Procedural entryThis page is a short order in Precision Asset Management Corp. v. United States. Read the opinion of the Court — 125 Fed. Cl. 228
United States Court of Federal Claims·Decided August 16, 2016·No. 16-261 C, 16-442 C·Published

Opinion

Post-Award Bid Protest; Subject Matter Jurisdiction; Standing; Economic Interest; Substantial Chance.

OPINION

Merow, Senior Judge

On February 24, 2016, Precision Asset Management Corporation (“Precision”) filed a bid protest challenging the Department of Housing and Urban Development’s (“HUD”) award of a property management contract to Alpine-First Preston JV II, LLC (“Alpine”). See Doe. 1. Shortly thereafter, on April 7, 2016, Q Integrated Companies, LLC (“Q Integrated”) filed a similar protest challenging the same award. See Case No. l:16-cv-442, Doe. 1. Alpine has intervened in both cases. At the request of the parties, and because the issues are sufficiently related, the court consolidated the two cases. See Doc. 81. 2

The government and Alpine have each filed a motion to dismiss the two complaints for lack of jurisdiction, claiming that neither Precision nor Q Integrated have the requisite standing to challenge HUD’s award decision. See Does. 36, 87. In addition, Precision and Alpine have each filed a motion to supplement the administrative record. See Docs. 41, 47.

I. BACKGROUND AND RELEVANT FACTS 3

The Federal Housing Authority (“FHA”), which is part of HUD, “administers the single-family mortgage insurance program.” See Doe. 36 at 9. When a homeowner defaults on an FHA-insured loan, many times, HUD ultimately acquires title to the property. See id. at 10. HUD outsources the management of these properties, contracting with various outfits for asset management services. Asset management includes services related to the marketing and sale of the properties HUD has acquired. See id.

A. The Solicitation

On July 26, 2014, HUD issued Solicitation No. DU204SA-13-R-0005 (the “solicitation”), requesting proposals for asset management services in twelve geographic areas. See AR at 44-1062.127 (original solicitation and subsequent modifications). The area at issue in this action, Area 3A, involves property in Illinois. See Doc. 36 at 9. Once the government received the requested proposals, the evaluation process involved two steps. First, HUD determined whether each proposal was technically acceptable, on a pass/fail basis. See AR at1054.

Those proposals that were deemed technically acceptable, were then evaluated with the goal of determining which was the best value to HUD. See id This analysis considered past performance and price, assigning approximately the same relative importance to each. See id. In order to determine the strength of a bidder’s past performance, the technical evaluation panel (“TEP”) analyzed the recency, relevancy, and quality of that performance, along with the panel’s confi *93 dence in the bidder’s ability to perform under the contract. See AR at 1057.

The TEP assigned each proposal one of five adjectival ratings for confidence and quality of past performance: excellent/high confidence, good/significant confidence, fair/ some confidence, no confidence, and neutral/unknown confidence. See AR at 1060-1061. In coming to these determinations, the TEP was to evaluate the three most recent, relevant references provided by the bidder. See AR at 1047. In place of the three most recent, relevant references, a bidder was also permitted to request that the TEP consider efforts with which certain key personnel had been involved. See AR at 1049.

B. Precision’s Proposal

Precision submitted its initial proposal for all twelve geographic areas on September 23, 2014. See AR at 2071-2340. For Area 3A, the only area at issue in this protest, Precision proposed a cost of $[...]. See AR 2329. The initial proposal included six contract references based on which HUD was to make its past performance evaluation. See AR at 2266-2277.

By letter, dated August 27, 2015, HUD notified Precision that it had established a competitive range and was initiating discussions, See AR at 3757. The letter also stated that the TEP found plaintiffs proposal to be “Technically Acceptable.” See id In an attachment enclosed with the letter, HUD noted that it had identified “[n]o weaknesses or deficiencies” in Precision’s proposal, and that it had “[n]o adverse past performance information.” AR at 3719. The only substantive note on the attachment was that while plaintiffs price was “deemed reasonable,” it was “either the highest or higher than the overall mean,” when compared to other proposals. Id.

HUD revised the solicitation several times, and plaintiff submitted its revised proposal on September 9, 2015. See AR at 3854-3885. Its revised proposal included “updated Past Performance Information and revised pricing.” Doc. 1 at 9. In its revised proposal, Precision idéntifíed three past performance efforts for evaluation: XXXXXXXXX XXXXXX XXXXXX XXXXXX. See AR at 3854-62. In its evaluation, the TEP looked at the XXXXXXX XXXXX XXXX XXXX efforts, but instead of considering the XXXXXXXX, it considered the XXXXXXXXXX, one of the references identified in Precision’s initial proposal. See AR at 4101. After conducting its past performance evaluation, HUD assigned plaintiffs proposal a “Neutral/Unknown Confidence” rating. See AR at 4277, Precision’s final proposed cost was $[...]. See AR at 4296.

C. Q Integrated’s Proposal

As Precision did, Q Integrated submitted its initial proposal for Area 3A on September 23, 2014. See AR at 1367-1678. In the proposal, Q Integrated stated that it would perform the contract in partnership with XXXXXXXX XXXX XXXXXX XXXXXX. See AR at 1389-1409. Specifically, Q Integrated proposed that XXXXXXXXX would serve as its subcontractor and would perform a maximum of 49 percent of the contract work. See AR at 1389,1399.

For its past performance evaluation, Q Integrated submitted a list of its own clients and XXXXXXXclients, along with identifying three specific efforts for the TEP to review. All three efforts were projects on which Q Integrated served as a subcontractor to XXXXXX, performing 20 percent of the work on the prime contracts. See AR at 1656-61.

HUD notified Q Integrated that it had established a competitive range and was initiating discussions by letter dated August 27, 2015. See AR at 3739. The letter stated that the TEP found Q Integrated’s proposal to be “Technically Acceptable.” See id. On the attachment included with the letter, the TEP noted “[n]o adverse past performance information,” and that Q Integrated’s price was “lower than the overall mean.” See AR at .3711.

Free access — add to your briefcase to read the full text and ask questions with AI

Precision Asset Management Corp. v. United States, 128 Fed. Cl. 90, 2016 WL 4530640 (uscfc 2016).

128 Fed. Cl. 90 (Precision Asset Management Corp. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Camp v. Pitts
411 U.S. 138 (Supreme Court, 1973)
Weeks Marine, Inc. v. United States
575 F.3d 1352 (Federal Circuit, 2009)
Rex Service Corp. v. United States
448 F.3d 1305 (Federal Circuit, 2006)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)
Donald A. Henke v. United States
60 F.3d 795 (Federal Circuit, 1995)
Bannum, Inc. v. United States
404 F.3d 1346 (Federal Circuit, 2005)
Brandt v. United States
710 F.3d 1369 (Federal Circuit, 2013)
Science and Management Resources, Inc. v. United States
117 Fed. Cl. 54 (Federal Claims, 2014)