Preload, Inc. v. Hammond Water Works Department and Jeffrey Porter General Contractors, Inc.

CourtIndiana Court of Appeals
DecidedAugust 6, 2012
Docket45A05-1201-PL-22
StatusUnpublished

This text of Preload, Inc. v. Hammond Water Works Department and Jeffrey Porter General Contractors, Inc. (Preload, Inc. v. Hammond Water Works Department and Jeffrey Porter General Contractors, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Preload, Inc. v. Hammond Water Works Department and Jeffrey Porter General Contractors, Inc., (Ind. Ct. App. 2012).

Opinion

Pursuant to Ind.Appellate Rule 65(D), this Memorandum Decision shall not be regarded as precedent or cited before any court except for the purpose of establishing the defense of res judicata, collateral estoppel, or the law of the case. FILED Aug 06 2012, 9:03 am ATTORNEYS FOR APPELLANT: J. MICHAEL CAVOSIE CLERK E. ROY RODABAUGH of the supreme court, court of appeals and tax court Easter & Cavosie Indianapolis, Indiana

IN THE COURT OF APPEALS OF INDIANA

PRELOAD, INC., ) ) Appellant-Third-Party Defendant ) ) vs. ) No. 45A05-1201-PL-22 ) HAMMOND WATER WORKS ) DEPARTMENT, ) ) and ) ) JEFFREY PORTER GENERAL ) CONTRACTORS, INC., ) Appellees-Plaintiffs. )

APPEAL FROM THE LAKE SUPERIOR COURT The Honorable William E. Davis, Judge Cause No. 45D05-1104-PL-42

August 6, 2012

MEMORANDUM DECISION - NOT FOR PUBLICATION

BAILEY, Judge Case Summary

Preload, Inc. (“Preload”), appellant and third-party defendant, appeals from the trial

court’s order compelling it to engage in arbitration with Jeffrey Porter General Contractors,

Inc. (“Jeffrey Porter”), appellee and plaintiff, and the Hammond Water Works Department

(“Hammond Water”), appellee and defendant/third-party plaintiff.

We affirm in part, reverse in part, and remand.

Issue

Preload presents a single issue on appeal, which we restate as whether the trial court

erroneously ordered Preload joined into an arbitration between Jeffrey Porter and Hammond

Water based upon identical arbitration provisions in separate agreements.

Facts and Procedural History

On May 1, 2008, Preload contracted with Hammond Water to construct tanks on a

project named “Contract 1 – Two 6MG Prestressed Tanks” (“Contract 1”). (App. at 15.) On

July 23, 2008, Jeffrey Porter contracted with Hammond Water to perform excavation and

landscaping work on a project named “Contract 3 – Package Pumping Station Installation

and Yard Piping” (“Contract 3”). (App. at 3.)

Although the parties entered into separate contracts—one between Preload and

Hammond Water, the other between Jeffrey Porter and Hammond Water—governing

separate projects, both Contract 1 and Contract 3 incorporated by reference a common set of

general conditions. The general conditions included an arbitration clause:

All claims, disputes, and other matters in question arising out of, or relating to, the Project Documents or the breach thereof, except for claims which have

2 been waived by the making and acceptance of final payment as provided for herein will be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. This agreement to arbitrate will be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators will be final, and judgment may be entered upon it in any court having jurisdiction thereof.

(App. at 14.)

On April 19, 2011, Jeffrey Porter filed suit against Hammond Water.1 In the

complaint, Jeffrey Porter alleged that it “was to use the top soil on the site to fulfill its

obligations” to perform landscaping work under Contract 3 (App. at 1), but that Hammond

Water had improperly removed the top soil, forcing Jeffrey Porter to advance costs for

replacement top soil. Jeffrey Porter therefore sought damages in compensation for its costs.

On June 8, 2011, Hammond Water filed its Answer to Complaint, Affirmative

Defenses and Third-Party Complaint. In the third-party complaint portion of the pleading,

Hammond Water alleged that, pursuant to Contract 1, Preload was to perform work “on the

same project site” as Jeffrey Porter, that Preload’s contract responsibilities included

excavation and landscaping, and that Preload removed any of the top soil that was the subject

of Jeffrey Porter’s suit. Referencing a provision in the contract with Preload that required

Preload to indemnify Hammond Water for any liability arising from “the failure, omission or

neglect of Preload” in performance under Contract 1, Hammond Water sought

indemnification against Preload for Jeffrey Porter’s claim. (App. at 12.)

