prod.liab.rep. (Cch) P 13,644 Concordia College Corporation, a Non-Profit Organization v. W.R. Grace & Co., Individually and as Successor-In-Interest to the Zonolite Companies and Western Mineral Products Company W.R. Grace & Co.--Conn., Individually and as Successor-In-Interest to the Zonolite Companies and Western Mineral Products Company Carey-Canada, Inc. Basic, Inc. The Celotex Corp., Individually and as Successor-In-Interest to Philip Carey Manufacturing Company, Philip Carey Corporation, Briggs Manufacturing Company and Panacon Corporation Keene Corporation, Individually and as Successor-In-Interest to the Ehret Magnesia Manufacturing Company, Baldwin-Hill Company, Baldwin-Ehret-Hill, Inc., Mundet Company, and Keene Building Products Corporation National Gypsum Company, Individually and as Successor-In-Interest to Gold Bond Building Products Corporation Pfizer, Inc., Individually and as Successor-In-Interest to Charles Pfizer & Company, Kelley Island Lime & Transport Company, Gibsonburg Lime Products Company and Basic, Inc. United States Gypsum Company

999 F.2d 326
CourtCourt of Appeals for the Eighth Circuit
DecidedSeptember 2, 1993
Docket92-1307
StatusPublished

This text of 999 F.2d 326 (prod.liab.rep. (Cch) P 13,644 Concordia College Corporation, a Non-Profit Organization v. W.R. Grace & Co., Individually and as Successor-In-Interest to the Zonolite Companies and Western Mineral Products Company W.R. Grace & Co.--Conn., Individually and as Successor-In-Interest to the Zonolite Companies and Western Mineral Products Company Carey-Canada, Inc. Basic, Inc. The Celotex Corp., Individually and as Successor-In-Interest to Philip Carey Manufacturing Company, Philip Carey Corporation, Briggs Manufacturing Company and Panacon Corporation Keene Corporation, Individually and as Successor-In-Interest to the Ehret Magnesia Manufacturing Company, Baldwin-Hill Company, Baldwin-Ehret-Hill, Inc., Mundet Company, and Keene Building Products Corporation National Gypsum Company, Individually and as Successor-In-Interest to Gold Bond Building Products Corporation Pfizer, Inc., Individually and as Successor-In-Interest to Charles Pfizer & Company, Kelley Island Lime & Transport Company, Gibsonburg Lime Products Company and Basic, Inc. United States Gypsum Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
prod.liab.rep. (Cch) P 13,644 Concordia College Corporation, a Non-Profit Organization v. W.R. Grace & Co., Individually and as Successor-In-Interest to the Zonolite Companies and Western Mineral Products Company W.R. Grace & Co.--Conn., Individually and as Successor-In-Interest to the Zonolite Companies and Western Mineral Products Company Carey-Canada, Inc. Basic, Inc. The Celotex Corp., Individually and as Successor-In-Interest to Philip Carey Manufacturing Company, Philip Carey Corporation, Briggs Manufacturing Company and Panacon Corporation Keene Corporation, Individually and as Successor-In-Interest to the Ehret Magnesia Manufacturing Company, Baldwin-Hill Company, Baldwin-Ehret-Hill, Inc., Mundet Company, and Keene Building Products Corporation National Gypsum Company, Individually and as Successor-In-Interest to Gold Bond Building Products Corporation Pfizer, Inc., Individually and as Successor-In-Interest to Charles Pfizer & Company, Kelley Island Lime & Transport Company, Gibsonburg Lime Products Company and Basic, Inc. United States Gypsum Company, 999 F.2d 326 (8th Cir. 1993).

