National Steel Corporation v. The Great Lakes Towing Company

574 F.2d 339, 1979 A.M.C. 369, 1978 U.S. App. LEXIS 11759
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 10, 1978
Docket76-2033
StatusPublished
Cited by8 cases

This text of 574 F.2d 339 (National Steel Corporation v. The Great Lakes Towing Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Steel Corporation v. The Great Lakes Towing Company, 574 F.2d 339, 1979 A.M.C. 369, 1978 U.S. App. LEXIS 11759 (6th Cir. 1978).

Opinion

JOHN W. PECK, Circuit Judge.

Plaintiff National Steel Corporation owns and operates four blast furnaces, on Zug Island, in the Rouge River near Detroit. The steelmaking capacity of the plant is determined by the output of the Zug Island furnaces, which normally operate at full capacity around the clock, seven days a week. The rest of the steelmaking facility is located on the mainland across the Short Cut Canal, and a railroad bridge owned by the plaintiff is the only means of transporting hot iron ore from the island to the mainland to be processed into steel slabs.

On October 11, 1972, defendant Great Lakes Towing Company was towing a Greek vessel, the Navishipper, up the river when one of the towlines snapped. The boat swung against the plaintiffs railroad bridge, causing structural damage. Repairs were promptly carried out, and the bridge was back in full use three days later.

Immediately after the collision National Steel stopped the transportation of hot ore across the bridge. After examination of the bridge, it was determined that light loads could be safely moved across, by alternating loaded cars with empty cars. Only three of the four furnaces were operating; the fourth was shut down for maintenance and repairs. By reducing the production of the three remaining blast furnaces as much as possible, the plaintiff was able to avoid shutting down the furnaces completely, and thus avoided significant shut-down and start-up costs. By the time repairs were completed on the bridge, approximately fifty hours of production were lost, amounting to slightly over 6000 tons of slabs of steel production.

The plaintiff brought an admiralty and maritime claim against the Navishipper, the tugboats, the Great Lakes Towing Company, and the manufacturers of the towline. At trial, all defendants other than the Great Lakes Towing Company were dismissed, liability was admitted by the defendant, and the trial was limited to the issue of damages. The plaintiff sought repair costs, expenses connected with the three days of impaired production, and damages for the lost fifty hours of production time.

Plaintiff routinely produces most of its steel needs, but to maintain an adequate inventory, from time to time it has to purchase supplemental supplies at an increased cost. Since it lost about 6000 tons of steel production during the three day interruption, and the plant normally operates at full capacity 365 days a year, plaintiff argues that it had to purchase 6000 tons more than it would have had to if there had been no interruption. Therefore, it contends that a reasonable measure of damages for lost production would be the difference between the cost to it of producing 6000 tons of steel, and the cost of purchasing 6000 tons in October, 1972.

The defendant argues, relying on plaintiff’s production records, that the 6000 tons of lost production were made up during the latter part of the month of October. There is no dispute that the average daily production after the accident was slightly greater than before the accident, and that the plaintiff actually exceeded its production goal in October. The plaintiff responds, however, that it operates continuously at full capacity, and that while daily production fluctuates somewhat, due to variations in the quality of raw materials and work crew efficiency, it has no power to “make *342 up” lost production time. Thus, even if production goals were exceeded, 6000 tons more would have been produced without the interruption.

Faced with this evidence, the district court found itself unable to decide whether the lost production time was made up due to a management decision, and thus decided the issue on the basis of which party had the burden of proof. While finding that $69,741 (the difference between the cost to National Steel to produce the steel and the cost to purchase it) was a reasonable measure of the value of the lost production, the district court held that the question of whether lost production was made up was not a matter of mitigation of damages, but was rather “a necessary part of the plaintiff’s presentation of proofs to support its claim for special damages.” Having thus concluded that the burden was on the plaintiff, the district court denied recovery for that element of damages, since the plaintiff had failed to convince the court by a preponderance of the evidence that it had not made up the lost production. Judgment was entered in favor of the plaintiff for repair costs and expenses directly related to the interruption of production only.

National Steel has appealed the denial of damages for lost production time. It argues that the trial court’s finding that the evidence was “about equal” on the question of whether lost production was made up was clearly erroneous, because the defendant presented no evidence to refute National Steel’s explanation for the fluctuating production levels. Further, it argues that even if the evidence was “equal,” the question is one of mitigation of damages, and the burden of proof should have been on the defendant.

Great Lakes Towing Company’s position is that the trial court was right in concluding that proof that the lost production time was not made up was part of plaintiff’s basic burden of proof as to loss. It also argues that the plaintiff failed to prove any connection between the alleged loss suffered and outside purchases of steel in October. Finally, the Towing Company contends that lost production time is an injury too remote for recovery.

Disposing of defendant’s final contention first, recovery for the value of production time lost as a result of negligence is permissible so long as the damages are proved to a “reasonable degree of certainty.” Cranston Print Works Co. v. Public Service Co. of N.C., 291 F.2d 638, 649 (4th Cir. 1961). Any harm proximately caused by negligent actions of a defendant is compensable, and although damages may not be determined by speculation or guesswork, evidence allowing a just and reasonable estimate of the damage based on relevant data is sufficient. Bigelow v. RKO Radio Pictures, Inc., 327 U.S. 251, 66 S.Ct. 574, 90 L.Ed. 652 (1946). The bridge had been used for many years as the sole means of transporting hot ore to the mainland. The Towing Company regularly moved boats through the Short Cut Canal, and its dock was located upstream of the bridge. The collision was the sole, direct cause of the interruption of production, and it was plainly foreseeable that damaging the bridge would have the result of denying the Steel Company the use of its production facilities. On rare occasions courts deny recovery of even foreseeable, proximately-caused damages on the grounds that the injury is too remote, and the defendant contends that this is such a case, relying on the well-known opinions in Petition of Kinsman Transit Co., 338 F.2d 708 (2d Cir. 1964) and 388 F.2d 821 (2d Cir. 1968). In those cases, a vessel was negligently tied and anchored in the Buffalo River. In January, an ice jam broke loose upriver and lodged against the boat, breaking her mooring lines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
574 F.2d 339, 1979 A.M.C. 369, 1978 U.S. App. LEXIS 11759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-steel-corporation-v-the-great-lakes-towing-company-ca6-1978.