Professional Serv. Ind. v. Jp Const.

491 N.W.2d 351, 241 Neb. 862
CourtNebraska Supreme Court
DecidedNovember 6, 1992
DocketS-90-022
StatusPublished

This text of 491 N.W.2d 351 (Professional Serv. Ind. v. Jp Const.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Serv. Ind. v. Jp Const., 491 N.W.2d 351, 241 Neb. 862 (Neb. 1992).

Opinion

491 N.W.2d 351 (1992)
241 Neb. 862

PROFESSIONAL SERVICE INDUSTRIES, INC., Appellant,
v.
J.P. CONSTRUCTION, INC., Appellee.

No. S-90-022.

Supreme Court of Nebraska.

November 6, 1992.

*352 Christopher J. Connolly, of Thompson, Crounse, Pieper & Brumbaugh, P.C., Omaha, for appellant.

Monte Taylor, of Taylor, Connolly & Kluver, Omaha, for appellee.

HASTINGS, C.J., and BOSLAUGH, WHITE, CAPORALE, SHANAHAN, GRANT, and FAHRNBRUCH, JJ.

WHITE, Justice.

This action arises from an agreement to perform testing services at an estimated cost for a road paving project. Plaintiff, Professional Service Industries, Inc. (PSI), which provided the testing services, appeals the dismissal of its petition and the award of a judgment on the counterclaim filed by appellee, J.P. Construction, Inc., the prime contractor.

PSI asserts on appeal that the trial court erred in determining that there was both a fair intent of the parties and a duty imposed on PSI that PSI would hold close to its estimated cost figure. Furthermore, PSI claims that the court altered the agreement, without finding that an ambiguity existed, by finding that the stated estimated cost was in fact a fixed price precluding PSI's recovery of certain charges and alternatively awarding J.P. Construction reimbursement for overpayment. We find that the terms of the agreement are sufficiently definite and certain to create a valid and enforceable service requirements contract, and no ambiguity being found, we reverse and remand.

In the spring of 1986, J.P. Construction obtained a bid for road paving construction at Offutt Air Force Base in Bellevue, Nebraska. Prior to submission of its bid, J.P. Construction received a subcontracting proposal from PSI for various quality control testing services. PSI submitted a written proposal, based on estimated fees, to perform soil compaction, concrete, asphalt, and other similar paving tests at a cost of $71,000. The proposal contained the schedule of unit prices for the various laboratory tests and hourly technical manpower rates which PSI routinely charged.

*353 Once J.P. Construction was awarded the bid, a written "Standard Sub-Contract Agreement" form (the agreement) was signed by both parties. The agreement provided that PSI would supply the required testing services for an estimated $44,000. The original proposal and fee schedules submitted by PSI were stapled to the agreement. No other documents were attached to the agreement.

Aside from the preprinted form language, the pertinent typed language of the agreement reads as follows: "Total Sub-contract (estimated) $44,000.00[.] Invoiced on a Unit Price Basis, either on a cost per hour or a cost per test. PSI Agreement Attached."

The agreement was silent as to costs for retests. However, on the "Schedule of Services" attached to the PSI proposal, the following language, with original emphasis retained, appears: "Retests, for non compliance, have not been considered in the estimate. Generally, retesting materials for qualification purposes will require a minor fee. Retesting failures of material placement will require extra field time."

Work commenced in June 1986. PSI provided testing services whenever requested and submitted monthly invoices based on the service rates listed in the proposed schedule of fees. J.P. Construction initially paid these bills without protest. However, 15 months into the project, J.P. Construction realized the total monthly billings had exceeded the $44,000 estimate and refused to make further payments.

PSI subsequently filed suit seeking payment of $15,786.68 plus accrued interest for services furnished on open account. Denying that any amounts were due PSI, J.P. Construction counterclaimed for reimbursement of $8,617.64 paid above the estimated amount and for an accounting to determine the improper charges.

