PRINCETON COMBUSTION RESEARCH LABORATORIES, INC. v. McCARTHY

674 F.2d 1016, 29 Cont. Cas. Fed. 82,415, 1982 U.S. App. LEXIS 20596
CourtCourt of Appeals for the Third Circuit
DecidedMarch 29, 1982
Docket81-3011
StatusPublished

This text of 674 F.2d 1016 (PRINCETON COMBUSTION RESEARCH LABORATORIES, INC. v. McCARTHY) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PRINCETON COMBUSTION RESEARCH LABORATORIES, INC. v. McCARTHY, 674 F.2d 1016, 29 Cont. Cas. Fed. 82,415, 1982 U.S. App. LEXIS 20596 (3d Cir. 1982).

Opinion

674 F.2d 1016

29 Cont.Cas.Fed. (CCH) 82,415

PRINCETON COMBUSTION RESEARCH LABORATORIES, INC., Appellee,
v.
Director, John McCARTHY, Jr., United States National
Aeronautics and Space Administration, Lewis
Research Center at Cleveland, Ohio.
Appeal of SHAKER RESEARCH CORPORATION.

No. 81-3011.

United States Court of Appeals, Third Circuit.

Submitted March 15, 1982.
Decided March 29, 1982.

W. Hunt Dumont, U. S. Atty., Ann C. Singer, Asst. U. S. Atty., Newark, N. J., for appellant, John McCarthy.

Martin Summerfield, President, Princeton Combustion Research Laboratories, Inc., pro se.

Before ADAMS, VAN DUSEN and GARTH, Circuit Judges.

OPINION OF THE COURT

GARTH, Circuit Judge:

This appeal arises out of a decision by Appellant, the National Aeronautics and Space Administration ("NASA"), to award a procurement contract to the other Appellant in this case, the Shaker Research Corporation ("Shaker") rather than to the Appellee, Princeton Combustion Research Laboratories, Inc. ("Princeton Combustion"). In an order dated December 4, 1981, the district court granted Princeton Combustion's motion for a preliminary injunction, declaring the award of the contract to Shaker to be clearly illegal and enjoining NASA from re-awarding the contract until it followed the proper procedures.1 Because we find that the district court's grant of the motion for a preliminary injunction was improper, we will vacate the district court's order of December 4, 1981.

I.

On April 3, 1981, the Lewis Research Center at Cleveland, Ohio, issued a Request for Proposal for a NASA contract for research into combustion technology. The information gained thereby would be used in the development of the Spacelab project, and though the contract itself was to be of a duration only of six months, further research and development, and so additional contracts, were also contemplated.

By the closing date of May 21, 1981, six companies had submitted bids in response to the Request for Proposal. The proposals were then forwarded to a Technical Evaluation Committee ("TEC"), which evaluated the strengths and weaknesses of the proposals and gave them ratings. The proposal submitted by Shaker was given the highest rating2 and carried a proposed cost of $37,647, only $1,000 more than the lowest bid and some $40,000 lower than the highest bid. The proposal submitted by Princeton Combustion was given the second-highest rating, and carried a proposed cost of approximately $10,000 more than the Shaker bid. In addition to rating them, the TEC also presented a detailed analysis of the bids. Shaker's proposal, the TEC found, showed "major strengths" in three of the four areas in which the evaluation was made3 whereas Princeton Combustion's proposal showed only "minor strengths" in those areas.4 Accordingly, on July 13, 1981, Shaker was selected as an offeror within the competitive range.

On July 21, 1981, Shaker submitted a revised proposal, naming a new Project Manager to replace the one who had just resigned, and proposing a slightly higher project cost. The TEC reconvened and determined that the point score assigned to Shaker's proposal should remain unchanged. Moreover, the increase in costs was considered to be only minor and still left Shaker's bid among the lowest submitted. Thus when the final selection was made on July 31, 1981, Shaker was given the contract. In accordance with NASA regulations, see 41 C.F.R. Ch. 18, § 3.106-3, the unsuccessful bidders were notified by letter on August 4, 1981, that they had not been selected. The unsuccessful bidders were also given an opportunity to meet with NASA officials concerning their rejection, and on September 18, 1981, Princeton Combustion took advantage of that opportunity. After the meeting, Princeton Combustion protested the selection of Shaker, informing NASA of its objections by telephone on September 24, 1981, and by two telegrams that NASA received sometime on September 25, 1981. In the meantime, NASA and Shaker had commenced negotiations over the final form of a contract, and having reached agreement, signed one on September 25, 1981.

On October 14, 1981, Princeton Combustion filed a complaint against NASA and Shaker in federal district court, seeking damages and injunctive relief. Specifically, the complaint requested that the district court set aside the award of the contract to Shaker and award it instead to Princeton Combustion. In essence, Princeton Combustion alleged that Shaker had little expertise in combustion technology, that Princeton Combustion's own proposal was superior, and that NASA had wrongfully refused to divulge to Princeton Combustion certain information regarding Shaker and the selection process. Princeton Combustion also charged that "(a)fter awarding the contract to Shaker, Defendant NASA permitted Shaker to increase its bid price," and, asserting that "(c)hanges after bid closing are rarely permitted," Princeton Combustion noted that Shaker had, on July 21, 1981, changed the Project Manager in its proposal. Complaint, PP 30, 31.

After a hearing on November 16, 1981, the district court announced on November 20, 1981, that it intended to issue an order declaring the contract illegal and enjoining its further performance. In an opinion delivered from the bench, the district court correctly stated the principles governing the grant of preliminary injunctive relief. The district court held that in general, the plaintiff must show that he has a reasonable probability of success on the merits, that he will suffer irreparable harm in the absence of preliminary injunctive relief, and that the interests of other affected persons and the general public weigh in favor of the grant of injunctive relief, or at least do not militate against it. In the area of government procurement contracts, however, the district court correctly noted that a more stringent standard governs a determination of the first factor, the likelihood of plaintiff's prevailing on the merits. Though the bidder has a legitimate interest in fair treatment in accordance with applicable statutes and regulations, the strong public interest in efficient procurement and cost minimization mandates that a procurement contract not be set aside at the behest of a "disappointed bidder" unless the awarding agency's decision was irrational or clearly illegal.

Applying those principles to the case before it, the district court found that the initial decision to award the contract to Shaker was rational, notwithstanding plaintiff's contentions to the contrary. App. 278-82. The district court also found that the decision to choose Shaker even after it had submitted its modification on July 21, 1981, was rational. App. 284. The district court, however, found that NASA had violated a regulation governing the acceptance of late modifications. That regulation, 41 C.F.R. Ch.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
674 F.2d 1016, 29 Cont. Cas. Fed. 82,415, 1982 U.S. App. LEXIS 20596, Counsel Stack Legal Research, https://law.counselstack.com/opinion/princeton-combustion-research-laboratories-inc-v-mccarthy-ca3-1982.