Producers Coke Co. v. Hillman

90 A. 144, 243 Pa. 313, 1914 Pa. LEXIS 620
CourtSupreme Court of Pennsylvania
DecidedJanuary 5, 1914
DocketAppeal, No. 46
StatusPublished
Cited by23 cases

This text of 90 A. 144 (Producers Coke Co. v. Hillman) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Producers Coke Co. v. Hillman, 90 A. 144, 243 Pa. 313, 1914 Pa. LEXIS 620 (Pa. 1914).

Opinion

Opinion by

Mr. Justice Stewart,

The action was for recovery for a definite quantity of coke sold and delivered by the plaintiff company to the defendants between 3d July, 1912, and the 29th of the same month, at specified rates per ton, on an implied promise that the defendants would pay for the coke furnished. In the affidavit of defense filed defendants aver that on or about 10th May, 1912, the plaintiff company and the defendants entered into a contract, evidenced by writings, by which the plaintiff agreed to place in the hands of the defendants for sale, substantially all the coke it produced during the six months from 1st July to December 31, 1912; that under this contract the defendants made sales of large quantities of coke in their own names for delivery between 1st July, and 31st December; that about 20th July the same year the plaintiff desiring to be relieved of its obligations to furnish defendants all the coke it produced within the [315]*315period named, by mutual agreement tbe original contract was rescinded, and as a consideration for defendants’ consent to the rescission tbe plaintiff promised and agreed that defendants should be protected as to tbe coke wbicb up to that time they bad sold; and that to this end it would deliver during tbe balance of tbe year tbe coke wbicb bad been sold by tbe defendants on certain terms then and there specified, as follows, “during tbe month of July 3,680 tons at tbe price of $2,379 per net ton and 2,124 tons per month for tbe months of August, September, October, November and December at tbe price of $2,345 per net ton.” Tbe plaintiff delivered to tbe defendants during July about 844% tons less than tbe amount called for, and failed to deliver any coke whatever during tbe month of September. Tbe suit was brought 19th September, 1912, to recover for coke delivered during July. Tbe contention on part of defendants was that tbe contract set up in tbe affidavit of defense was éntire, and that there could be no recovery by plaintiff for any partial performance. A rule for judgment for want of a sufficient affidavit of defense was made absolute, and judgment followed. Tbe appeal is from tbe judgment so entered, and challenges tbe correctness of tbe court’s construction of tbe contract set out in tbe affidavit, in bolding it to be divisible and not entire. Where a question of this kind arises it is tbe intention of tbe parties that controls and not tbe divisibility of tbe subject: Shinn v. Bodine, 60 Pa. 182; and this intention is to be collected from tbe words employed where tbe intention can be clearly derived therefrom. When, as understood in their Ordinary sense, tbe words do not disclose tbe manner and intent to wbicb tbe parties intended to be bound, resort must be bad to rules of construction as aids. Having regard simply to tbe words employed in this contract, tbe inference that tbe contract was intended to be entire would be quite as reasonable as that it was intended to be divisible. If there are provisions wbicb indicate that a divisible contract [316]*316was intended, there are others which quite as clearly indicate the opposite. The .distinguishing mark of a divisible contract is that it admits of apportionment of the consideration on either side so as to correspond to the unascertained consideration on the other side. Where such a purpose appears in the contract, or is clearly deducible therefrom, it is allowed great significance when ascertaining the intention of the parties. It is a mistake, however, to suppose that in every case it is conclusive in itself. It is determining only when there are no opposing signs or marks. Where these latter are present it becomes a question of preponderance.

“If, therefore, although the terms of the contract afford the rule for the apportionment of the consideration, yet if there be a special agreement to take the whole or nothing, or if the evidence clearly shows that such was the purpose of the parties, the contract would be entire.”

Story on Contracts, Sec. 24th. And again, in Sec. 24 this appears,

“Agreeably moreover to the weight of authority, a stipulation that the price shall be paid by instalments as the goods are delivered or the work proceeds, will not render a contract for an entire thing, as, for instance, to build a house or furnish a given weight or quantity of merchandise, divisible, or so apportion the consideration to the several parties as to dispense with an exact fulfillment of the law; and if the contractor fails to do all, he will not only be precluded from recovering what remains unpaid, but may be compelled to refund the sums which he has already received; and it will make no difference that the default arose without negligence on his part.”

