Gesellenbrief). The Gesellenbrief certifies that an electrician has received proper training and is qualified. The Industries und Handelskammer, or Chamber of Commerce, issues a different certificate called a Journeyman Electrician Apprenticeship Diploma (Journeyman Diploma). The Journeyman Diploma is similar to the Gesellenbrief in that it also certifies an electrician's training and qualification. However, the training an electrician undergoes to receive a Gesellenbrief and a Journeyman Diploma is different. The Gesellenbrief training is practical, and focuses upon preparing electricians to service residential and business customers directly. The Journeyman Diploma training, on the other hand, is academic, and focuses upon preparing electricians to work in an industrial environment. (Tr. 2/172-75, 3/93, 233-34, 236-37)

II. Solicitation and Contract

2. On August 15, 2014, the government issued Solicitation No. W912CM-14-T-0019 (0019 Solicitation) for the maintenance, inspection, and repair of fire alarms, sprinklers, and suppression systems in various operation and maintenance (OMA) and Army Family Housing (AFH) facilities at U.S. Army Garrison, Wiesbaden (R4, tab 2).

3. PROTEC submitted an offer on September 3, 2014. Its offer did not include any Journeyman Diplomas or Gesellenbriefs for its personnel. Nor did PROTEC's offer include any indication as to whether its personnel possessed Journeyman Diplomas or Gesellenbriefs. (R4, tab 6(h))

1 Because we find that the above reasons justified non-payment of the invoices, we do not address the government's other proffered reasons for not paying the invoices. The government's motion to strike addresses those other reasons, so we deny that motion as moot. 2 4. The government found PROTEC's offer to be technically acceptable (R4, tab 7 at 2; tr. 3/41-44). On September 28, 2014, the government awarded Contract No. W912CM-14-D-0007 (0007 Contract) to PROTEC based upon the 0019 Solicitation (R4, tab 1).

5. The 0007 Contract stated that "[t]he contractor shall not deviate from the approved maintenance schedule without prior approval of the" contracting officer representative (COR) (R4, tab 1 at 55). The 0007 Contract did not provide that the COR would make appointments with the customers (tr. 3/55).

6. Performance work statement (PWS) § 1.4.8.e stated that:

The contractor shall ensure that its personnel performing required services have at least the following certificates: training diploma electrical engineering (unchanged German version "Gesellenbrief electricians") and have VdS/DIN 14675 certificates for fire alarm systems, sprinkler fire extinguishing systems and VdS for kitchen fire extinguishing systems for kitchen installations, FRYERS, grills (electric or gas).

(R4, tab I at 47)

7. The 0007 Contract also required PROTEC to "[s ]ubmit invoices for the previous month's contract services in Wide Area Work Flow (WA WF) for approval by the COR No Later Than (NLT) the 10th working [day] of the next month." By stating that invoices had to be for "the previous month's contract services," the 0007 Contract required that each invoice be for no more than one month's services. (R4, tab I at 25 (emphasis added)) The 0007 Contract stated that "[b]efore invoicing in WAWF the performed services, the COR shall verify the draft invoice." However, the 0007 Contract did not authorize PROTEC to delay the submission of an invoice while PROTEC sought clarification from the CO of any COR decision regarding a draft invoice. (Id. at 51)

8. The 0007 Contract required the government to conduct a contractor performance ·evaluation in accordance with Federal Acquisition Regulation (FAR) Subpart 42.15 (R4, tab I at 25). FAR 42. l 503(b )(1 )-which is part of Subpart 42.15-provides that "[t]he evaluation should include clear relevant information that accurately depicts the contractor's performance, and be based on objective facts supported by program and contract or order performance data."

3 III. Contract Administration

A. Schedule

9. The 0007 Contract involved two types of buildings: (1) those-such as office buildings-that required an appointment before PROTEC could work in the building; and (2) those-such as soldiers' quarters-that did not require such an appointment. Approximately half of the buildings required an appointment. (Tr. 1/53-54, 132) The buildings requiring an appointment further broke down into high security buildings and lower security buildings. High security buildings requiring appointments constituted about 20 of the 400 buildings covered by the 0007 Contract-or approximately 5 percent of the buildings (tr. 3/11).

10. By October 17, 2014, the government had accepted PROTEC's proposed schedule (app. supp. R4, tab 58(1) at 1).

11. PROTEC failed to perform services in both high security buildings and other buildings in accordance with the approved schedule (app. supp. R4, tab 59(g); tr. 3/104 ).

12.

Free access — add to your briefcase to read the full text and ask questions with AI

PROTEC GmbH, (asbca 2019).

PROTEC GmbH (PROTEC GmbH) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Savantage Financial Services, Inc. v. United States
595 F.3d 1282 (Federal Circuit, 2010)
Todd Construction, L.P. v. United States
656 F.3d 1306 (Federal Circuit, 2011)