PRIME EAGLE GROUP LTD. v. Steel Dynamics, Inc.

614 F.3d 375, 2010 U.S. App. LEXIS 15337, 2010 WL 2899097
CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 27, 2010
Docket09-1663
StatusPublished
Cited by21 cases

This text of 614 F.3d 375 (PRIME EAGLE GROUP LTD. v. Steel Dynamics, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PRIME EAGLE GROUP LTD. v. Steel Dynamics, Inc., 614 F.3d 375, 2010 U.S. App. LEXIS 15337, 2010 WL 2899097 (7th Cir. 2010).

Opinion

EASTERBROOK, Chief Judge.

Nakornthai Strip Mill Public Company Limited began building a new steel mini-mill in Thailand during the 1990s. When the project ran into technical and financial difficulties, it asked Steel Dynamics, a film with expertise in developing and running steel mini-mills, to lend assistance. Steel Dynamics did so, and it also helped Nakornthai raise capital. The mill was started and seemingly ran productively. But in late 1998 steel prices were down, the economy of Southeast Asia was in recession, and Steel Dynamics concluded that the venture was going to lose money. It decided to withdraw, lest it become liable for some of these losses. (Steel Dynamics had dispatched a management team that had operational control of the mill.) Prime Eagle Group, which sues as Nakornthai’s assignee, contends in this litigation under the international-diversity jurisdiction, see 28 U.S.C. § 1332(a)(2), that Steel Dynamics chose fraud as its means of exit and must pay damages in tort. The parties agree that Indiana law supplies the rule of decision.

According to Prime Eagle, the fraud was telling Nakornthai’s board of directors and principal investors that the mini-mill had design flaws that would cost about $100 million to fix. When the management team under Steel Dynamics’ control began preparations for these changes, major investors pulled the plug. The mill was idle from December 1998 (when it was put out of service by lightning) until it restarted in December 2003. Meanwhile, Nakornthai was reorganized under Thai insolvency law. In June 2002 it commissioned an engineering study, which two months later concluded that the mill’s design and construction were sound. The mill has operated successfully since its restart, without the costly changes that Steel Dynamics had said were essential. Prime Eagle believes that Steel Dynamics must pay $1 billion for losses suffered while the mill was idle or operated at less than capacity, plus the costs of conducting the Thai reorganization proceeding.

Prime Eagle filed this suit in 2008, a decade after the supposed fraud. (We have recited the complaint’s allegations, which may or may not be true.) The statute of limitations in Indiana is six years. Ind.Code § 34-11-2-7(4). A claim accrues, and the statute of limitations begins to run, “when a claimant knows or in the exercise of ordinary diligence should have known of the injury.” Cooper Industries, LLC v. South Bend, 899 N.E.2d 1274, 1280 (Ind.2009).

Steel Dynamics observes that Nakornthai knew of the injury when the mill was closed; Prime Eagle replies that Nakornthai did not know that it had been played false until the consultant’s report in 2002. Cf. Merck & Co. v. Reynolds, — U.S.-, 130 S.Ct. 1784, 176 L.Ed.2d 582 (2010) (discussing the discovery doctrine for federal securities claims). Normally knowledge of who injured you is essential, in addition to knowledge of the injury’s existence. See Jay E. Hayden Foundation v. First Neighbor Bank, N.A., 610 F.3d 382, 386-87 (7th Cir.2010). Nakornthai knew the “who” no later than it knew the existence of its injury.

Prime Eagle asks us to treat knowledge of a given person’s culpability, as well as that person’s causal role, as an additional element of a claim’s accrual. That’s a less *378 common element. See United States v. Kubrick, 444 U.S. 111, 119-25, 100 S.Ct. 352, 62 L.Ed.2d 259 (1979). The district judge did not decide whether a claim’s accrual is postponed until the victim knows about the defendant’s fault, because Nakornthai had actual knowledge on that front no later than September 1998, when its own president wrote the board of directors a detailed letter disagreeing with Steel Dynamics and concluding that the mill should be restarted as is. The board chose to fire its president instead and cannot maintain that it was ignorant. The court found the suit untimely and entered judgment for Steel Dynamics. 2009 WL 449173, 2009 U.S. Dist. LEXIS 13943 (N.D.Ind. Feb. 23, 2009).