At trial, the parties gave conflicting explanations for the variance between the proposed figure and the final written agreement estimate. J.P. Construction asserted that PSI primarily changed its proposal because of a competitor's bid of $45,000. J.P. Construction maintained that PSI agreed to reduce its originally proposed figure because PSI could economize on time and charges due to other concurrent projects PSI had at Offutt Air Force Base. J.P. Construction also claimed that the price was estimated to cover any unforeseen quantity changes in materials, but that, in fact, no surprises occurred that required unforeseen additional work.

Conversely, PSI asserted that after learning of other competitors' proposals, PSI agreed to reduce its price to reflect an estimated amount based on unit prices for each testing service actually requested by J.P. Construction instead of a guaranteed set amount. PSI further asserted that the variance between the $44,000 estimate and the final total charges of $68,404.32 was justified in part because (1) the project was not shut down in the winter months as expected, (2) the project took approximately 3 months longer to complete than scheduled, (3) retests were not taken into consideration in the projected estimate, (4) the project required more retests than normal, and (5) control charts were requested to be prepared which were not part of the original agreement.

The court reviewed the original PSI proposal and calculated the originally anticipated manpower costs. The court then subtracted this manpower cost from the original proposed cost of $71,000 and arrived at an estimated lab testing expense. By comparing this anticipated lab testing expense with the actual invoiced costs, the court determined that J.P. Construction had received $3,745.84 worth of additional unanticipated laboratory tests.

Finding that the fair intent of the parties was that PSI was to "hold closely to its estimate," the trial court held that PSI had failed in its duty to reduce either the number of hours or the hourly costs to come within the intent of the parties. The court dismissed PSI's claim with prejudice and awarded J.P. Construction a judgment against PSI in the amount of $4,871.80 (the $8,617.64 demand minus the $3,745.84 for additional tests). PSI appealed.

The parties do not dispute, nor do we discern any reason to otherwise hold, that *354 the written agreement is a binding contract. Instead, the center of the present controversy is the proper construction of the contract.

Generally, the proper construction of a written contract and an examination of a contract for ambiguity are questions of law. See, Spittler v. Nicola, 239 Neb. 972, 479 N.W.2d 803 (1992); Luschen Bldg. Assn. v. Fleming Cos., 226 Neb. 840, 415 N.W.2d 453 (1987). Furthermore, in a judgment under review, an appellate court has an obligation to reach a conclusion on questions of law independent of the trial court. Nebraska Builders Prod. Co. v. Industrial Erectors, 239 Neb. 744, 478 N.W.2d 257 (1992).

We first note that this contract is for the performance of services, that therefore the Uniform Commercial Code is inapplicable, and that common-law principles of construction or interpretation of a document apply.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spittler v. Nicola
479 N.W.2d 803 (Nebraska Supreme Court, 1992)
Marvin E. Jewell & Co. v. Thomas
434 N.W.2d 532 (Nebraska Supreme Court, 1989)
International Harvester Credit Corp. v. Lech
438 N.W.2d 474 (Nebraska Supreme Court, 1989)
Griswold & Rauma, Architects, Inc. v. Aesculapius Corp.
221 N.W.2d 556 (Supreme Court of Minnesota, 1974)
Nowak v. Burke Energy Corp.
418 N.W.2d 236 (Nebraska Supreme Court, 1988)
Crowley v. McCoy
449 N.W.2d 221 (Nebraska Supreme Court, 1989)
Nebraska Builders Products Co. v. Industrial Erectors, Inc.
478 N.W.2d 257 (Nebraska Supreme Court, 1992)
Albee v. Maverick Media, Inc.
474 N.W.2d 238 (Nebraska Supreme Court, 1991)
Husen v. Husen
487 N.W.2d 269 (Nebraska Supreme Court, 1992)
Ruzicka v. Petersen
330 N.W.2d 913 (Nebraska Supreme Court, 1983)
Wurst v. Blue River Bank
454 N.W.2d 665 (Nebraska Supreme Court, 1990)
Luschen Building Ass'n v. Fleming Companies, Inc.
415 N.W.2d 453 (Nebraska Supreme Court, 1987)
Professional Service Industries, Inc. v. J. P. Construction, Inc.
491 N.W.2d 351 (Nebraska Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
491 N.W.2d 351, 241 Neb. 862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-serv-ind-v-jp-const-neb-1992.