Persson v. Scotia Prince Cruises, Ltd.

330 F.3d 28, 20 I.E.R. Cas. (BNA) 1507, 2003 U.S. App. LEXIS 10441, 2003 WL 21212546
CourtCourt of Appeals for the First Circuit
DecidedMay 27, 2003
Docket02-1590, 02-1591
StatusPublished
Cited by26 cases

This text of 330 F.3d 28 (Persson v. Scotia Prince Cruises, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Persson v. Scotia Prince Cruises, Ltd., 330 F.3d 28, 20 I.E.R. Cas. (BNA) 1507, 2003 U.S. App. LEXIS 10441, 2003 WL 21212546 (1st Cir. 2003).

Opinion

TORRUELLA, Circuit Judge.

Hartmut Rathje, Kenth Persson, and Rolf Sjostrom, (collectively, the “Officers”) were the captain, chief engineer, and chief engineer/consulting superintendent, respectively, of the M7S SCOTIA PRINCE. The SCOTIA PRINCE is a cargo and passenger ferry operated by Scotia Prince Cruises, Ltd. (“SPC”) between Portland, Maine and Yarmouth, Nova Scotia. Claiming they were fired in April 2001, the Officers brought suit under the federal court’s admiralty jurisdiction against SPC for breach of their employment contracts. SPC raised as a defense that the Officers had resigned and counterclaimed, alleging that the Officers had breached a fiduciary duty by failing to maintain the vessel.

A bench trial was held by consent before a magistrate judge, who held that (a) Rathje and Persson resigned without giving prior notice pursuant to their employment contracts and therefore were not entitled to wages following their departure from the vessel; (b) SPC terminated Sjds-trom’s employment as consulting superintendent (though not as chief engineer) without permitting him to work his “notice period” of nine months and therefore owed Sjostrom nine months of superintendent pay; and (c) the Officers were not liable to SPC for any negligent maintenance of the vessel. All issues are appealed: Rathje and Persson appeal the decision that they are not entitled to wages and vacation pay; SPC appeals the decision that it is liable to Sjostrom for damages and that its former employees are not liable for damage to the ship. After reviewing the record, we affirm.

I. Background Facts

We recount only the facts relevant to our decision; a more complete description of the facts can be found in the district court’s opinion. See Rathje v. Scotia Prince Cruises, Ltd., 2002 WL 389303 at *1-12, No. 01-123-P-DMC, 2002 U.S. Dist. LEXIS 4078, at *5-38 (D.Me. Mar. 13, 2002).

The Officers began working aboard the M/S SCOTIA PRINCE in the late 1980s. Each Officer had an employment contract with Prince of Fundy Cruises, Ltd. (“POF”), SPC’s predecessor. Notice time for termination under Rathje’s employment contract was three months; under Persson’s contract, sixty days notice was required. Sjostrom’s contract stated: “[Nine] months notice of termination required by both parties.” Sjostrom worked in Sweden; POF contracted first with the Swedish company Marine Trading and then with Plus 2 Ferryeonsultation AB (“Plus 2”) to pay Sjostrom’s salary in Swedish kronas.

At the beginning of the 2001 season, SPC’s Chairman, Matthew Hudson, met with the Officers and advised them that he was contemplating the engagement of International Shipping Partners, Inc. (“ISP”), a manning/purchasing contractor. Although several top managers had been fired, Hudson assured the Officers that this would not affect their contracts, which were “ring-fenced.” 1 Hudson also stated that the employees who had been terminated would receive a severance package *31 of one week’s pay for each year of service with the company.

Hudson engaged ISP the next morning, April 5, 2001, to take over the complete management of the vessel. ISP met with the Officers and presented a budget showing Rathje and Persson to be receiving significantly less compensation than provided in their current contracts, and Sjos-trom to be receiving no compensation at all as superintendent (because ISP assumed those duties). The Officers were upset, and the meeting ended with the Officers telling ISP, “Basically it’s either you or us.”