Opinion

999 F.2d 326

Prod.Liab.Rep. (CCH) P 13,644
CONCORDIA COLLEGE CORPORATION, a non-profit organization, Appellant,
v.
W.R. GRACE & CO., individually and as successor-in-interest
to the Zonolite Companies and Western Mineral Products
Company; W.R. Grace & Co.--Conn., individually and as
successor-in-interest to the Zonolite Companies and Western
Mineral Products Company; Carey-Canada, Inc.; Basic, Inc.;
The Celotex Corp., individually and as
successor-in-interest to Philip Carey Manufacturing Company,
Philip Carey Corporation, Briggs Manufacturing Company and
Panacon Corporation; Keene Corporation, individually and as
successor-in-interest to the Ehret Magnesia Manufacturing
Company, Baldwin-Hill Company, Baldwin-Ehret-Hill, Inc.,
Mundet Company, and Keene Building Products Corporation;
National Gypsum Company, individually and as
successor-in-interest to Gold Bond Building Products
Corporation; Pfizer, Inc., individually and as
successor-in-interest to Charles Pfizer & Company, Kelley
Island Lime & Transport Company, Gibsonburg Lime Products
Company and Basic, Inc.; United States Gypsum Company, Appellees.

No. 92-1307.

United States Court of Appeals,
Eighth Circuit.

Submitted Feb. 19, 1993.
Decided July 14, 1993.
Rehearing and Suggestion for Rehearing En Banc Denied Sept. 2, 1993.

Daniel A. Speights, Hampton, SC, argued (Steven C. Lian, Minot, ND, and Jon M. Arntson, Fargo, ND, on the brief), for appellant.

Allen W. Hinderaker, Minneapolis, MN, argued (David F. Herr and Mary R. Vasaly, Minneapolis, MN, C. Todd Koebele and Thomas M. Conlin, St. Paul, MN, Thomas H. Shiah, Sandra Wallace Napolitano, Thomas Caswell and Brooks F. Poley of Minneapolis, MN, Kell M. Damsgaard and Dennis J. Valenza of Philadelphia, PA, and Hugh V. Plunkett, III, and William D. Hittler, Minneapolis, MN, on the brief), for appellees.

Before BOWMAN, WOLLMAN, and HANSEN, Circuit Judges.

BOWMAN, Circuit Judge.

This is an appeal from summary judgment in favor of W.R. Grace & Company; W.R. Grace & Company--Connecticut; Carey-Canada, Inc.; Basic, Inc.; Celotex Corporation; Keene Corporation; National Gypsum Company; Pfizer, Inc.; and United States Gypsum Company (collectively W.R. Grace1), all manufacturers of asbestos-containing building materials, on the claim of Concordia College Corporation for recovery of its abatement costs in removing asbestos from its buildings. We affirm.

Two Minnesota statutes are especially relevant here, and we begin by identifying them and their applicability to this case. The first is the statute of limitations and repose for actions arising out of construction to improve real property, and reads in pertinent part as follows:

Except where fraud is involved, no action by any person in contract, tort, or otherwise to recover damages for any injury to property, real or personal, ... arising out of the defective and unsafe condition of an improvement to real property, ... shall be brought against any person ... furnishing the ... materials ... more than two years after discovery of the injury ... nor, in any event shall such a cause of action accrue more than ten years after substantial completion of the construction.

Minn.Stat. § 541.051(1)(a) (1992). The "repose" aspect of the statute prohibits accrual of any cause of action after ten years. Thus regardless of when the injury is discovered, that is, when the cause accrues, see id. § 541.051(1)(b), the cause will be deemed accrued no later than ten years after substantial completion of the construction (absent a showing of fraud).

The other statute that is critical to the resolution of this case is a "revival" statute for asbestos cases, enacted in 1987. Under the statute, an asbestos abatement recovery action "that would otherwise be barred before July 1, 1990, as a result of expiration of the applicable period of limitation, is revived or extended. An asbestos action revived or extended under this subdivision may be begun before July 1, 1990." Id. § 541.22(2) (1992).

Concordia filed suit under the District Court's2 diversity jurisdiction on June 29, 1990, but the defendants in the suit were not served until July 24, 1990. The District Court granted summary judgment for the defendants, holding that Concordia's suit was barred by the statute of repose, and was not revived under section 541.22 because it was not "begun before July 1, 1990." Concordia contends that the statute of repose did not operate to bar its claim in this case and, should this Court find otherwise, that the revival statute operated to restore the action. We disagree with both propositions and affirm the judgment of the District Court.