Although the parties have filed lengthy briefs covering many subjects, the only one that we need to discuss is whether the president’s knowledge is imputed to Nakornthai. If it is, then Nakornthai knew in fall 1998 that Steel Dynamics’ assertions were false, or at least questionable enough to justify an investigation. The report commissioned in 2002 could have been commissioned in 1998. (We put to one side the question why Prime Eagle waited years after Nakornthai received the consultant’s report. Legal counsel had to have appreciated that a court might deem the claim to have accrued earlier. Waiting until what is by one’s own calculation the tail end of a period of limitations is a formula for disaster.)

Nakornthai’s president during 1998 was John Schultes, an engineer who had worked for USX (U.S. Steel) before he joined Nakornthai as President and CEO in October 1995. That was well before Steel Dynamics became involved. No one contends that Schultes was beholden to Steel Dynamics or under its influence. Schultes knew the design of the plant and believed that Steel Dynamics was wrong in asserting that major changes were required. He told the board of directors this in a comprehensive letter. He was fired for his troubles — but his view was vindicated by the consultant’s report in 2002 and the successful restart of the mill in 2003.

Corporations do not have brains, but they do have employees. One fundamental rule of agency law is that corporations “know” what their employees know— at least, what employees know about subjects that are within the scope of their duties. (What a mailroom employee knew, or thought he knew, about the plant’s design would not be imputed to Nakornthai.) Schultes knew in 1998 that Steel Dynamics was not giving Nakornthai accurate information; therefore Nakornthai itself knew this. See EEOC v. G-K-G, Inc., 39 F.3d 740, 748 (7th Cir.1994); William Meade Fletcher, Cyclopedia of the Law of Corporations § 811 (2010 ed.) (“notice to and knowledge of the president of a corporation relating to its affairs and business is notice to and knowledge of the corporation”). And Nakornthai’s injury began (and the claim thus accrued) no later than July 1999, when its investors withdrew their support, left the plant idle, and threw the firm into insolvency.

Prime Eagle says that this is not so, because Schultes was “in an extremely diminished capacity.” Presumably this does not mean that he was on the verge of insanity. What Prime Eagle means is that he had lost the board’s confidence and was on his way out. But the board has itself to blame. You can’t stare the truth in the face, disbelieve it, and then claim to have been ignorant. See Acme Propane, Inc. v. Tenexco, Inc., 844 F.2d 1317 (7th Cir.1988) (a truthful written disclosure prevents a claim of reliance on oral deceit).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buccini v. Carrasco
N.D. Illinois, 2025
LJM Partners, Ltd. v. Does
N.D. Illinois, 2023
Torres v. LVNV Funding, LLC
N.D. Illinois, 2018
Samaron Corp. v. United of Omaha Life Insurance
822 F.3d 361 (Seventh Circuit, 2016)
Price Waicukauski & Riley, LLC v. Murray
47 F. Supp. 3d 810 (S.D. Indiana, 2014)
Michelle Knight v. Enbridge Pipelines (FSP)
759 F.3d 675 (Seventh Circuit, 2014)
United States v. Anchor Mortgage Corp.
711 F.3d 745 (Seventh Circuit, 2013)
Peterson v. McGladrey & Pullen, LLP
676 F.3d 594 (Seventh Circuit, 2012)
Alexander Chemical Corp. v. G.S. Robins & Co.
852 F. Supp. 2d 1048 (N.D. Illinois, 2012)
Premium Plus Partners, L.P. v. Goldman, Sachs & Co.
648 F.3d 533 (Seventh Circuit, 2011)
Fish v. Greatbanc Trust Co.
830 F. Supp. 2d 426 (N.D. Illinois, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
614 F.3d 375, 2010 U.S. App. LEXIS 15337, 2010 WL 2899097, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prime-eagle-group-ltd-v-steel-dynamics-inc-ca7-2010.