Over the course of the next few days, several email messages and facsimiles were sent between the Officers and Hudson. In their first message, the Officers wrote:

As it stand[s] now, we see only two options. We stick to the agreement you presented last night, i.e. ISP serves as a manning agency only and the current contracts and conditions are maintained, possible new conditions only applying to new hires. Alternatively, if ISP takes over both complete manning and technical management, we ([Rathje and Pers-son] ) accept the standard severance package (one week for every year of service) and [Sjostrom] gives the 9-month notice in accordance with his contract.

When Hudson responded that their contracts were “ring-fenced,” the Officers asked Hudson to focus on the statement beginning “As it stands now ...” so they could “concentrate on [their] jobs or go home.” In response, Hudson stated, “I consider that the [Officers] have effectively resigned and I accept those resignations on behalf of [SPC].”

The Officers’ last day was April 20; Rathje and Persson acknowledge payment in full up to that date and Sjostrom acknowledges payment in full to April 30. They filed this lawsuit seeking payment for the termination periods provided for in their contracts.

After the Officers were replaced, SPC discovered various problems with the upkeep of the ship including damage to the wood. SPC alleged that the Officers were responsible, and cross-claimed for more than one million dollars. The bench trial was held on February 11-15, 2002, and a decision was issued on March 13, 2002. This appeal followed.

II. Standard of Review

We review the district court’s legal conclusions de novo. Watson v. Deaconess Waltham Hosp., 298 F.3d 102, 108 (1st Cir.2002). We review factual determinations for clear error. Fed.R.Civ.P. 52(a) (2003). Our job is to determine whether the decision below is reasonable in light of the entire record. See Portland Natural Gas Transmission Sys. v. 19.2 Acres of Land, 318 F.3d 279, 281 (1st Cir.2003). We give great respect to the district court’s “opportunity to hear the testimony, observe the witnesses’ demeanor, and evaluate the facts at first hand,” United States v. Nee, 261 F.3d 79, 84 (1st Cir.2001) (internal quotation omitted), and defer to the trial court’s findings unless “we form a strong, unyielding belief that a mistake has been made.” Windsor Mount Joy Mut. Ins. Co. v. Giragosian, 57 F.3d 50, 53 (1st Cir.1995) (internal quotation omitted). Even then, we may affirm the judgment on any grounds revealed by the record. United States v. Puerto Rico, 287 F.3d 212, 218 (1st Cir.2002).

III. Discussion

We have jurisdiction over this dispute, which arises out of employment contracts aboard a vessel. See U.S. Const. *32 Art. III, § 2; 28 U.S.C. § 1383(2003); 7A J.W. Moore, Moore’s Federal Practice § 0.225, at 2701, § 0.230, at 2783 (2d ed.1996) (hereinafter

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Isabella v. Town of Seekonk
D. Massachusetts, 2024
McClain v. Cape Air
D. Massachusetts, 2023
(PC) McMillan v. Delgado
E.D. California, 2021
Fernandez v. UBS AG
222 F. Supp. 3d 358 (S.D. New York, 2016)
Aragao v. Mortgage Electronic Registration Systems, Inc.
22 F. Supp. 3d 133 (D. Massachusetts, 2014)
Blake v. Professional Coin Grading Service
898 F. Supp. 2d 365 (D. Massachusetts, 2012)
LOMBARD MEDICAL TECHNOLOGIES, INC. v. Johannessen
729 F. Supp. 2d 432 (D. Massachusetts, 2010)
Watkins v. OMNI LIFE SCIENCE, INC.
692 F. Supp. 2d 170 (D. Massachusetts, 2010)
In Re the Complaint of Martin
596 F. Supp. 2d 142 (D. Massachusetts, 2009)
Commonwealth of PR v. United States
490 F.3d 50 (First Circuit, 2007)
Pearce v. Duchesneau Group, Inc.
392 F. Supp. 2d 63 (D. Massachusetts, 2005)
Rational Software v. Sterling Corporation
393 F.3d 276 (First Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
330 F.3d 28, 20 I.E.R. Cas. (BNA) 1507, 2003 U.S. App. LEXIS 10441, 2003 WL 21212546, Counsel Stack Legal Research, https://law.counselstack.com/opinion/persson-v-scotia-prince-cruises-ltd-ca1-2003.