Porter v. Saez, Unpublished Decision (5-4-2004)

2004 Ohio 2498
CourtOhio Court of Appeals
DecidedMay 4, 2004
DocketCase No. 03AP-1026.
StatusUnpublished
Cited by7 cases

This text of 2004 Ohio 2498 (Porter v. Saez, Unpublished Decision (5-4-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Porter v. Saez, Unpublished Decision (5-4-2004), 2004 Ohio 2498 (Ohio Ct. App. 2004).

Opinion

OPINION
{¶ 1} Plaintiff-appellant, Mary Carolyn Porter, appeals from a judgment of the Franklin County Court of Common Pleas that (1) granted summary judgment in favor of defendant-appellee, Heather Reed, and (2) dismissed Porter's motion for partial summary judgment against defendants-appellees, Aaron M. Saez and Heather Reed, pertaining to Porter's claims of fraudulent transfer and civil conspiracy. For the following reasons, we affirm.

{¶ 2} According to Porter, on or about June 2, 1999, Aaron Saez dba 3R Contracting Services, presented Porter with a proposal concerning the construction of a garage on Porter's property. According to the proposal, the cost for the project was $13,800 with payment to be made in three installments of $4,600. Prior to accepting the proposal, Porter purportedly asked Saez if he was a licensed contractor and if he was bonded. Saez purportedly assured Porter that he was a licensed contractor. Upon Porter's acceptance of the proposal, Saez allegedly informed Porter that construction would begin the week of June 7, 1999. However, according to Porter, construction of the project actually began the first week of July 1999, not the week of June 7, 1999, as Saez earlier had represented.

{¶ 3} According to Porter, Saez asked for a $1,000 advance to cover initial material costs and the cost of a construction permit. Porter paid the requested advance to Saez. On June 28, 1999, Porter also paid $3,600 to Saez and, on July 3, 1999, Porter paid $4,600 to Saez.

{¶ 4} According to Porter, in early July 1999, Saez installed footers and framed the garage; however, little work was completed during the remainder of July 1999. During the weekend of July 31, 1999, Porter purportedly discovered that the actual size of the garage was smaller than what was provided for in the garage specifications.

{¶ 5} On or about August 1, 1999, Saez allegedly assured Porter that construction would be completed within approximately ten days. During the week of August 2, 1999, siding and roofing were installed. However, according to Porter, as of August 12, 1999, no electrical work had been completed, no concrete floor or apron had been installed, and the main door and back door had not been installed.

{¶ 6} During the following weeks, Porter purportedly attempted several times to contact Saez. On August 25, 1999, Saez allegedly contacted Porter and informed her that he needed $2,000 to finish the construction project. According to Porter, Saez also informed her that if she did not pay the requested $2,000, she would be in breach of contract.

{¶ 7} Rather than pay $2,000 directly to Saez, Porter purportedly offered to directly pay Saez's subcontractors and requested an itemization of how the $2,000 should be allocated. Saez allegedly never responded to the offer.

{¶ 8} In a letter dated September 7, 1999, that was sent to Saez via certified mail, Porter outlined aspects of the project that were nonconforming with the project's specifications and informed Saez that their contract was terminated. Saez allegedly refused to accept service of the letter.

{¶ 9} Subsequently, Porter retained the services of other contractors to complete the construction of the garage at additional cost to her. After Porter retained the services of other contractors, she discovered that the location of the garage's foundation, which purportedly had been installed by Saez, violated a city ordinance due to its proximity to the property line. Porter retained an attorney to assist with a petition for a variance.

{¶ 10} The variance was later granted. However, as a condition of granting the variance, Porter was required to record a maintenance easement with a neighbor. As a consequence of her efforts to secure a variance, Porter incurred $1,363 in costs and fees.

{¶ 11} For his part, Saez, who is self-employed as a landlord and handyman, admits that he agreed to build the garage for Porter. According to Saez, Porter, who was a social acquaintance of Saez, approached him at a coffee shop and asked if he would build a garage for her. Prior to contracting with Porter, Saez allegedly had never constructed a garage nor had Saez allegedly advertised that he built garages. Saez denies he has a construction business of any kind and he admits that he does not have a professional builder's license.

{¶ 12} According to Saez, at the time he agreed to build the garage, he believed he could construct the garage with the assistance of Edward Elford,1 a general contractor, who purportedly had represented to Saez that he had the necessary license and experience to construct a garage.

{¶ 13} Saez claims Elford agreed to apply for the permit and, accordingly, Saez gave Elford money to apply for the permit and to purchase building supplies. Later, however, Saez learned that Elford only possessed a general contractor's license and lacked a home improvement contractor's license. Moreover, according to Saez, Elford began the construction project without the required permit.2

{¶ 14} According to Saez, Elford drew the plans for the garage, dug the footer, measured the lot, measured the placement of the footers, hired masons, built the walls, and built half of the roof tresses.

{¶ 15} At some point, Elford left the project and failed to respond to Saez's request to return to the construction site. Saez concedes that certain work was not completed, such as hanging the back door and pouring the concrete floor. However, contrary to Porter's claim, Saez asserts Porter and he never agreed to equip the garage with electricity.

{¶ 16} On June 28, 2001, Porter filed a complaint in the Franklin County Court of Common Pleas against Saez wherein Porter alleged: (1) Saez breached the contract with Porter; (2) Saez intentionally misrepresented himself to be a licensed contractor and intentionally misrepresented that he would obtain a building permit; (3) Saez violated R.C. Chapter 1345, the Ohio Consumer Sales Practices Act; and (4) Saez acted in bad faith.3

{¶ 17} During the course of litigation, several discovery problems arose, some of which resulted in sanctions against Saez, Saez's girlfriend, Heather Reed, with whom Saez resides, and another person and entity.

{¶ 18} On September 4, 2001, Porter moved for a default judgment as to liability and for a hearing to consider the issue of damages. On September 19, 2001, the trial court rendered a default judgment in Porter's favor as to liability and ordered a hearing to consider the issue of damages.

{¶ 19} On December 11, 2001, the trial court, through a magistrate, conducted a hearing to determine damages. That same day, claiming excusable neglect, Saez moved for relief from judgment and for a stay of the proceedings.

{¶ 20} On December 17, 2001, the trial court, through a magistrate, concluded that both treble damages and attorney fees were warranted based upon Saez's conduct. However, the magistrate did not make a determination concerning the amount of attorney fees and recommended another hearing to consider that issue. Saez did not object to the magistrate's decision.

{¶ 21}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Open Container, Ltd. v. CB Richard Ellis, Inc.
2015 Ohio 85 (Ohio Court of Appeals, 2015)
West-Kimmons v. Univ. of Toledo Med. Ctr.
2013 Ohio 5931 (Ohio Court of Claims, 2013)
Merchants Natl. Bank v. Overstake
2012 Ohio 6309 (Ohio Court of Appeals, 2012)
Horsley v. Burton
2010 Ohio 6315 (Ohio Court of Appeals, 2010)
Mosley v. Miami Shores of Moraine, 21587 (5-4-2007)
2007 Ohio 2138 (Ohio Court of Appeals, 2007)
Porter v. Saez, Unpublished Decision (6-24-2004)
2004 Ohio 3322 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 2498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/porter-v-saez-unpublished-decision-5-4-2004-ohioctapp-2004.