All the buildings at issue here were "substantially completed" between 1957 and 1970, and the District Court held that Concordia's claims were barred by operation of the ten-year repose provision of section 541.051. Concordia argues that the District Court improperly applied the statute of repose retroactively to bar its suit. We review the District Court's application and interpretation of state law de novo. See Salve Regina College v. Russell, 499 U.S. 225, 111 S.Ct. 1217, 113 L.Ed.2d 190 (1991).

Section 541.051 was enacted in 1980 in substantially its present form, but with a fifteen-year accrual period for the repose provision.3 The Minnesota Supreme Court held in 1986 that the two-year limitations period in section 541.051 had been applied retroactively--and improperly--to bar a "claim[ ] existing when it was enacted in 1980." Lovgren v. Peoples Elec. Co., 380 N.W.2d 791, 795 (Minn.1986); see also Minn.Stat. § 645.21 (1992) ("No law shall be construed to be retroactive unless clearly and manifestly so intended by the legislature."). The court did not address retroactive application of the repose provision, however, and so Lovgren is not determinative of the outcome in this case.

The exact date when Concordia discovered (or reasonably should have discovered) the injury alleged in this case is not clear from the record before us, although the District Court indicated that the need for abatement was apparent to Concordia no later than 1984. It may be that Concordia's cause of action is barred by the general six-year tort statute of limitations in effect before enactment of section 541.051 in 1980. See supra n. 3. It also is entirely possible that the cause of action is barred by the two-year statute of limitations found in the reenacted version of section 541.051, an issue the District Court specifically declined to decide. We need not remand for decision of these issues, however, as we conclude that the ten-year repose provision of section 541.051 was properly applied to this action.

In 1988, the Minnesota legislature enacted the following law (which was never codified, apparently because it was effective for only a very limited period of time after enactment):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Pipe & Construction Co. v. Utah
414 U.S. 538 (Supreme Court, 1974)
Eisen v. Carlisle & Jacquelin
417 U.S. 156 (Supreme Court, 1974)
Walker v. Armco Steel Corp.
446 U.S. 740 (Supreme Court, 1980)
Crown, Cork & Seal Co. v. Parker
462 U.S. 345 (Supreme Court, 1983)
Salve Regina College v. Russell
499 U.S. 225 (Supreme Court, 1991)
Sartori v. Harnischfeger Corp.
432 N.W.2d 448 (Supreme Court of Minnesota, 1988)
Lovgren v. Peoples Elec. Co., Inc.
380 N.W.2d 791 (Supreme Court of Minnesota, 1986)
Calder v. City of Crystal
318 N.W.2d 838 (Supreme Court of Minnesota, 1982)
State Ex Rel. Spannaus v. Hopf
323 N.W.2d 746 (Supreme Court of Minnesota, 1982)
Pacific Indemnity Co. v. Thompson-Yaeger, Inc.
260 N.W.2d 548 (Supreme Court of Minnesota, 1977)
Independent School District No. 622 v. Keene Corp.
495 N.W.2d 244 (Court of Appeals of Minnesota, 1993)
Pulley v. Burlington Northern, Inc.
568 F. Supp. 1177 (D. Minnesota, 1983)
Singer v. Eli Lilly & Co.
153 A.D.2d 210 (Appellate Division of the Supreme Court of New York, 1990)
Clark v. Abbott Laboratories
155 A.D.2d 35 (Appellate Division of the Supreme Court of New York, 1990)
Concordia College Corp. v. W.R. Grace & Co.
999 F.2d 326 (Eighth Circuit, 1993)
Central Wesleyan College v. W.R. Grace & Co.
143 F.R.D. 628 (D. South Carolina, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
999 F.2d 326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prodliabrep-cch-p-13644-concordia-college-corporation-a-non-profit-ca8-1993.