Price-Orem Investment Co. v. Rollins, Brown & Gunnell, Inc.

784 P.2d 475, 123 Utah Adv. Rep. 37, 1989 Utah App. LEXIS 187, 1989 WL 151312
CourtCourt of Appeals of Utah
DecidedDecember 14, 1989
Docket870550-CA
StatusPublished
Cited by25 cases

This text of 784 P.2d 475 (Price-Orem Investment Co. v. Rollins, Brown & Gunnell, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Price-Orem Investment Co. v. Rollins, Brown & Gunnell, Inc., 784 P.2d 475, 123 Utah Adv. Rep. 37, 1989 Utah App. LEXIS 187, 1989 WL 151312 (Utah Ct. App. 1989).

Opinion

OPINION

GARFF, Judge:

Appellant Rollins, Brown & Gunnell, Inc. (Rollins) appeals the trial court’s judgment of $21,210.80 against it, pursuant to a tort action brought by respondent Price-Orem Investment Co. (Price-Orem). Price-Orem cross appeals, requesting prejudgment interest and a higher award of costs. We affirm.

During July 1973, John Price Associates, Price-Orem’s general partner, contracted with Rollins to survey property owned by Price-Orem, which was to be developed into the Orem Plaza Shopping Center. Later, Price-Orem acquired a second parcel of property adjacent to the north boundary of the first parcel.

John Price Associates again contracted with Rollins to stake the layout of the shopping center buildings, which were to be built on both parcels of property. Rol-lin’s employee erroneously surveyed the layout for the buildings.

Not realizing that this mistake had been made, Price-Orem commenced building in accordance with Rollins’ faulty survey. On July 17, 1974, after construction on the shopping center had been started but before it had been substantially completed, Price-Orem discovered the error. Rollins admitted its mistake and sought to ameliorate the error by submitting to Price-Orem various proposals, costing about $3,000 apiece, to correct the error. Price-Orem, however, refused to implement any of these suggestions because of the resulting delay, possible loss of its anchor tenant, and potentially increased financing costs. Instead, Price-Orem determined to adjust for the error by shortening the shop space thirty feet. Because the shop space, as constructed, was seventy feet deep, Price-Orem lost 2100 square feet of shop space due to the error.

Price-Orem filed this action on September 5, 1974, which was tried before a jury on November 17 to 19, 1980. The jury returned a verdict for Price-Orem, assessing damages of $30,000. Rollins moved for judgment NOV, remittitur, or a new trial, asserting that damages were excessive because the evidence demonstrated that the cost of repair at the time the error was discovered was $3,000 and, also, that any additional retail space would have violated Orem City parking requirements.

On January 12, 1981, upon Rollins’ motion, the trial court ruled that the evidence was insufficient to justify the verdict and granted a new trial. On the day of trial, however, the trial court determined that John Price Associates, which had not been named in the action, was a necessary and indispensable party. Upon Priee-Orem’s refusal to name John Price Associates in its complaint, the court dismissed the action. Price-Orem appealed. The Utah Supreme Court then reversed and remanded the case for trial.

The case again came to trial on June 1 to 3, 1987. Price-Orem introduced, as evidence showing the amount of damages, an appraisal made in 1977 by Ralph Wright, a professional appraiser. Using an income approach to valuation, Wright estimated that the present value of the lost income over forty years was $72,351 and the cost of constructing the lost space would have been $42,000, resulting in a net loss of $30,351. He based his appraisal upon 1977 economic assumptions rather than the actual rental history of the shopping center occurring after 1977. Price-Orem presented testimony that it had paid, additionally, $3,000 to redraw the shopping center plans, $210 for additional curb and gutter work, and $300 for extra piping. Rollins presented evidence concerning the amount of parking required for the complex and testimony that the shopping center, as presently constructed, did not have sufficient parking space to comply with the applicable Orem City parking ordinances.

The jury found both parties negligent, attributing forty percent to Price-Orem and sixty percent to Rollins. It determined *478 that Price-Orem had been damaged in the amount of $33,861. The jury reduced this amount by forty percent, the amount of Price-Orem’s negligence, finding that Price-Orem was entitled to a net judgment of $20,316.60 plus costs. The trial court fixed costs at $894.20, which included Price-Orem’s cost of transcripts on the previous appeal.

Rollins filed motions for a directed verdict, judgment NOV, and to tax costs, asserting that Price-Orem was not entitled to recover the cost of the previous trial transcripts. Price-Orem moved for an award of prejudgment interest on its damage award. The trial court ultimately awarded Price-Orem $20,317 in damages and $297.30 in costs, which did not include the cost of the transcripts. It also denied Rollins’ motion for judgment NOV and Price-Orem’s motion for prejudgment interest.

