Portland Natural Gas Transmission System v. 19.2 Acres of Land

318 F.3d 279, 158 Oil & Gas Rep. 393, 2003 U.S. App. LEXIS 1682, 2003 WL 203472
CourtCourt of Appeals for the First Circuit
DecidedJanuary 31, 2003
Docket02-1369
StatusPublished
Cited by11 cases

This text of 318 F.3d 279 (Portland Natural Gas Transmission System v. 19.2 Acres of Land) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Portland Natural Gas Transmission System v. 19.2 Acres of Land, 318 F.3d 279, 158 Oil & Gas Rep. 393, 2003 U.S. App. LEXIS 1682, 2003 WL 203472 (1st Cir. 2003).

Opinion

TORRUELLA, Circuit Judge.

The Fifth Amendment permits the federal government to take personal property for public use, but requires payment of “just compensation.” Plaintiffs-appellants, Portland Natural Gas Transmission System and Maritimes & Northeast Pipeline, L.L.C. (“the Pipeline Companies”), took by eminent domain temporary and permanent easements on land in Haverhill, Massachusetts owned by defendant-appellee, WBC Extrusion Products, Inc. (“WBC”), to construct, operate and maintain a pipeline as permitted by the Natural Gas Act, 15 U.S.C. § 717f(h). A bench trial was held in the United States District Court for the District of Massachusetts to determine the amount of compensation due. The court determined that WBC was entitled to $152,677 plus interest. The Pipeline Companies appeal, claiming that the amount is not justified by the evidence produced at trial. We affirm.

I.Background

The facts of this dispute are detailed in the district court’s opinion, Portland Natural Gas Transmission Sys. v. 19.2 Acres of Land, 195 F.Supp.2d 314, 316-19 (D.Mass.2002), and we repeat only those necessary to our decision. At the time of the taking, WBC owned two parcels totaling approximately seventy-six acres. Parcel 1 was divided into eight lots to be used for an industrial park; Parcel 2 was a non-builda-ble vacant lot. WBC occupied Lot 7 in Parcel 1, and the other seven were empty and for sale. The permanent gas pipeline easement is fifty feet wide and runs through Lots 1 and 8 on Parcel 1 and through Parcel 2, encumbering approximately 2.37 acres total. The temporary easement ran along a similar path, reaching approximately 2.10 acres total.

II.Standard of Review

We review the district court’s findings of facts, including the amount of compensation due, for clear error. Fed. R.Civ.P. 52(a); S. Nat. Gas Co. v. Land, Cullman County, 197 F.3d 1368, 1372 (11th Cir.1999) (“This court reviews the district court’s determination of just compensation for clear error.”); Puerto Rico Ports Auth. v. M/V Manhattan Prince, 897 F.2d 1, 3 (1st Cir.1990). Our job is not to weigh the evidence anew, but simply to determine whether the decision reached by the trial court is “plausible in light of the record viewed in its entirety.” Anderson v. City of Bessemer City, 470 U.S. 564, 574, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985). The fact that the ruling was substantially based on physical or documentary evidence, rather than credibility determinations, does not alter our deferential analysis. Id. Any rulings of law are subject to de novo review. United States v. Mass. Water Res. Auth., 256 F.3d 36, 47 (1st Cir.2001).

As this case is fact intensive, we note that the appellant has a difficult task of overcoming the trial court’s findings. Determining the value of real estate is not a science, and the decision of a lower tribunal is ordinarily not disturbed unless “grossly inadequate or excessive.” 4A Julius L. Sackman, Nichols on Eminent Domain § 17.1[4], 23.01 (rev.3d ed.2001) (hereinafter Nichols on Eminent Domain ).

III.Discussion

The land taken by the Pipeline Companies is in Massachusetts, and the *282 district court applied Massachusetts law to determine the just compensation to which WBC was entitled. As the parties do not contest this choice of law and there is no indication that it makes any difference as to any of the contested issues, we accept this premise without necessarily endorsing it. 1 Under Massachusetts law, just compensation is defined as

the value [of the land] before the recording of the order of taking, and in case only part of a parcel of land is taken there shall be included damages for all injury to the part not taken caused by the taking or by the public improvement for which the taking is made.

Mass. Gen. Laws ch. 79, § 12 (2002). Therefore, although the easement did not abrogate all of WBC’s bundle of rights, WBC is entitled to compensation for the decrease in value of the land encumbered by the easement as well as the decrease in value of the other land on the lots, or the “remaining land.” In addition, WBC is entitled to compensation for the temporary easement, or the two years when the Pipeline Companies were using part of WBC’s land for construction of the pipeline. The compensation awards for these three areas — the encumbered land, the remaining land, and the land temporarily taken — are the subject of this appeal.

A. Encumbered and Remaining Land

In 1998, the Pipeline Companies promulgated “Requirements for Construction On or Near Company Facilities” (the “Requirements”) to protect their pipelines from encroachment and disturbance caused by construction activity on or near the easement. WBC claimed that the easement together with the Requirements rendered the permanent easement area worthless. 2 The Pipeline Companies’ expert testified that the encumbered land was still useful and retained fifty percent of its value. The district court found that the Requirements diminished the value of the encumbered land beyond the Pipeline Companies’ suggestion of fifty percent. The court found that “a potential buyer who has read [the Requirements] would be likely to fear a substantial degree of infringement on the land encumbered by a permanent easement,” and determined that the encumbered land was reduced in value by seventy-five percent. Portland Natural Gas, 195 F.Supp.2d at 324. The court also determined that the Requirements reduced the value of the remaining land by ten percent because “[a] reasonable buyer, after reading the [Requirements], would almost certainly anticipate that building in the vicinity of the easement areas of Lots 1 and 8 would involve extra administrative ‘hassle,’ and possible extra construction expenditures.” Id. at 324. The Pipeline Companies argue that the diminution of the encumbered land is only fifty percent and that there is no diminution of the remaining land. The *283 Pipeline Companies claim that (1) the damages theory employed by the district court was not litigated and therefore constituted unfair surprise, and (2) there was no evidence that the Requirements diminished the value of the encumbered or remaining land.

1. Unfair Surprise

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paducah Independent School District v. Putnam & Sons, LLC
520 S.W.3d 367 (Kentucky Supreme Court, 2017)
Arkansas Game & Fish Commission v. United States
736 F.3d 1364 (Federal Circuit, 2013)
Powell v. Tosh
942 F. Supp. 2d 678 (W.D. Kentucky, 2013)
North Adams Apartments Ltd. Partnership v. City of North Adams
940 N.E.2d 494 (Massachusetts Appeals Court, 2011)
Russell v. City of New Bedford
910 N.E.2d 404 (Massachusetts Appeals Court, 2009)
Jensen v. City of New Albany
868 N.E.2d 525 (Indiana Court of Appeals, 2007)
Persson v. Scotia Prince Cruises, Ltd.
330 F.3d 28 (First Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
318 F.3d 279, 158 Oil & Gas Rep. 393, 2003 U.S. App. LEXIS 1682, 2003 WL 203472, Counsel Stack Legal Research, https://law.counselstack.com/opinion/portland-natural-gas-transmission-system-v-192-acres-of-land-ca1-2003.