Preferred Equities Corp. v. State Engineer

75 P.3d 380, 119 Nev. 384, 119 Nev. Adv. Rep. 44, 2003 Nev. LEXIS 53
CourtNevada Supreme Court
DecidedAugust 29, 2003
DocketNo. 38037
StatusPublished
Cited by4 cases

This text of 75 P.3d 380 (Preferred Equities Corp. v. State Engineer) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Preferred Equities Corp. v. State Engineer, 75 P.3d 380, 119 Nev. 384, 119 Nev. Adv. Rep. 44, 2003 Nev. LEXIS 53 (Neb. 2003).

Opinion

OPINION1

Per Curiam:

This is an appeal from a district court order denying a petition for judicial review of State Engineer Ruling No. 4499,2 which rejected appellant Preferred Equities Corporation’s (PEC) application to change the diversion point and usage of certain water rights it held in Nye County, Nevada. We affirm the district court’s order denying PEC’s petition for judicial review. Although the district court improperly ruled that it lacked subject matter jurisdiction to hear PEC’s appeal of Ruling No. 4499, we conclude that the district court properly denied relief on mootness grounds.

FACTUAL AND PROCEDURAL BACKGROUND

This appeal concerns Nevada State Engineer Ruling No. 4499, referred to above, and a prior State Engineer Ruling, No. 4481, both made in connection with the same water rights.

In 1988, PEC filed an application with the Nevada State Engineer to change the diversion point and usage of the water rights in question here. For reasons that are not entirely clear, the State Engineer did not immediately act on that application and, in 1992, [386]*386commenced separate forfeiture proceedings on the same water rights. In Ruling No. 4481, dated December 20, 1996, the State Engineer concluded that PEC did not utilize the subject water rights for a period exceeding five years, and thus, he declared the rights in forfeit. PEC chose not to appeal this ruling. Thereafter, on February 25, 1997, the State Engineer issued Ruling No. 4499, denying the 1988 application to change the point of diversion and the usage of the rights that were declared forfeited in Ruling No. 4481.

In May of 1997, PEC filed a petition for judicial review of Ruling No. 4499 in the district court. The State Engineer moved to dismiss the petition with respect to Ruling No. 4499.3 In his motion, the State Engineer argued that PEC’s failure to appeal Ruling No. 4481 within thirty days4 rendered that ruling final and that, accordingly, PEC’s appeal of Ruling No. 4499 was an impermissible attempt to review the finally adjudicated forfeiture stemming from Ruling No. 4481. The State Engineer also argued that the denial of PEC’s application to change the point of diversion and usage was correct on substantive grounds because PEC failed to make beneficial use of the water rights during the prescriptive time period. The district court agreed with the State Engineer and dismissed PEC’s petition in connection with Ruling No. 4499. PEC appeals.

DISCUSSION

The State Engineer’s Ruling No. 4481 became final thirty days after it was rendered, and PEC elected not to appeal that determination.5 PEC does not contest the finality of Ruling No. 4481, or that it failed to make beneficial use of its water for a period of at least five years. Instead, PEC seeks an independent review of the diversion and usage decision, claiming on statutory and equitable grounds that the diversion and usage application tolled the running of the five-year divestiture time period.

[387]*387 Mootness

The State Engineer contends that PEC is barred from bringing the petition in connection with Ruling No. 4499.6 We agree.

To explain, under NRS 534.090(1), PEC’s water rights reverted to the public once the State Engineer determined them forfeited in 1996, and the forfeiture became final upon PEC’s failure to appeal that ruling within thirty days.7 This reversion became final during the intervening period between PEC’s application to change the diversion point of its water rights in 1988 and the final determination denying that application in 1997. Thus, after Ruling No. 4481 became final, PEC’s application to change the diversion point no longer dealt with a water right that it owned. Consequently, PEC’s application became moot,8 and the district court properly denied the application to modify finally forfeited water rights.

The claim of tolling under NRS 533.040(2)

PEC argues that an application to change the place and manner of use of water rights tolled the forfeiture period by implication under NRS 533.040(2):

If at any time it is impracticable to use water beneficially or economically at the place to which it is appurtenant, the right may be severed from the place of use and be simultaneously transferred and become appurtenant to another place of use, in the manner provided in this chapter, without losing priority of right.

PEC contends that, if it could not make beneficial use of the water in one location, it would be wasteful to require continuing use of the water while awaiting a decision of the State Engineer. While PEC’s argument is compelling, it does not overcome the [388]*388overriding public policy that any failure of beneficial use for five years results in forfeiture and does not address the failure to appeal Ruling No. 4481 within the thirty-day window.

PEC does not contend that it made beneficial use of its water; that was the reason why it applied to change the diversion point of its rights. However, if PEC could not make use of its water, the proper process was to request an extension under NRS 534.090(2),9 or to file a timely appeal after issuance of Ruling No. 4481, arguing that the application tolled the forfeiture proceedings. We therefore reject PEC’s interpretation of NRS 533.040(2).

Equitable relief

PEC requests that this court grant it equitable relief from the forfeiture. However, PEC’s reliance on cases in which we granted such relief is misplaced.

As previously noted, NRS 533.450(1) allows a person aggrieved by a decision or order of the State Engineer to appeal within thirty days “following the rendition of the order or decision in question.” This court strictly construes statutes dealing with mandatory filing dates in water rights actions,10 and “[i]t is . . . settled in this state that the water law and all proceedings thereunder are special in character, and the provisions of such law not only lay down the method of procedure but strictly limit[ ] [the method] to that provided.”11

[389]*389This case is dissimilar from the few water rights cases in which this court has granted equitable relief from the termination of water rights, notwithstanding the failure of a water rights holder to timely file an appeal from the State Engineer’s termination decision.12 In those cases, the water rights holders were able to demonstrate beneficial use of their rights within the prescriptive period.13

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STATE ENGINEER VS. HAPPY CREEK, INC.
2019 NV 41 (Nevada Supreme Court, 2019)
Palomino Dev. v. King, P.E.
Nevada Supreme Court, 2013

Cite This Page — Counsel Stack

Bluebook (online)
75 P.3d 380, 119 Nev. 384, 119 Nev. Adv. Rep. 44, 2003 Nev. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/preferred-equities-corp-v-state-engineer-nev-2003.