Rollins appeals and Price-Orem cross-appeals.

The parties raise the following issues: (1) Did the trial court err in admitting into evidence an appraisal based upon estimated income of the shopping center when actual income data was available? (2) Did the trial court err in denying Rollins’ motion for directed verdict or judgment NOV where evidence was presented indicating that construction of the lost retail space would have violated Orem City parking ordinances? (3) Is Price-Orem entitled to an award of prejudgment interest? (4) Is Price-Orem entitled to an award for the cost of the trial transcripts used in the previous appeal?

DAMAGES.

Rollins asserts that the trial court erred by admitting into evidence Price-Orem’s appraisal based upon the estimated income of the shopping center, when actual income data was available. It argues that Price-Orem’s evidence was insufficient because historical data should have been relied upon, instead, to support the trial court’s award of damages, and that Priee-Orem’s only evidence for curb, gutter work, and plumbing expenses was unsupported testimony. Therefore, Rollins argues that the damage award was based upon unsubstantial and inadequate evidence and that its motions for directed verdict and judgment NOV should have been granted.

We note, initially, that we “will reverse a judgment based on a jury verdict ‘only if, viewing the evidence in the light most favorable to the verdict, there is no substantial evidence to support it.’ ” Canyon Country Store v. Bracey, 781 P.2d 414, 417 (Utah 1989) (quoting In re Estate of Kesler, 702 P.2d 86, 88 (Utah 1985)). We find, first, under this standard, that Price-Orem’s uncontroverted testimony as to the curb, gutter, and plumbing expenses was sufficient evidence to support the trial court’s award of those expenses.

We must, however, still determine whether Price-Orem’s appraisal was sufficient evidence to support the remainder of the judgment. The objective in rendering an award of damages is to award the injured party full compensation for actual losses incurred, see Henderson v. For-Shor Co., 757 P.2d 465, 469 (Utah Ct.App.1988), by evaluating any loss “suffered by the most direct, practical and accurate method that can be employed.” Even Odds, Inc. v. Nielson, 22 Utah 2d 49, 448 P.2d 709, 711 (1968).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Total Restoration Inc. v. Merritt
2017 UT App 162 (Court of Appeals of Utah, 2017)
Francis v. National DME
2015 UT App 119 (Court of Appeals of Utah, 2015)
Stevens-Henager College v. Eagle Gate
2011 UT App 37 (Court of Appeals of Utah, 2011)
STEVENSEN 3RD EAST, LC v. Watts
2009 UT App 137 (Court of Appeals of Utah, 2009)
Traco Steel Erectors, Inc. v. Comtrol, Inc.
2007 UT App 407 (Court of Appeals of Utah, 2007)
Birch v. Fire Insurance Exchange
2005 UT App 395 (Court of Appeals of Utah, 2005)
Smith v. Fairfax Realty, Inc.
2003 UT 41 (Utah Supreme Court, 2003)
Kilpatrick v. Wiley, Rein & Fielding
2001 UT 107 (Utah Supreme Court, 2001)
Lefavi v. Bertoch
2000 UT App 5 (Court of Appeals of Utah, 2000)
Cooperative Communications, Inc. v. at & T
31 F. Supp. 2d 1317 (D. Utah, 1999)
Alta Health Strategies, Inc. v. CCI Mechanical Service
930 P.2d 280 (Court of Appeals of Utah, 1996)
Utah Foam Products Co. v. Upjohn Co.
930 F. Supp. 513 (D. Utah, 1996)
State v. Jaeger
896 P.2d 42 (Court of Appeals of Utah, 1995)
Klinger v. Kightly
889 P.2d 1372 (Court of Appeals of Utah, 1995)
Anesthesiologists Associates of Ogden v. St. Benedict's Hospital
852 P.2d 1030 (Court of Appeals of Utah, 1993)
Anesthesiologists Assoc. v. ST. BENEDICT'S
852 P.2d 1030 (Court of Appeals of Utah, 1993)
Krauss v. Utah State Department of Transportation
852 P.2d 1014 (Court of Appeals of Utah, 1993)
Andreason v. Aetna Casualty & Surety Co.
848 P.2d 171 (Court of Appeals of Utah, 1993)
Brown v. Richards
840 P.2d 143 (Court of Appeals of Utah, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
784 P.2d 475, 123 Utah Adv. Rep. 37, 1989 Utah App. LEXIS 187, 1989 WL 151312, Counsel Stack Legal Research, https://law.counselstack.com/opinion/price-orem-investment-co-v-rollins-brown-gunnell-inc-utahctapp-1989.