Professional Construction, Inc. v. Historic Walnut Square, LLC

CourtIndiana Court of Appeals
DecidedDecember 27, 2023
Docket23A-PL-00654
StatusPublished

This text of Professional Construction, Inc. v. Historic Walnut Square, LLC (Professional Construction, Inc. v. Historic Walnut Square, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Construction, Inc. v. Historic Walnut Square, LLC, (Ind. Ct. App. 2023).

Opinion

FILED Dec 27 2023, 8:52 am

CLERK Indiana Supreme Court Court of Appeals and Tax Court

ATTORNEYS FOR APPELLANTS ATTORNEYS FOR APPELLEE Maggie L. Smith David L. Guevara Joshua N. Kutch James R. A. Dawson Indianapolis, Indiana Indianapolis, Indiana

Heather M. Hawkins Cincinnati, Ohio

IN THE COURT OF APPEALS OF INDIANA

Professional Construction, Inc., December 27, 2023 and West Bend Mutual Court of Appeals Case No. Insurance Company, 23A-PL-654 Appellants-Defendants, Appeal from the Marion Superior Court v. The Honorable Heather A. Welch, Judge Historic Walnut Square, LLC, Trial Court Cause No. Appellee-Plaintiff 49D01-2206-PL-21757

Opinion by Chief Judge Altice Judges May and Foley concur.

Altice, Chief Judge.

Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 1 of 20 Case Summary [1] Professional Construction, Inc. (Contractor) and West Bend Mutual Insurance

Company (Surety) (collectively, Appellants) bring this interlocutory appeal of

the trial court’s denial of their motion to enforce arbitration agreement and stay

litigation in a lawsuit brought by Historic Walnut Square, LLC (Owner).

Appellants present the following restated issues for review:

1. Did the trial court properly determine that Contractor waived its contractual right to demand arbitration by filing suit against Owner in Wisconsin?

2. Did the trial court err by determining that Surety had no right to enforce the arbitration provision in the construction contract?

3. Where is the proper venue for arbitration?

[2] We reverse and remand.

Facts & Procedural History [3] In 2020, Owner solicited bids for a construction project for the development of

a forty-unit, multi-family housing project in Terre Haute and ultimately selected

Contractor as general contractor for the project. On August 6, 2020, they

executed two standard form American Institute of Architects (AIA)

agreements, A101-2017 and A201-2017 (collectively, the Construction

Contract). Additionally, Contractor obtained a Payment Bond and a

Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 2 of 20 Performance Bond (collectively, the Bonds), also AIA standard form

agreements, through Surety in the amount of the Construction Contract.

[4] The Construction Contract provides for binding arbitration, pursuant to § 15.4

of AIA Document A201-2017, of any claim subject to or not resolved by

mediation and expressly indicates that the Federal Arbitration Act (the FAA)

shall govern. § 15.4.1 provides in relevant part:

[A]ny claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect on the date of the Agreement. The Arbitration shall be conducted in Fond du Lac County, Wisconsin unless expressly prohibited by law, in which case mediation [sic] shall be held in the place where the Project is located, unless another location is mutually agreed upon. A demand for arbitration shall be made in writing, delivered to the other party to the Contract, and filed with the person or entity administering the arbitration.

Appellants’ Appendix Vol. 2 at 111. Further, pursuant to § 15.4.3, the agreement

to arbitrate “shall be specifically enforceable under applicable law in any court

having jurisdiction thereof.” Id.

[5] Certain contractual disputes arose between Contractor and Owner and came to

a head in the beginning of 2022. The details of the disputes are not particularly

relevant here; our focus is on the parties’ attempts to resolve them. Contractor

initially communicated its claim to the architect (Architect) – the project’s

initial decision maker under the Construction Contract. Unsatisfied with

Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 3 of 20 Architect’s decision and anticipating a breach of the Construction Contract by

Owner, Contractor stopped work on the project on February 11, 2022. Owner

then declared Contractor in default and made a claim against Surety on the

Performance Bond.

