Slutsky-Peltz Plumbing & Heating Co. v. Vincennes Community School Corp.

556 N.E.2d 344, 1990 Ind. App. LEXIS 838, 1990 WL 100849
CourtIndiana Court of Appeals
DecidedJuly 17, 1990
Docket63A01-9001-CV-36
StatusPublished
Cited by11 cases

This text of 556 N.E.2d 344 (Slutsky-Peltz Plumbing & Heating Co. v. Vincennes Community School Corp.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slutsky-Peltz Plumbing & Heating Co. v. Vincennes Community School Corp., 556 N.E.2d 344, 1990 Ind. App. LEXIS 838, 1990 WL 100849 (Ind. Ct. App. 1990).

Opinion

BAKER, Judge.

STATEMENT OF THE CASE

Defendant-appellants, Slutsky-Peltz Plumbing & Heating, Co. (Slutsky-Peltz) and Traylor Bros., Inc. (Traylor Bros.), appeal the trial court's order compelling them to submit to arbitration.

We affirm.

*345 STATEMENT OF THE FACTS

In the 1970's, plaintiff-appellee Vin-cennes Community School Corporation initiated plans to construct a new high school. Plaintiff-appellee, Vincennes Community School Building Corporation was created for the purpose of financing construction (the School Corporation and the Building Corporation will be referred to collectively in this opinion as "Vincennes"). Vincennes decided that a contract with multiple prime contractors was the most efficient way to solicit bids. Following the bidding process, Traylor Bros. was awarded the contract for general construction, Slutsky-Peltz was awarded the contract for the mechanical work, and Barth Electric Company (Barth) was awarded the contract for the electrical work.

Each of the three prime contractors entered into its own contract with Vincennes. The terms of each contract provided that Vincennes would assign, inter alia, the electrical and mechanical contracts for coordination to the contractor for general construction, Traylor Bros. The prime contracts required each prime contractor to coordinate its work with the work of the other prime contractors. With respect to coordination, Traylor Bros. was required under the contract to provide a project coordinator while Slutsky-Peltz was required to provide a coordinator for the mechanical and electrical aspects of the construction.

After construction commenced, coordination and scheduling were disrupted due to delays in completion of some of the projects. Coordination meetings were held at which complaints were lodged against Slutsky-Peltz for failing to coordinate its work with the other contractors and for its delay in completing its projects. When efforts to rehabilitate the scheduling and coordination problems proved unsuccessful, Barth, the electrical contractor, exercised its right under its prime contract to demand arbitration. On November 5, 1987, Barth made a demand for arbitration against Vincennes (hereinafter referred to as the Barth arbitration). In its application for arbitration, Barth alleged that delays and deviations had occurred on the project and that there was a failure of coordination between the prime contractors. Barth alleged it had been damaged thereby and sought monetary damages and time extensions to complete its work on the project.

In response to Barth's demand for arbitration, Vincennes filed a motion request ing joinder of Slutsky-Peltz and Traylor Bros. as third party defendants in the Barth arbitration. Subsequently, Slutsky, Peltz filed a separate demand for arbitration against Vincennes (the Slutsky-Peltz arbitration). In its application, Slutsky, Peltz alleged damages resulting from delays in the project, failure of coordination, and scheduling problems.

A pre-arbitration hearing was held in the Barth arbitration in which the arbitrators determined that Slutsky-Peltz and Traylor Bros. could not be joined in the Barth arbitration without either their consent or a court order compelling them to do so. The arbitrators gave Vincennes time in which to obtain a court order compelling Slutsky, Peltz and Traylor Bros. to participate in the Barth arbitration. Vincennes promptly filed an application to compel arbitration in which it requested joinder of the two prime contractors in the Barth arbitration. Both Slutsky-Peltz and Traylor Bros. moved to dismiss Vincennes' application for failure to state a claim upon which relief could be granted. Vincennes subsequently amended its application to request a stay of the Slutsky-Peltz arbitration pending decision of the joinder and consolidation issues arising from the Barth arbitration. It further filed a motion for summary judgment alleging there was no genuine issue of material fact with respect to the joinder of Slutsky, Peltz and Traylor Bros. in the Barth arbitration.

