Primrose Retirement Communities, L.L.C. v. Omni Contruction Company, Inc.

CourtDistrict Court, D. South Dakota
DecidedSeptember 25, 2017
Docket1:17-cv-01007
StatusUnknown

This text of Primrose Retirement Communities, L.L.C. v. Omni Contruction Company, Inc. (Primrose Retirement Communities, L.L.C. v. Omni Contruction Company, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Primrose Retirement Communities, L.L.C. v. Omni Contruction Company, Inc., (D.S.D. 2017).

Opinion

UNITED STATES DISTRICT COURT FILED DISTRICT OF SOUTH DAKOTA SEP 25 2017

NORTHERN DIVISION her

PRIMROSE RETIREMENT COMMUNITIES, 1:17-CV-01007-RAL L.L.C., AND RACINE RETIREMENT, L.L.C., Plaintiffs, OPINION AND ORDER CONFIRMING ARBITRATION AWARD vs. OMNI CONTRUCTION COMPANY, INC., Defendant.

Plaintiffs Primrose Retirement Communities, LLC and Racine Retirement, LLC (collectively “Primrose’”) filed this action in state court together with a Motion to Confirm Arbitration Award and Enter Judgment Thereon, Doc. 1-1. Defendant Omni Construction Company, Inc. (Omni) removed the action to this Court. Doc. 1. Jurisdiction exists under the Federal Arbitration Act, 9 U.S.C. § 1-10, and under 28 U.S.C. § 1332, diversity of citizenship jurisdiction. Omni resisted the Motion to Confirm Arbitration Award and filed a Motion to Either Vacate or Modify the Arbitration Award, Docs. 7, 8, 9, 21. Primrose opposed that motion. Docs. 19, 20. This Court held oral argument on the motion and requested filing of the transcript and exhibits of the arbitration to more fully consider Omni’s arguments in the context of the entire case. Doc. 22. The transcript and exhibits of the arbitration hearing then were filed. Does. 23, 24. For the reasons explained herein, this Court confirms the arbitration award in favor of Primrose and denies Omni’s motion to vacate or modify the award. I. Summary of Material Facts

Plaintiffs, which are being jointly referred to as “Primrose” in this Opinion and Order, are South Dakota limited liability corporations with their principal places of business in Aberdeen, South Dakota. Doc. 1-1 at 2. Primrose entered into a Form Agreement Between Primrose and Contractor (the Contract) with Omni on July 26, 2013, for the construction in the Village of Mount Pleasant, Wisconsin, of a 76-unit independent and assisted living facility and a four building, eight-unit independent living villas (the Project). Doc. 1-1 at 6-59. The Contract required Omni to achieve substantial completion of the entire work no later than 52 calendar weeks from date of commencement, Doc. 1-1 at 7, § 3.3, and had a fixed contract sum of $7,809,540, Doc. 1-1 at 8, 7 4.1. The contract attached and referenced General Conditions of Contract for Construction (General Conditions). Doc. 1-1 at 6, § 1; Doc. 1-1 at 13-53. Section 4.6 of the General Conditions contained valid and enforceable arbitration provisions, including § 4.6.2: Claims not resolved by mediation shall be decided by arbitration which unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect. The agreed hearing locale of any arbitration proceeding shall be at Aberdeen, South Dakota unless the parties mutually agree otherwise... Doc. 1-1 at 31. Section 4.6.6 of the General Conditions makes any arbitration award final, allows judgment to be entered thereon, and selects South Dakota state or federal court for any action to confirm or challenge any arbitration award. Doc. 1-1 at 32. The date of commencement of the Project was on or about August 12, 2013. Disputes arose between Primrose and Omni during construction. Omni fell behind schedule, which it blamed on the weather, other excusable neglect, and Primrose’s withholding of some progress payments. Primrose and Omni discussed the importance of Omni making up time. Primrose became deeply concerned about Omni’s delays, Omni’s personnel turnover, days when little to

no work was being done, and Omni’s varying excuses for being behind schedule. Primrose and Omni discussed as early as January of 2014 whether termination of the Contract for cause should occur, and Omni at that time assured Primrose that it could make up lost time. The parties adjusted the completion deadline. In the summer of 2014, it became clear that Omni would not complete the Project by the adjusted completion deadline. Primrose delivered its first Notice to Cure to Omni, which prompted Omni to forecast “a new and unlikely completion date” as the arbitration award put it. See Doc. 1-1 at 57. That schedule also was adjusted again. Primrose’s representatives visited the Project site on October 27, 2014; found no one from Omni on site; and learned that Omni’s latest of four superintendents had quit the job the previous Friday. On October 28, 2014, Primrose chose to terminate Omni’s contract for cause based on Omni’s breach and hired other contractors to complete the project. Primrose then filed a demand for arbitration under Section 4.6 of the General Conditions seeking various damages and relief. Omni answered and counterclaimed seeking damages from Primrose under a number of claims and theories. The parties conducted discovery, including depositions taken of each other’s key witnesses and experts. A three arbitration panel—James Duffy O’Connor, an attorney and the chair of the Construction Law Group of Maslon Edelman Borman & Brand, LLP; John G. Patterson, an attorney in the construction law practice of Fredrikson & Byron, P.A.; and William M. Beadie, a construction, contracts and construction surety lawyer at Moore, Costello & Hart, P.L.L.P— convened in Aberdeen for a five day evidentiary arbitration hearing from December 6 to December 10, 2016. The arbitrators heard from nine witnesses testifying live at the hearing, considered three video depositions together with deposition transcripts, and received thousands of pages of exhibits contained in some ten three-ring binders. The transcript of the arbitration

hearing is 1,676 pages long. Review of the transcript and materials from the arbitration makes clear that both sides were given an ample opportunity to present their evidence, case and arguments. The Scheduling Order issued by the arbitrators on December 3, 2015, prior to the arbitration stated in Paragraph 17: The arbitrators shall issue reasoned awards for both cases’ unless the parties agree otherwise. A “reasoned” award means that the arbitration will set out a brief summary of the principal reasons supporting their award(s), but shall not include findings of fact or conclusions of law. Doc. 9-3 at 17. On March 15, 2017, the arbitrators issued a six-page Final Award of Arbitrators. Doc. 1-1 at 54-59. The Final Award found that “Omni breached the Contract by substantially falling short of completing their work within the Contract time, and that Primrose was justified in terminating Omni for cause.” Doc. 1-1 at 55. The arbitrators addressed and rejected Omni’s excuses for its delays. Doc. 1-1 at 55-57. Although the arbitrators found that “Omni suffered some excusable delay because of unusually severe weather, the extent of the delay falls substantially short of the number of days Omni claims.” Doc. 1-1 at 56. The arbitrators found Omni’s final forecasted completion date to be unrealistic and that “[tJhe percentage of completion referenced in the Pay Applications leading up to the date of Omni’s termination, were not binding on the parties, were disputed and were not the most reliable measure of the remaining Work.” Doc. 1-1 at 57-58. The arbitrators rejected some of Primrose’s arguments, including that Omni’s claims were untimely and that Primrose sustained damage from Omni filing an incorrect and overstated lien claim. Doc. 1-1 at 58. The arbitrators did not grant Omni relief on any of its counterclaims. Doc. 1-1 at 54.

' The parties have a dispute concerning another project that is subject to arbitration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Primrose Retirement Communities, L.L.C. v. Omni Contruction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/primrose-retirement-communities-llc-v-omni-contruction-company-inc-sdd-2017.