[6] On February 14, 2022, Contractor (by email and certified mail) sent a written

demand for mediation/arbitration to Owner and Architect. After setting out

Contractor’s position in detail, the letter concluded with the following:

Demand for Mediation/ Arbitration Given the Owner’s position, and the Architect’s decision to affirm the Owner’s position, concerning the substantial completion date, pursuant to §§ 15.3 and 15.4 of the Construction Contract, PCI hereby demands mediation and arbitration of the current dispute between the parties.

Pertinent sections dealing with mediation and arbitration in the Construction Contract, call for mediation to be administered by the American Arbitration Association ("AAA"). We are not opposed to this prescription, however, due to the likely urgency of the matter, PCI would consider using an alternate mediation agency or mediator. Please advise on your position on this as soon as possible. If we do not hear back from you by February 17, 2022, we will assume the Owner’s preference is to have the matter handled by an AAA mediator, and we will file the mediation/ arbitration demand with the AAA.

Appellants’ Appendix Vol. 3 at 46 (emphases in original).

[7] Surety quickly followed Contractor’s demand for mediation/arbitration with a

letter to Owner requesting a meeting in Wisconsin with decision makers for all

parties present, along with Architect. On February 23, Owner responded and

proposed “a meeting that does not involve the Contractor or the sideshow of

topics, such as liquidated damages, which are unrelated to the immediate goal

of performing and completing the Construction Contract.” Id. at 22.

Court of Appeals of Indiana | Opinion 23A-PL-654 | December 27, 2023 Page 4 of 20 [8] On February 27, Surety wrote Owner again and emphasized that there were

issues between Owner and Contractor that were “worth mediating” and that

resolving these issues was “critical” to Surety’s decision regarding the claim on

the Performance Bond. Id. at 25, 26. Surety proposed that all parties meet on

March 4 and agree to prompt mediation of any issues not resolved at that

meeting.

[9] On March 1, Owner responded that it would not entertain Contractor’s input in

the matter between Owner and Surety, explaining in part:

Right now, and while the Owner attempts to recover the Project from the Contractor’s defective, untimely performance, there is nothing to mediate. The Owner is open to negotiations and engaging a third party mediator to resolve any remaining claims, but only after the Owner and Surety have all of the relevant information, the Surety performs its obligations under the Performance Bond, and the Work is complete. It is only then that the parties may be able to bring this matter to a full, final resolution. Mediation efforts now would be premature and waste precious time.

Id. at 30.

[10] On April 17, 2022, Surety denied Owner’s claims on the Bonds and provided a

detailed explanation of its denial. In summary, Surety claimed that Owner had

repudiated the Construction Contract prior to Contractor justifiably stopping

work and that Owner’s subsequent refusal to mediate or arbitrate the dispute

between Contractor and Owner also constituted a breach of the Construction

Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southland Corp. v. Keating
465 U.S. 1 (Supreme Court, 1984)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Marie v. Allied Home Mortgage Corp.
402 F.3d 1 (First Circuit, 2005)
Grigsby & Associates, Inc. v. M Securities Investment
664 F.3d 1350 (Eleventh Circuit, 2011)
Jack Ehleiter v. Grapetree Shores, Inc.
482 F.3d 207 (Third Circuit, 2007)
JPD, INC. v. Chronimed Holdings, Inc.
539 F.3d 388 (Sixth Circuit, 2008)
Ryder v. Bank of Hickory Hills
585 N.E.2d 46 (Illinois Supreme Court, 1992)
Sundance Homes, Inc. v. County of Du Page
746 N.E.2d 254 (Illinois Supreme Court, 2001)
BG Group, PLC v. Republic of Argentina
134 S. Ct. 1198 (Supreme Court, 2014)
Paige Martin v. Gary Yasuda
829 F.3d 1118 (Ninth Circuit, 2016)
Brickstructures, Inc. v. Coaster Dynamix, Inc.
952 F.3d 887 (Seventh Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Professional Construction, Inc. v. Historic Walnut Square, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-construction-inc-v-historic-walnut-square-llc-indctapp-2023.