Preload filed its answer and affirmative defenses to Hammond Water’s third-party 1 The City of Hammond was also a named defendant in the complaint. On August 25, 2011, Jeffrey Porter stipulated to the dismissal of the City of Hammond from the suit, and the trial court entered an order of dismissal as to the City on August 26, 2011. The City of Hammond is thus no longer a party to this action.

3 complaint on July 7, 2011. Among its affirmative defenses, Preload pled that Contract 1

included the above-cited arbitration clause and “this action should be stayed or dismissed

accordingly.” (App. at 23.)

On October 20, 2011,2 Jeffrey Porter filed a motion with the trial court to compel

Preload’s joinder into arbitration proceedings between Jeffrey Porter and Hammond Water:

Jeffrey Porter and [Hammond Water] have agreed to arbitration of this matter…. However, [Preload] refuses to participate in the arbitration. Wherefore, the Plaintiff, Jeffrey Porter, by counsel, requests the Court to order all three parties to arbitration for the purposes of trying to resolve this dispute amicably and for the economy of justice.

(App. at 29.)

On October 25, 2011, Preload filed its response to the motion to compel arbitration.

In its response, Preload argued that it could not be joined in the arbitration because Preload

and Jeffrey Porter were not in privity with each other, Preload and Jeffrey Porter were not

working on the same contract, the arbitration clause at issue did not expressly provide for

joinder of arbitration parties, and Hammond Water had in any event not yet been found liable

for damages by the arbitrator and thus was not yet entitled to indemnification from Preload.

On December 28, 2011, the trial court conducted a hearing on Jeffrey Porter’s motion

to compel arbitration. The same day, the trial court granted the motion to compel Preload’s

participation in the arbitration between Jeffrey Porter and Hammond Water.

This appeal ensued.

2 This date appears in the chronological case summary (“CCS”). We remind counsel that in civil appeals, our appellate rules provide that “the appellant’s Appendix shall contain … copies of the following documents, if they exist: (a) the chronological case summary for the trial court or Administrative Agency.” Ind. Appellate Rule 50(A)(2) (emphasis added). The CCS in this case was not provided by Preload in its appellant’s Appendix, but rather by the clerk of the trial court along with the hearing record.

4 Discussion and Decision

On appeal, Preload argues that the trial court erred when it compelled Preload’s

joinder in the arbitration between Jeffrey Porter and Hammond Water.

Ordinarily, we review an order compelling arbitration de novo. TWH, Inc. v. Binford,

898 N.E.2d 451, 453 (Ind. Ct. App. 2008). However, neither Jeffrey Porter nor Hammond

Water has filed a responsive brief in this court. In such circumstances, we do not undertake

the burden of developing arguments for the appellee. Id. We review the trial court’s order

for prima facie error. Id. at 453 n.1. Prima facie error is error “‘at first sign, on first

appearance, or on the face of it.’” Id. (quoting Railing v. Hawkins, 746 N.E.2d 980, 982

(Ind. Ct. App. 2001)).

“A written agreement to submit to arbitration is valid, and enforceable, an existing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loran W. Robbins v. B and B Lines, Inc.
830 F.2d 648 (Seventh Circuit, 1987)
Troy Bank & Trust Company v. Brantley
82 So. 2d 618 (Supreme Court of Alabama, 1955)
GREEN TREE SERVICING, LLC v. Brough
930 N.E.2d 1238 (Indiana Court of Appeals, 2010)
Mislenkov v. Accurate Metal Detinning, Inc.
743 N.E.2d 286 (Indiana Court of Appeals, 2001)
Strong v. Jackson
781 N.E.2d 770 (Indiana Court of Appeals, 2003)
Norwood Promotional Products, Inc. v. Roller
867 N.E.2d 619 (Indiana Court of Appeals, 2007)
TWH, INC. v. Binford
898 N.E.2d 451 (Indiana Court of Appeals, 2008)
Precision Homes of Indiana, Inc. v. Pickford
844 N.E.2d 126 (Indiana Court of Appeals, 2006)
Railing v. Hawkins
746 N.E.2d 980 (Indiana Court of Appeals, 2001)
Mayo v. State
681 N.E.2d 689 (Indiana Supreme Court, 1997)
Sanford v. Castleton Health Care Center, LLC
813 N.E.2d 411 (Indiana Court of Appeals, 2004)
Safety National Casualty Co. v. Cinergy Corp.
829 N.E.2d 986 (Indiana Court of Appeals, 2005)
Harry Baker Smith Architects II, PLLC v. Sea Breeze I, LLC
83 So. 3d 395 (Court of Appeals of Mississippi, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Preload, Inc. v. Hammond Water Works Department and Jeffrey Porter General Contractors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/preload-inc-v-hammond-water-works-department-and-jeffrey-porter-general-indctapp-2012.