In support of the text the case of Shaw v. Turnpike Company, 2 P. & W., 454, is cited, in which a contract that provided for apportionment of consideration was held to be entire, and the plaintiff was denied the right to recover except on full performance. In the case cited by the learned trial judge, and in those cited by counsel [317]*317for appellee, in support of the construction that prevailed, the fact that the contract provided for payment pro tanto upon delivery of fractional parts of the whole amount contracted for, was allowed to be determining, only because there was entire absence of anything indicating a different purpose. Certainly in no one of these cases is it held that a provision such as this is of such controlling effect, that it must be allowed to defeat the plain and manifest object of the contract. And yet that would be the effect here if it should be allowed to govern. Each party to this contract had a definite object in view which was so clearly expressed that there was no room for doubt by either. The plaintiff, whose sole object was to secure a cancellation of the agreement which required it to deliver to the defendants for sale its entire output of coke during the remaining months of the year, must have fully understood the object of the defendants in requiring, as a condition of their assent, a promise from the plaintiff company that it would protect the defendants from liability on contracts of sale they had already entered into, by furnishing them the coke sufficient to meet their engagements, at a definite fixed price. The contract here set up is a promise by the plaintiff company, on a sufficient consideration, that it would make these deliveries, not only some but all of them, for the one definite purpose to save harmless the defendants who otherwise, because of market vicissitudes, would be exposed to the danger of loss. These engagements by the defendants were for deliveries at specified times, in specified amounts, and at specified rates; and the promise by the plaintiff, as averred, was to supply the defendants with an adequate amount of coke to meet them all, amounting in the aggregate to 14,300 tons. There is no mistaking the end or object in view, and it is quite as apparent that to hold this contract severable and not entire, would defeat the object both parties had in view. The consideration paid by the defendants — surrender of their rights under the earlier contract — was based upon [318]*318a contemplated entire performance by the plaintiff, for, except as this was so, the agreement accomplished nothing in the way of protection to the defendants.

“Where a bill of parcels is taken, and includes the articles bought under one whole price, it would, if accepted, afford evidence of an intention by both parties to treat the contract as entire.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marvin Raab v. Howard Lander
427 F. App'x 182 (Third Circuit, 2011)
Jacobs v. CNG Transmission Corp.
332 F. Supp. 2d 759 (W.D. Pennsylvania, 2004)
Jacobs v. CNG Transmission Corp.
772 A.2d 445 (Supreme Court of Pennsylvania, 2001)
Carroll Township Authority v. Municipal Authority
603 A.2d 243 (Commonwealth Court of Pennsylvania, 1992)
Continental Supermarket Food Service, Inc. v. Soboski
232 A.2d 216 (Superior Court of Pennsylvania, 1967)
C & D FARMS, INC. v. Cerniglia
189 So. 2d 384 (District Court of Appeal of Florida, 1966)
Kaufman Hotel & Restaurant Co. v. Thomas
190 A.2d 434 (Supreme Court of Pennsylvania, 1963)
William Feinstein Bros., Inc. v. LZ Hotte Granite Co.
184 A.2d 540 (Supreme Court of Vermont, 1962)
Heilwood Fuel Co. v. Manor Real Estate Co.
175 A.2d 880 (Supreme Court of Pennsylvania, 1961)
Cohen v. Johnson
91 F. Supp. 231 (M.D. Pennsylvania, 1950)
Awner v. Halpern
65 Pa. D. & C. 580 (Philadelphia County Court of Common Pleas, 1948)
In Re Kellett Aircraft Corporation
77 F. Supp. 959 (E.D. Pennsylvania, 1948)
Levine v. Reynolds
54 A.2d 514 (Supreme Judicial Court of Maine, 1947)
Metcalf v. R. D. Keene & Co.
164 So. 704 (Supreme Court of Florida, 1935)
Byren & Weil, Inc. v. French & Keeley, Inc.
157 A. 367 (Superior Court of Pennsylvania, 1931)
Hayday v. Hammermill Paper Co.
237 N.W. 600 (Supreme Court of Minnesota, 1931)
Garman Bros. v. Hoover Et Ux.
95 Pa. Super. 203 (Superior Court of Pennsylvania, 1928)
Fifer v. King
88 Pa. Super. 203 (Superior Court of Pennsylvania, 1926)
Cambria Car & Foundry Co. v. Royal Quemahoning Coal Co.
5 Pa. D. & C. 254 (Westmoreland County Court of Common Pleas, 1924)
Orenstein v. Kahn
119 A. 444 (Supreme Court of Delaware, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
90 A. 144, 243 Pa. 313, 1914 Pa. LEXIS 620, Counsel Stack Legal Research, https://law.counselstack.com/opinion/producers-coke-co-v-hillman-pa-1914.