Project B.A.S.I.C. v. Kemp

768 F. Supp. 21, 1991 U.S. Dist. LEXIS 10147, 1991 WL 134916
District Court, D. Rhode Island·Decided June 14, 1991·No. Civ. A. 89-0248P, 91-0188P·Published·Cited by 6 cases

Opinion

MEMORANDUM AND ORDER

PETTINE, Senior District Judge.

It is with deep regret and great concern that I revisit this case. Project B.A.S.I.C. began in April 1989 and, in the words of the Providence Housing Authority (“PHA”), has involved a “near-epic saga of litigation.” On April 12, 1991, the parties entered into a settlement stipulation. It was my hope at that time the project would run smoothly without any further intervention by this Court. The possibility of my intervention, however, was left open by the terms of the settlement which left in force my decree of July 17, 1989. Project B.A.S.I.C. v. Kemp, 721 F.Supp. 1501 (D.R.I.1989). I return to this case now because of a related case, Phoenix-Griffin Group II Ltd. v. Kemp, C.A. No. 91-0188P.

BACKGROUND

Briefly, this case involves low income housing. A number of units in the City of Providence were demolished and now the PHA and Department of Housing and Urban Development (“HUD”) are under an obligation to replace those 240 units of housing. In my original order, I set a deadline for the completion of the replacement housing; that deadline is June 17, 1991. Project B.A.S.I.C., 721 F.Supp. at 1515.

Phoenix-Griffin Group II Ltd. (“Phoenix”) is one of the contractors selected by the PHA to build ninety-two of the first 131 replacement units of scattered site housing. Phoenix has already completed and turned over to PHA ownership fifty-two units. The remaining forty units are in varying stages of construction, although most are near completion.

When Phoenix started work on the project, it asked PHA whether it would have to pay Davis-Bacon Act wages for its employees at its off-site prefabrication plant on Veazie Street. See 40 U.S.C. § 276a et seg. After consulting with the regional HUD office, PHA told Phoenix that it would not have to pay those higher wages. In March 1991, PHA was informed by HUD that the United States Department of Labor was conducting an investigation of Phoenix’s operations and that PHA, therefore, had to withhold $500,000 from the project at least until completion of the investigation. This action by the Labor Department and HUD came as a surprise not only to the PHA, but also to Phoenix.

On April 15, 1991, Phoenix filed suit to enjoin the withholding of the $500,000. Although nominally a defendant in that action, PHA supports Phoenix’s contention that it was given advice by HUD that was, evidently, contrary to the Labor Department’s interpretation of the Davis-Bacon Act. Phoenix alleges that without that $500,000 it cannot continue construction; its line of credit cannot withstand that loss. As a result, work will stop and those in dire need of the replacement housing, the poor and homeless of Providence, will not have decent housing.

This case is a classic example of two arms of the federal government battling over their respective domains. The battle has created a nightmare not only for this *24 Court, but for those who have labored so long to provide new low income housing and for those who await it. Both agencies make respectable arguments with regard to the regulations within their own realms, but they refuse to look past those regulations. This Court has overseen the Project B.A.S.I.C. litigation from the beginning and my paramount concern has always been to provide sorely needed housing as expeditiously as possible. It was with these needs in mind that I instructed the parties to Phoenix-Griffin, most of whom are also parties to Project B.A.S.I.C., to brief for me the issues surrounding the possible issuance of a contempt decree based on my ordered June 17, 1991 deadline for the completion of housing. For the following reasons, I have decided that I will hold HUD in contempt, once the deadline passes, if it continues to impede the completion of the project.

DISCUSSION

It is beyond dispute that this Court has the inherent equitable power to enforce its July 17, 1989 order with civil contempt and to impose fines for non-compliance. See Morales-Feliciano v. Parole Board of Puerto Rico, 887 F.2d 1, 4-6 (1st Cir.1989), cert. denied, — U.S.-, 110 S.Ct. 1511, 108 L.Ed.2d 646 (1990). Clearly, impossibility is a defense to contempt. Oriel v. Russell, 278 U.S. 358, 365-66, 49 S.Ct. 173, 175, 73 L.Ed. 419 (1929). There need not be wilful defiance to find a party in contempt, nor will a showing of substantial compliance with a court’s order excuse a party. Morales, 887 F.2d at 4-5. “Good faith alone is not a defense to civil con-tempt_ [impossibility would be a defense to contempt, ... [but] the test of impossibility may be particularly strict [where] the needs of [the plaintiffs] are urgent.” Id. at 5 (citations omitted).

The PHA has demonstrated to this Court that it will be truly impossible for it to comply with my order. As witnessed by this Court, the PHA has made a diligent effort to comply with the order. The matter, however, has been taken out of its hands by the federal government. PHA derives all of its funding for this project from HUD, and PHA is now under a direct order from HUD to withhold the monies on the basis of the Labor Department’s instructions. There is nothing within PHA’s power that can change this scenario. PHA, therefore, can assert the defense of impossibility.

HUD, however, “has not shown that causes beyond its control have made it overwhelmingly difficult or anywhere near impossible” to move this project closer to completion. See id. HUD has it within its power and discretion to issue a “change-order” which would authorize additional funding to cover the Labor Department lien and allow Phoenix to complete the remaining forty units. Although I specifically instructed HUD to point out to this Court any impediment to its issuance of such a change-order, HUD could point to no such provision and instead stressed its “full discretionary power” over expenditures.

Rather than focusing on an impossibility defense, HUD has chosen to argue primarily that my original order was not directed against it. Although HUD was clearly a defendant in Project B.A.S.I.C., my order stated:

IT IS HEREBY ORDERED that the PHA proceed as soon as possible to begin construction of the 240 public housing units, funded by HUD.... The PHA is ordered to complete construction of all 240 units of replacement housing within 23 months of the date of this Opinion. 721 F.Supp. at 1515.

Before addressing this defense, I must first state that my clear intention at the time of the order was to bind HUD as well as the PHA. Without HUD’s continued funding and approval, the PHA could not go forward with the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Project B.A.S.I.C. v. Kemp, 768 F. Supp. 21, 1991 U.S. Dist. LEXIS 10147, 1991 WL 134916 (D.R.I. 1991).

768 F. Supp. 21 (Project B.A.S.I.C. v. Kemp) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related