The trial court, after hearing oral argument on all motions, entered extensive findings of fact and conclusions of law and determined that Vincennes was entitled to summary judgment. The trial court ordered a stay of the Slutsky-Peltz arbitration and joinder of Slutsky-Peltz and Tray-lor Bros. in the Barth arbitration. The trial court further denied Slutsky Peltz's and *346 Traylor Bros.' motions to dismiss. Slut sky-Peltz and Traylor Bros. now appeal, raising one issue for our review which we restate as whether consolidation and join-der of all the prime contractors into one arbitration proceeding was proper under the terms of the prime contracts and under Indiana law.

DISCUSSION AND DECISION

Slutsky-Peltz and Traylor Bros. argue that while this dispute is subject to Indiana's Uniform Arbitration Act, IND. CODE 34-4-2-1 to -22, the trial court erred in ordering them to arbitrate because the Act does not specifically allow for join-der and consolidation of arbitration actions. We agree that the Act does not so provide. The Act, however, does not prohibit such action by the trial court. The statute's intended purpose is to provide a means for resolving disputes other than costly litigation. Shahan v. Brinegar (1979), 181 Ind.App. 39, 390 N.E.2d 1036. If this court were to construe the statute to limit to two the number of parties subject to arbitration, the underlying purpose of the statute would be defeated.

The statute instructs the trial court to determine whether an agreement to arbitrate exists between the parties. IND. CODE 34-4-2-3. If such an agreement exists, the trial court must order arbitration. In the present case, a contract that provides for arbitration exists. The question, therefore, is whether the arbitration provision in the contract amounts to an agreement by Slutsky-Peltz and Traylor Bros. to submit to arbitration through consolidation and joinder. The answer to this question is a matter of contract interpretation.

Generally, construction of a written contract is a question of law for which summary judgment is particularly appropriate. Hall-Hottel Co. v. Oxford Square Co-Op, Inc. (1983), Ind.App., 446 N.E.2d 25. Where no defect is claimed to have occurred during formation of the contract, its terms, if unambiguous, are conclusive on the question of the intentions of the parties. Underwriting Members of Lloyds of London v. United Home Life Ins. Co. (1990), Ind.App., 549 N.E.2d 67. Slutsky-Peltz and Traylor Bros. cite International Bhd. of Elec. Workers, Local 1400 v. Citizens Gas & Coke Util. (1982), Ind.App., 428 N.E.2d 1320, for the proposition that trial courts may not extend arbitration agreements by construction or implication. We agree that trial courts may not extend such agreements. They may, however, determine the issues and the parties subject to arbitration pursuant to the plain meaning of the agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.
679 F.3d 643 (Seventh Circuit, 2012)
Vehicle Service Group, LLC v. Auto Equipment Co.
838 F. Supp. 2d 842 (S.D. Indiana, 2011)
BMD Contractors, Inc. v. Fidelity & Deposit Co.
828 F. Supp. 2d 978 (S.D. Indiana, 2011)
In Re United Pub. Workers, Afscme, Loc. 646
244 P.3d 609 (Hawaii Intermediate Court of Appeals, 2010)
Campbell v. Spade
617 N.E.2d 580 (Indiana Court of Appeals, 1993)
Fetz v. Phillips
591 N.E.2d 644 (Indiana Court of Appeals, 1992)
Whiteco Industries, Inc. v. Nickolick
571 N.E.2d 1337 (Indiana Court of Appeals, 1991)
Freiburger v. Bishop Dwenger High School
569 N.E.2d 755 (Indiana Court of Appeals, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
556 N.E.2d 344, 1990 Ind. App. LEXIS 838, 1990 WL 100849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slutsky-peltz-plumbing-heating-co-v-vincennes-community-school-corp-indctapp-1990.