Prince Manufacturing Co. v. United States

437 F. Supp. 1041, 1977 U.S. Dist. LEXIS 13591
CourtDistrict Court, N.D. Illinois
DecidedOctober 6, 1977
Docket76 C 4708
StatusPublished
Cited by4 cases

This text of 437 F. Supp. 1041 (Prince Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prince Manufacturing Co. v. United States, 437 F. Supp. 1041, 1977 U.S. Dist. LEXIS 13591 (N.D. Ill. 1977).

Opinion

MEMORANDUM OPINION

Motion and Cross-Motion for Summary Judgment

MAROYITZ, Senior District Judge.

Plaintiff Prince Manufacturing Company (“Prince”) brought this action against the United States and the Interstate Commerce Commission (the “Commission”) to review and set aside orders of the Commission entered in Docket No. 36102, The Prince Manufacturing Company v. Norfolk and Western Railway Company, (“N&W”). In that order, the Commission found certain demur-rage charges levied against Prince neither unjust nor unreasonable and, accordingly, dismissed Prince’s complaint seeking waiver of undercharges. Jurisdiction of this Court is invoked pursuant to 28 U.S.C. § 1336(a).

Pending before the Court are plaintiff’s motion for summary judgment and defendants’ joint cross-motion for summary judgment. Neither party claims a genuine issue of a material fact and both plaintiff and defendants seek a judgment in their favor as a matter of law. For the reasons set forth below, defendants’ motion is denied and plaintiff’s motion is granted, with modification of the relief sought.

I.

The facts of this case are not disputed. On October 24, 1972, Prince ordered 8 carloads of iron ore from Cleveland Cliffs Iron Ore Company of Ishpeming, Michigan, for shipment to its Quincy, Illinois plant. On November 13, 1972, Prince ordered 8 additional cars. Both orders called for immediate shipment. The ore was available but was not shipped immediately because the originating carrier failed to make cars available. Four cars were shipped between November 7 and November 9 and unloaded upon arrival. The remaining 12 cars were shipped between November 27-30 and arrived between December 6-15.

During the first part of December, the weather in Illinois turned unusually cold, with temperatures dropping as low as 20 degrees below zero. When the cars arrived at Quincy, they were frozen solid. On December 11 and 12, the ore-laden cars were subjected to an ice storm which rendered Prince’s shipment into 12 solid blocks.

The twelve cars were detained for a total of 1,158 days, an average of 96.5 days per car. Prince was precluded from using open fires to thaw the cars by the Environmental Protection Act of 1970 and the Regulations of the Illinois Environmental Protection Agency. Prince did succeed in unloading one car during a short thaw in early February, 1973, through the use of 40 person-hours of labor and 40 hours of crane time. Thereafter, the weather again turned cold. Prince’s employees checked the remaining cars several times to determine if unloading could be accomplished by ordinary means. When the weather finally warmed, Prince began unloading the 11 remaining cars, which were released between March 15 and April 9, 1973.

Under the N&W tariff, over $32,000 of compensatory and penalty demurrage charges were assessed against Prince. On November 27,1974, Prince filed a complaint with the Commission, alleging that the penalty portion of the demurrage charges was unreasonable, in violation of Section 1 of the Interstate Commerce Act, 49 U.S.C. § 1. Prince made no objection to the compensatory charges levied by N&W.

*1044 The Administrative Law Judge (“ALJ”) who reviewed the evidence concluded, in an initial decision served June 19, 1975, that Prince had exercised due diligence in the handling and disposition of the 12 cars, and found the penalty charges to be unjust and unreasonable. Exceptions to the ALJ’s decision were filed by the N&W, to which Prince did not reply.

Review Board Number 4 reversed the decision of the ALJ in a report and order served December 3, 1975. The Review Board found that Prince had not demonstrated that it made any “special efforts” to minimize the 1,158 detention days. Prince filed a petition for reconsideration, to which the N&W replied. The Commission, Appellate Division 2, denied the petition in an order served May 5, 1976, reinstating the report and order of Review Board Number 4 served December 3, 1975. On December 23, 1975, Prince brought this action for this Court’s review of the Commission’s decision.

The question before the Court is whether the Commission’s finding that certain demurrage charges were just and reasonable is supported by substantial evidence, and is not arbitrary, capricious, or otherwise not in accordance with the law.

II.

The threshold question, however, is whether the Report and Order of Review Board Number 4 is the Report and Order of the Commission. If it is not, plaintiff contends, then the Commission has neglected to include a statement of “findings and conclusions, and the reasons or basis therefor, on all the material issues of fact, law, or discretion presented on the record,” a violation of 5 U.S.C. § 557(c). See also, 5 U.S.C. § 555(e).

It is clear, however, that the Commission, Appellate Division 2, explicitly adopted the decision of Review Board Number 4. The Commission’s order reads in part:

It is further ordered, That the report and order entered in this proceeding on November 20,1975, and served December 3,1975, which pursuant to section 17(8) of the Interstate Commerce Act was stayed pending disposition of the petition [for reconsideration filed by Prince] be, and it is hereby, reinstated without any change in the requirements of said report and order, including the requirement that the complaint be, and it is hereby, dismissed^]

We therefore agree with defendants that in determining whether the Commission’s decision has a clearly articulated basis, this Court must focus on the decision of Review Board Number 4. We must also decide, however, whether that decision was in accord with the Commission’s prior position on penalty charges.

III.

As defendants point out, demur-rage — the right of a carrier to assess charges for undue detention of its equipment — is a well established institution in the transportation industry. Iversen v. United States, 63 F.Supp. 1001, 1003-05 (D.D.C.1946), aff’d mem., 327 U.S. 767, 66 S.Ct. 825, 90 L.Ed. 998 (1946). Demurrage existed at common law, and continues to exist subject to regulation by the Commission. Turner, Dennis & Lowry Lumber Co. v. Chicago, M. & St. P. Ry., 271 U.S. 259, 262, 46 S.Ct. 530, 70 L.Ed. 934 (1926). Demurrage serves two purposes. Its first function is to compensate the carrier for any loss incurred by the detention of its cars. Its second function, at issue in the case at bar, is to deter the shipper or consignee from reducing the efficiency of the rail system by needlessly detaining cars. Id. Thus, demurrage includes both compensatory and regulatory, or penalty, elements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gunia v. Cook County Sheriff's Merit Board
570 N.E.2d 653 (Appellate Court of Illinois, 1991)
Moore v. Department of Driver Services
559 N.E.2d 182 (Appellate Court of Illinois, 1990)
Nevada Power Co. v. Watt
515 F. Supp. 307 (D. Utah, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
437 F. Supp. 1041, 1977 U.S. Dist. LEXIS 13591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prince-manufacturing-co-v-united-states-ilnd-1977.